xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

Article 2

SCHEDULE 1E+WAUTHORISED PROJECT

PART 1E+WAUTHORISED DEVELOPMENT

1.  A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act which is located in the North Sea approximately 121 kilometres to the northeast of the north Norfolk coast and approximately 10 kilometres west of the median line between UK and Netherlands waters, comprising—E+W

Work No. 1—

(a)an offshore wind turbine generating station with a gross electrical output of over 100 megawatts comprising up to 231 wind turbine generators each fixed to the seabed by either monopile foundation, mono suction bucket foundation, jacket foundation or gravity base foundation;

(b)up to three offshore accommodation platforms fixed to the seabed within the area shown on the works plan by monopile foundation, mono suction bucket foundation, jacket foundation, or gravity base foundation and which may be connected to each other or one of the offshore substations within Work No. 2 by an unsupported bridge; and

(c)a network of cables between the wind turbine generators and between the wind turbine generators and Work No. 2 including one or more cable crossings;

and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—

Work No. 2—

(a)up to 12 offshore type 1 substations each fixed to the seabed by either monopile foundation, mono suction bucket foundation, jacket foundation, gravity base foundation or box-type gravity base foundations and which may be connected to each other or one of the offshore accommodation platforms within Work No.1(b) by an unsupported bridge;

(b)up to four offshore type 2 substations each fixed to the seabed by either monopile foundations, mono suction bucket foundations, jacket foundations, gravity base foundations, jacket foundations, box-type gravity base foundations, pontoon gravity base 1 foundations, or pontoon gravity base 2 foundations and which may be connected to each other or one of the offshore accommodation platforms within Work No.1(b) by an unsupported bridge;

(c)a network of cables;

(d)up to six cable circuits between Work No. 2 and Work No. 3, and between Work No. 3 and Work No.5 consisting of offshore export cables along routes within the Order limits seaward of MLWS including one or more cable crossings; and

(e)up to eight temporary horizontal directional drilling exit pits;

Work No. 3—

(a)in the event that the mode of transmission is HVAC, up to four offshore HVAC booster stations fixed to the seabed within the area shown on the works plan by either monopile foundation, mono suction bucket foundation, jacket foundation, gravity base foundation, or box-type gravity base foundations;

(b)in the event that the mode of transmission is HVAC, up to six offshore subsea HVAC booster stations fixed to the seabed by either monopile foundation, mono suction bucket foundation, jacket foundation, gravity base foundation, or box-type gravity base foundations;

(c)in the event that the mode of transmission is HVAC, a network of cables between HVAC booster stations or offshore subsea HVAC booster stations; and

(d)in the event that the mode of transmission is HVAC, up to six cable circuits between Work No. 2 and Work No. 3, and between Work No. 3 and Work No.5 consisting of offshore export cables along routes within the Order limits seaward of MHWS including one or more cable crossings;

Work No. 4— a temporary work area associated with Work No.2 and Work No.3 for vessels to carry out intrusive activities alongside Work No.2 or Work No.3;

Work No. 5— landfall connection works comprising up to six cable circuits and ducts and onshore construction works within the Order limits seaward of MHWS and landward of MLWS;

Commencement Information

I1Sch. 1 Pt. 1 para. 1 in force at 22.1.2021, see art. 1

In the county of Norfolk, districts of North Norfolk, Broadland and South NorfolkE+W

Work No. 6— onshore connection works consisting of up to six cable circuits, ducts and between Work No. 5 and Work No. 7 landward of MHWS and onshore construction works;

Work No.7— onshore connection works consisting of—

(a)up to six cable circuits and associated electrical circuit ducts between Work No. 6 [F1and] Work No. 8;

(b)onshore construction works;

(c)up to six transition joint bays; and

(d)horizontal directional drilling launch pits;

Work No. 8— onshore connection works consisting of—

(a)up to six cable circuits and associated electrical circuit ducts to Work No. 11;

(b)onshore construction works;

(c)up to 440 link boxes; and

(d)up to 440 joint bays;

Work No. 9— onshore connection works consisting of the construction of an onshore HVAC booster station, together with onshore construction works;Work No. 10— onshore connection works consisting of an onshore HVDC/HVAC substation, including up to six cable circuits and electrical circuit ducts, and onshore construction works;Work No. 11— onshore connection works consisting of up to six cable circuits and electrical circuit ducts between Work No. 10 and Work No. 12 and onshore construction works;Work No. 12— onshore connection works consisting of up to six cable circuits and electrical circuit ducts between Work No. 11 and the Norwich Main National Grid substation, including a connection above ground and electrical engineering works within or around the National Grid substation buildings and compound, and onshore construction works;Work No. 13— a construction compound to support the construction of Work Nos. 8, 9, 10, 11, 12, 14 and 15;Work No. 14— temporary vehicular access tracks to serve Work Nos. 7, 8, 9, 10, 11, 12, 13 and 15; andWork No. 15— temporary storage areas to assist with the onshore connection works.

In connection with such Work Nos. 1 to 5 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and which fall within the scope of the work assessed by the environmental statement, including—

(a)scour protection around the foundations of the offshore structures;

(b)cable protection measures such as the placement of rock and/or concrete mattresses, with or without frond devices;

(c)the removal of material from the seabed required for the construction of Work Nos. 1 to 5 and the disposal of up to 3,563,133 cubic metres of inert material of natural origin within the Order limits produced during construction drilling, seabed preparation for foundation works, cable installation preparation such as sandwave clearance, boulder clearance and pre-trenching and excavation of horizontal directional drilling exit pits; and

(d)removal of static fishing equipment;

and in connection with such Work Nos. 6 to 15 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and which fall within the scope of the work assessed by the environmental statement, including—

(a)ramps, means of access and footpaths;

(b)bunds, embankments, swales, landscaping, fencing and boundary treatments;

(c)habitat creation;

(d)jointing bays, link boxes, cable ducts, cable protection, joint protection, manholes, marker posts, underground cable marker, tiles and tape, and lighting and other works associated with cable laying;

(e)works for the provision of apparatus including cabling, water and electricity supply works, foul drainage provision, surface water management systems and culverting;

(f)works to alter the position of apparatus, including mains, sewers, drains and cables;

(g)works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;

(h)landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised project;

(i)works for the benefit or protection of land affected by the authorised project;

(j)working sites in connection with the construction of the authorised project, construction lay down areas and compounds, storage compounds and their restoration.

2.  The grid coordinates for that part of the authorised project which is seaward of MHWS are specified below—E+W

Point IDLatitude (DMS)Longitude (DMS)Point IDLatitude (DMS)Longitude (DMS)
152° 57′ 23.299″ N1° 5′ 48.611″ E6453° 45′ 27.296″ N2° 34′ 19.781″ E
252° 58′ 22.516″ N1° 4′ 22.810″ E6553° 45′ 17.155″ N2° 33′ 57.193″ E
352° 59′ 43.107″ N1° 3′ 16.300″ E6653° 44′ 25.151″ N2° 28′ 22.483″ E
453° 0′ 12.806″ N1° 3′ 4.176″ E6753° 43′ 43.437″ N2° 23′ 42.266″ E
553° 0′ 41.322″ N1° 3′ 5.626″ E6853° 43′ 38.549″ N2° 23′ 1.918″ E
653° 2′ 15.365″ N1° 3′ 25.796″ E6953° 40′ 30.736″ N2° 17′ 49.303″ E
753° 4′ 22.383″ N1° 5′ 4.618″ E7053° 37′ 10.969″ N2° 7′ 19.167″ E
853° 4′ 48.739″ N1° 5′ 38.118″ E7153° 37′ 2.480″ N2° 6′ 39.277″ E
953° 5′ 0.912″ N1° 6′ 53.813″ E7253° 36′ 20.389″ N2° 5′ 9.581″ E
1053° 4′ 56.963″ N1° 8′ 49.809″ E7353° 35′ 18.067″ N2° 5′ 0.546″ E
1153° 4′ 47.089″ N1° 10′ 20.278″ E7453° 34′ 58.529″ N2° 4′ 49.759″ E
1253° 4′ 50.116″ N1° 12′ 8.936″ E7553° 34′ 37.908″ N2° 4′ 16.626″ E
1353° 5′ 1.606″ N1° 14′ 7.325″ E7653° 32′ 54.718″ N2° 4′ 40.220″ E
1453° 5′ 2.192″ N1° 14′ 30.074″ E7753° 32′ 31.275″ N2° 4′ 37.727″ E
1553° 4′ 58.764″ N1° 14′ 55.483″ E7853° 31′ 59.257″ N2° 4′ 11.934″ E
1653° 4′ 32.854″ N1° 16′ 47.381″ E7953° 31′ 13.675″ N2° 3′ 20.449″ E
1753° 4′ 32.226″ N1° 19′ 19.524″ E8053° 30′ 18.703″ N2° 2′ 26.715″ E
1853° 4′ 54.358″ N1° 22′ 30.281″ E8153° 30′ 0.496″ N2° 1′ 55.943″ E
1953° 5′ 6.119″ N1° 25′ 0.302″ E8253° 29′ 53.014″ N2° 1′ 22.871″ E
2053° 5′ 7.887″ N1° 26′ 23.233″ E8353° 29′ 52.335″ N2° 0′ 47.588″ E
2153° 5′ 4.100″ N1° 27′ 30.916″ E8453° 28′ 18.157″ N1° 53′ 52.525″ E
2253° 5′ 52.998″ N1° 28′ 30.016″ E8553° 27′ 38.035″ N1° 51′ 19.593″ E
2353° 14′ 11.509″ N1° 41′ 28.704″ E8653° 27′ 25.643″ N1° 50′ 32.418″ E
2453° 14′ 27.431″ N1° 42′ 14.962″ E8753° 27′ 18.150″ N1° 50′ 31.601″ E
2553° 15′ 49.705″ N1° 44′ 10.074″ E8853° 26′ 16.707″ N1° 50′ 4.603″ E
2653° 16′ 25.597″ N1° 44′ 37.874″ E8953° 25′ 53.921″ N1° 50′ 10.016″ E
2753° 19′ 1.814″ N1° 45′ 50.556″ E9053° 25′ 34.502″ N1° 50′ 4.308″ E
2853° 22′ 33.955″ N1° 46′ 57.914″ E9153° 24′ 21.903″ N1° 49′ 42.825″ E
2953° 22′ 55.872″ N1° 46′ 55.918″ E9253° 24′ 2.505″ N1° 49′ 42.663″ E
3053° 23′ 22.176″ N1° 47′ 7.319″ E9353° 23′ 34.480″ N1° 49′ 32.287″ E
3153° 23′ 41.762″ N1° 47′ 5.727″ E9453° 23′ 14.095″ N1° 49′ 34.013″ E
3253° 24′ 11.270″ N1° 47′ 16.705″ E9553° 22′ 47.157″ N1° 49′ 22.581″ E
3353° 24′ 33.225″ N1° 47′ 17.703″ E9653° 22′ 23.714″ N1° 49′ 23.370″ E
3453° 25′ 56.028″ N1° 47′ 42.459″ E9753° 18′ 42.217″ N1° 48′ 12.788″ E
3553° 26′ 20.933″ N1° 47′ 36.143″ E9853° 15′ 55.220″ N1° 46′ 54.772″ E
3653° 26′ 43.765″ N1° 47′ 45.420″ E9953° 15′ 3.154″ N1° 46′ 14.109″ E
3753° 27′ 30.131″ N1° 48′ 5.945″ E10053° 13′ 23.395″ N1° 43′ 55.484″ E
3853° 27′ 46.677″ N1° 48′ 5.619″ E10153° 13′ 5.062″ N1° 43′ 4.402″ E
3953° 28′ 17.076″ N1° 48′ 21.428″ E10253° 4′ 59.121″ N1° 30′ 24.338″ E
4053° 28′ 37.302″ N1° 49′ 1.846″ E10353° 4′ 20.493″ N1° 29′ 37.106″ E
4153° 29′ 38.707″ N1° 52′ 55.786″ E10453° 4′ 9.988″ N1° 29′ 29.310″ E
4253° 31′ 13.071″ N1° 59′ 48.933″ E10553° 3′ 47.663″ N1° 28′ 59.880″ E
4353° 31′ 19.720″ N2° 0′ 36.709″ E10653° 3′ 36.602″ N1° 28′ 9.237″ E
4453° 32′ 1.260″ N2° 1′ 17.462″ E10753° 3′ 36.599″ N1° 27′ 27.833″ E
4553° 32′ 51.864″ N2° 2′ 12.822″ E10853° 3′ 40.623″ N1° 26′ 14.722″ E
4653° 34′ 50.465″ N2° 1′ 45.585″ E10953° 3′ 39.011″ N1° 25′ 12.221″ E
4753° 35′ 23.664″ N2° 1′ 56.535″ E11053° 3′ 28.120″ N1° 22′ 53.680″ E
4853° 35′ 46.884″ N2° 2′ 37.417″ E11153° 3′ 4.980″ N1° 19′ 32.112″ E
4953° 36′ 32.251″ N2° 2′ 43.845″ E11253° 3′ 6.278″ N1° 16′ 22.646″ E
5053° 37′ 0.888″ N2° 2′ 53.784″ E11353° 3′ 34.066″ N1° 14′ 17.070″ E
5153° 37′ 20.916″ N2° 3′ 21.412″ E11453° 3′ 23.126″ N1° 12′ 23.483″ E
5253° 38′ 20.262″ N2° 5′ 30.569″ E11553° 3′ 19.662″ N1° 10′ 8.762″ E
5353° 38′ 31.038″ N2° 6′ 19.862″ E11653° 3′ 30.020″ N1° 8′ 33.828″ E
5453° 41′ 39.572″ N2° 16′ 17.662″ E11753° 3′ 32.792″ N1° 7′ 6.899″ E
5553° 44′ 4.728″ N2° 20′ 18.541″ E11853° 1′ 51.145″ N1° 5′ 45.682″ E
5653° 51′ 54.307″ N2° 19′ 24.004″ E11953° 0′ 17.303″ N1° 5′ 29.793″ E
5753° 52′ 12.798″ N2° 19′ 38.938″ E12052° 59′ 10.951″ N1° 6′ 24.006″ E
5853° 59′ 22.420″ N2° 11′ 50.694″ E12152° 58′ 23.000″ N1° 7′ 34.209″ E
5953° 59′ 19.280″ N2° 13′ 34.691″ E12252° 57′ 44.291″ N1° 7′ 45.470″ E
6053° 58′ 42.514″ N2° 32′ 43.904″ E12352° 57′ 19.850″ N1° 7′ 56.688″ E
6154° 0′ 4.028″ N2° 40′ 52.651″ E12452° 56′ 59.623″ N1° 8′ 4.381″ E
6253° 48′ 57.136″ N2° 44′ 53.902″ E12552° 57′ 2.633″ N1° 7′ 44.016″ E
6353° 41′ 22.175″ N2° 47′ 35.927″ E12652° 57′ 4.058″ N1° 7′ 42.464″ E

Commencement Information

I2Sch. 1 Pt. 1 para. 2 in force at 22.1.2021, see art. 1

PART 2E+WANCILLARY WORKS

1.  Works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—E+W

(a)temporary landing places, moorings or other means of accommodating vessels in the construction and/or maintenance of the authorised development;

(b)marking buoys, beacons, fenders and other navigational warning or ship impact protection works; and

(c)temporary works for the benefit or protection of land or structures affected by the authorised development.

Commencement Information

I3Sch. 1 Pt. 2 para. 1 in force at 22.1.2021, see art. 1

PART 3E+WREQUIREMENTS

Time limitsE+W

1.  The authorised project must commence no later than the expiration of seven years beginning with the date this Order comes into force.

Commencement Information

I4Sch. 1 Pt. 3 para. 1 in force at 22.1.2021, see art. 1

Detailed offshore design parametersE+W

2.—(1) The total number of wind turbine generators comprised in the authorised project must not exceed 231 and a total rotor swept area of 8.8 square kilometres.

(2) Subject to sub-paragraph (3), each wind turbine generator forming part of the authorised project must not—

(a)exceed a height of 325 metres when measured from LAT to the tip of the vertical blade;

(b)exceed a rotor diameter of 265 metres;

(c)be less than 41.8 metres from LAT to the lowest point of the rotating blade; and

(d)be less than one kilometre from the nearest wind turbine generator in all directions.

(3) The reference in sub-paragraph (2)(d) to the location of a wind turbine generator is a reference to the centre point of that wind turbine generator.

(4) Wind turbine generator foundation structures forming part of the authorised scheme must be one of the following foundation options: monopile foundation, mono suction bucket foundation, jacket foundation or gravity base foundation.

(5) No wind turbine generator—

(a)jacket foundations employing pin piles forming part of the authorised project shall have a pin pile diameter of greater than four metres; and

(b)monopile foundation forming part of the authorised project shall have a diameter greater than 15 metres.

(6) The total seabed footprint area for wind turbine generator foundations must not exceed—

(a)435,660 square metres excluding scour protection; and

(b)1,623,182 square metres including scour protection.

Commencement Information

I5Sch. 1 Pt. 3 para. 2 in force at 22.1.2021, see art. 1

3.—(1) The total number of offshore electrical installations and offshore accommodation platforms shall not exceed 21, and shall consist of no more than—E+W

(a)12 offshore type 1 substations;

(b)four offshore type 2 substations;

(c)four offshore HVAC booster stations;

(d)six offshore subsea HVAC booster stations; and

(e)three offshore accommodation platforms.

(2) The dimensions of any offshore type 1 substation forming part of the authorised project must not exceed—

(a)90 metres in height when measured from LAT;

(b)100 metres in length; and

(c)100 metres in width.

(3) The dimensions of any offshore type 2 substation forming part of the authorised project must not exceed—

(a)110 metres in height when measured from LAT;

(b)180 metres in length; and

(c)90 metres in width.

(4) The dimensions of any offshore HVAC booster station forming part of the authorised project must not exceed—

(a)90 metres in height when measured from LAT;

(b)100 metres in length; and

(c)100 metres in width.

(5) The dimensions of any offshore subsea HVAC booster station forming part of the authorised project must not exceed—

(a)15 metres in height when measured from the seabed;

(b)50 metres in length; and

(c)50 metres in width.

(6) The dimensions of any offshore accommodation platform forming part of the authorised project must not exceed—

(a)64 metres in height when measured from LAT;

(b)60 metres in length; and

(c)60 metres in width.

(7) Any bridge located between any offshore substation or accommodation platform shall be no longer than 100 metres.

(8) Offshore accommodation platform foundation structures forming part of the authorised project must be one of the following foundation options: monopile foundations, mono suction bucket foundations, jacket foundations, or gravity base foundations.

(9) Offshore installation foundation structures forming part of the authorised scheme must be one of the following foundation options—

(a)for offshore type 1 substations, offshore HVAC booster stations and offshore subsea HVAC booster stations either monopile foundations, mono suction bucket foundations, jacket foundations, gravity base foundations, jacket foundations or box-type gravity base foundations; and

(b)for offshore type 2 substations, either monopile foundations, mono suction bucket foundations, jacket foundations, gravity base foundations, jacket foundations, box-type gravity base foundations, pontoon gravity base 1 foundations, or pontoon gravity base 2 foundations.

(10) No offshore installation or offshore accommodation platform—

(a)jacket foundation employing pin piles forming part of the authorised project shall have a pin pile diameter of greater than 4 metres; and

(b)monopile foundation forming part of the authorised project shall have a diameter greater than 15 metres.

(11) The total seabed footprint area for offshore accommodation platform foundations must not exceed—

(a)8,836 square metres excluding scour protection; and

(b)28,628 square metres including scour protection.

(12) The total seabed footprint area for offshore electrical installation foundations must not exceed—

(a)138,900 square metres excluding scour protection; and

(b)267,900 square metres including scour protection.

Commencement Information

I6Sch. 1 Pt. 3 para. 3 in force at 22.1.2021, see art. 1

4.  The total volume of scour protection for wind turbine generators, offshore accommodation platforms and offshore electrical installations shall not exceed 2,709,673 cubic metres.E+W

Commencement Information

I7Sch. 1 Pt. 3 para. 4 in force at 22.1.2021, see art. 1

5.—(1) The number of cable circuits shall not exceed six.E+W

(2) The total length of the cables comprising Work No. 1(c) shall not exceed 830 kilometres.

(3) The total length of the cables comprising Work Nos. 2(c), 2(d) and 3(d) shall not exceed 1,371 kilometres.

(4) The total volume of cable protection (excluding cable crossings) shall not exceed 2,201,000 cubic metres with a maximum footprint of 1,540,700 square metres.

(5) The total volume of cable protection associated with cable crossings shall not exceed 784,875 cubic metres with a maximum footprint of 747,500 square metres.

(6) The total number of the cable crossings must not exceed 44 unless otherwise agreed with the MMO.

Commencement Information

I8Sch. 1 Pt. 3 para. 5 in force at 22.1.2021, see art. 1

Phases of authorised developmentE+W

6.—(1) The authorised development may not be commenced until a written scheme setting out the phases of construction of the authorised project has been submitted to and approved by the relevant planning authority, in relation to the connection works, or the MMO, in relation to works seaward of MHWS.

(2) The phases of construction referred to in sub-paragraph (1) shall not exceed two, save that each phase may be undertaken in any number of stages as prescribed in the written scheme.

(3) The scheme must be implemented as approved.

Commencement Information

I9Sch. 1 Pt. 3 para. 6 in force at 22.1.2021, see art. 1

Detailed design approval onshoreE+W

7.—(1) Construction of the connection works in either Work No.9 or Work No. 10 shall not commence until details of—

(a)the layout;

(b)scale;

(c)proposed finished ground levels;

(d)external appearance and materials;

(e)hard surfacing materials;

(f)vehicular and pedestrian access, parking and circulation areas;

(g)minor structures, such as furniture, refuse or other storage units, signs and lighting; and

(h)proposed and existing functional services above and below, ground, including drainage, power and communications cables and pipelines, manholes and supports [F2,]

relating to that work of the authorised project have been submitted to and approved in writing by the relevant planning authority.

(2) The details submitted under sub-paragraph (1) must be in accordance with the limits of deviation set out in the onshore limits of deviation plan and substantially in accordance with the design objectives and principles.

(3) The connection works in Works No.9 and 10 must be carried out in accordance with the approved details.

(4) The connection works in either Work No.9 or Work No. 10 shall not commence until explanation of the choice of HVDC or HVAC for that phase has been provided in writing to the relevant planning authority, either before, or at the same time as, the details referred to in [F3sub-paragraph] (1).

Textual Amendments

Commencement Information

I10Sch. 1 Pt. 3 para. 7 in force at 22.1.2021, see art. 1

Provision of landscapingE+W

8.—(1) No phase of the connection works may commence until for that phase a written landscape plan and associated work programme (which accords with the outline landscape plan and outline ecological management plan) has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and the Historic Buildings and Monuments Commission for England.

(2) The term “commence” as used in requirement 8(1) shall include any onshore site preparation works.

(3) The landscape plan must include details of—

(a)surveys, assessments and method statements as guided by BS 5837 and the Hedgerows Regulations 1997; F4...

(b)location, number, species, size and planting density of any proposed planting;

(c)cultivation, importing of materials and other operations to ensure plant establishment;

(d)existing trees and hedges to be retained with measures for their protection during the construction period; and

(e)implementation timetables for all landscaping works.

(4) The landscape plan must be carried out as approved.

Textual Amendments

Commencement Information

I11Sch. 1 Pt. 3 para. 8 in force at 22.1.2021, see art. 1

Implementation and maintenance of landscapingE+W

9.—(1) All landscape works must be carried out in accordance with the landscape plans approved under requirement 8 (provision of landscaping), and in accordance with the relevant recommendations of appropriate British Standards.

(2) Any tree or shrub planted as part of an approved landscape plan that, within a period of ten years after planting, is removed by the undertaker, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise approved in writing by the relevant planning authority.

Commencement Information

I12Sch. 1 Pt. 3 para. 9 in force at 22.1.2021, see art. 1

Ecological management planE+W

10.—(1) No phase of the connection works may commence until for that phase a written ecological management plan (which accords with the outline ecological management plan and the relevant recommendations of appropriate British Standards) reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and (where works have potential to impact wetland habitats) the Environment Agency.

(2) The onshore site preparation works may not commence until a written ecological management plan (which accords with the outline ecological management plan) for those works reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs; and

(3) The ecological management plan must include an implementation timetable and must be carried out as approved.

Commencement Information

I13Sch. 1 Pt. 3 para. 10 in force at 22.1.2021, see art. 1

Highway accessesE+W

11.—(1) Construction of any new permanent or temporary means of access to a highway, or alteration, or use of an existing means of access to a highway, shall not commence until an access plan for that access has been submitted to and approved by Norfolk County Council as the local highway authority.

(2) The access plan must include details of the siting, design, layout, visibility splays, access management measures and a maintenance programme relevant to the access it relates to.

(3) The highway authority must be consulted on the access plan before it is submitted for approval.

(4) The highway accesses (including visibility splays) must be constructed and maintained in accordance with the approved details.

Commencement Information

I14Sch. 1 Pt. 3 para. 11 in force at 22.1.2021, see art. 1

Fencing and other means of enclosureE+W

12.—(1) No phase of the connection works may commence until for that phase written details of all proposed permanent fences, walls or other means of enclosure of the connection works have been submitted to and approved by the relevant planning authority.

(2) Any temporary fences, walls or other means of enclosure must be provided in accordance with the outline code of construction practice.

(3) All construction sites must remain securely fenced in accordance with the code of construction practice at all times during construction of the relevant phase of the connection works.

(4) Any temporary fencing must be removed on completion of the relevant phase of the connection works.

(5) Any approved permanent fencing in relation to an onshore HVDC/HVAC substation or onshore HVAC booster station must be completed before that onshore HVDC/HVAC substation or onshore HVAC booster station is brought into use and maintained for the operational lifetime of the onshore HVDC/HVAC substation or onshore HVAC booster station.

Commencement Information

I15Sch. 1 Pt. 3 para. 12 in force at 22.1.2021, see art. 1

Surface and foul water drainageE+W

13.—(1) No phase of the connection works shall commence until for that phase written details of the surface and (if any) foul water drainage system (including means of pollution control) have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the lead local flood authority.

(2) The surface and foul water drainage system for each phase must be constructed and maintained in accordance with the approved details.

Commencement Information

I16Sch. 1 Pt. 3 para. 13 in force at 22.1.2021, see art. 1

Contaminated land and groundwater schemeE+W

14.—(1) No phase of the authorised development within the area of a relevant planning authority may be commenced until a scheme to deal with the contamination of any land (including groundwater) within the Order limits that is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to, and approved by, the relevant planning authority in consultation with the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.

(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination and the remedial measures to be taken for that stage to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.

(3) Such remediation as may be identified in the approved scheme must be carried out in accordance with the approved scheme.

Commencement Information

I17Sch. 1 Pt. 3 para. 14 in force at 22.1.2021, see art. 1

Surface waterE+W

15.—(1) No part of the onshore HVDC/HVAC substation or onshore HVAC booster station shall commence until, in respect of that installation, a detailed surface water scheme has been prepared in consultation with the Environment Agency and Norfolk County Council and submitted to and approved in writing by Norfolk County Council.

(2) The detailed surface water schemes must accord with the outline code of construction practice and—

(a)be based on sustainable drainage principles;

(b)an assessment of the hydrological and hydrogeological context of the onshore HVDC/HVAC substation or onshore HVAC booster station, as applicable; and

(c)include detailed designs of a surface water drainage scheme.

(3) Construction of the onshore HVDC/HVAC substation or HVAC booster station as applicable must be carried out in accordance with the approved scheme.

Commencement Information

I18Sch. 1 Pt. 3 para. 15 in force at 22.1.2021, see art. 1

Onshore ArchaeologyE+W

16.—(1) No phase of the connection works may commence until for that phase a written scheme of archaeological investigation (which must accord with the outline onshore written scheme of investigation) for Work Nos. 6 to 15 has been submitted to and approved by the relevant planning authority in consultation with Norfolk County Council and the Historic Buildings and Monuments Commission for England.

(2) The term “commence” as used in requirement 16(1) shall include any onshore site preparation works.

(3) Any archaeological investigations must be carried out in accordance with the approved scheme.

(4) The archaeological site investigations and post investigation assessment must be completed for that phase in accordance with the programme set out in the written scheme of archaeological investigation and provision made for analysis, publication and dissemination of results and archive deposition secured for that phase.

Commencement Information

I19Sch. 1 Pt. 3 para. 16 in force at 22.1.2021, see art. 1

Code of construction practiceE+W

17.—(1) No phase of any works landward of MLWS may commence until for that phase a code of construction practice (which must accord with the outline code of construction practice) has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, the relevant SNCBs, the relevant highway authority and, if applicable, the MMO.

(2) The term “commence” as used in requirement 17(1) shall include any onshore site preparation works.

(3) All construction works for each phase must be undertaken in accordance with the relevant approved code of construction practice.

Commencement Information

I20Sch. 1 Pt. 3 para. 17 in force at 22.1.2021, see art. 1

Construction traffic management planE+W

18.—(1) No phase of the connection works may commence until written details of a construction traffic management plan (which accords with the outline construction traffic management plan) for that phase has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority. The construction traffic management plan shall include, in respect of Link 89, as referred to in the Environmental Statement, a Cawston Highway Intervention Scheme agreed between the undertaker and the relevant highway authority.

(2) The term “commence” as used in requirement 18(1) shall include any onshore site preparation works.

(3) The construction traffic management plan for each phase must be implemented as approved for that phase.

Commencement Information

I21Sch. 1 Pt. 3 para. 18 in force at 22.1.2021, see art. 1

European protected species onshoreE+W

19.—(1) No phase of the connection works may commence until final pre-construction survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by that phase of the connection works or in any of the trees to be lopped or felled as part of that phase of the connection works.

(2) Where a European protected species is shown to be present, the relevant part of the connection works must not begin until, after consultation with the relevant SNCBs and the relevant planning authority, a scheme of protection and mitigation measures has been submitted to and approved by the relevant planning authority or a European protected species licence granted by Natural England.

(3) The connection works must be carried out in accordance with the approved scheme.

(4) In this Requirement, “European protected species” has the same meaning as in regulations 42 and 46 of the Conservation of Habitats and Species Regulations 2017 M1.

Commencement Information

I22Sch. 1 Pt. 3 para. 19 in force at 22.1.2021, see art. 1

Marginal Citations

Restoration of land used temporarily for constructionE+W

20.  Any land landward of MLWS within the Order limits which is used temporarily for construction of the connection works and not ultimately incorporated in permanent works or approved landscaping, must be reinstated in accordance with such details as the relevant planning authority in consultation with, where appropriate, the MMO, and the relevant highway authority, may approve, as soon as reasonably practicable and in any event within twelve months of completion of the relevant phase of the connection works.

Commencement Information

I23Sch. 1 Pt. 3 para. 20 in force at 22.1.2021, see art. 1

Control of noise during operational phaseE+W

21.—(1) Prior to commencement of any phase of works landward of MHWS, a noise management plan (NMP) for Work Nos. 9 and 10 shall be submitted to and approved by the relevant planning authority.

(2) The NMP must set out the particulars of—

(a)the noise attenuation and mitigation measures to be taken to minimise noise resulting from Work Nos. 9 and 10, including any noise limits; and

(b)a scheme for monitoring attenuation and mitigation measures provided under sub-paragraph (a) which must include—

(i)the circumstances under which noise will be monitored;

(ii)the locations at which noise will be monitored;

(iii)the method of noise measurement (which must be in accord with BS 4142:2014+A1:2019, an equivalent successor standard or other agreed noise measurement methodology appropriate to the circumstances); and

(iv)a complaints procedure.

(3) The NMP must be implemented as approved.

Commencement Information

I24Sch. 1 Pt. 3 para. 21 in force at 22.1.2021, see art. 1

Local skills and employmentE+W

22.—(1) No phase of the connection works may commence until for that phase a skills and employment plan (which accords with the outline skills and employment plan) in relation to the authorised development—

(a)within the boundaries of Norfolk County Council has been submitted to and approved by Norfolk County Council; and

(b)within the boundaries of North East Lincolnshire Council has been submitted to and approved by North East Lincolnshire Council.

(2) The skills and employment plan described under requirement 22(1)(a) shall be prepared in consultation with Norfolk County Council, North Norfolk District Council, Broadland District Council, South Norfolk Council and the New Anglia Local Enterprise Partnership, or such other body as may be approved by Norfolk County Council.

(3) The skills and employment plan described under requirement 22(1)(b) shall be prepared in consultation with Humber Local Enterprise Partnership, or such other body as may be approved by North East Lincolnshire Council.

(4) Each skills and employment plan shall identify opportunities for individuals and businesses based in the regions of East Anglia or the Humber to access employment opportunities associated with the construction, operation and maintenance of the authorised development.

(5) The skills and employment plans shall be implemented as approved.

Commencement Information

I25Sch. 1 Pt. 3 para. 22 in force at 22.1.2021, see art. 1

Onshore decommissioningE+W

23.—(1) Within three months of the cessation of commercial operation of the connection works an onshore decommissioning plan must be submitted to the relevant planning authority for approval unless otherwise agreed in writing by the relevant planning authority.

(2) The relevant planning authority must provide its decision on the onshore decommissioning plan required under requirement 23(1) within three months of submission of such plan unless otherwise agreed in writing by the relevant planning authority and the undertaker.

(3) The decommissioning plan must be implemented as approved unless otherwise agreed in writing by the relevant planning authority.

Commencement Information

I26Sch. 1 Pt. 3 para. 23 in force at 22.1.2021, see art. 1

Notification of generation of powerE+W

24.  The undertaker shall notify the relevant planning authority and the MMO upon first generation of power from each phase of the authorised project not less than seven days after the occurrence of this event.

Commencement Information

I27Sch. 1 Pt. 3 para. 24 in force at 22.1.2021, see art. 1

Requirement for written approvalE+W

25.  Where the approval, agreement or confirmation of the Secretary of State, relevant planning authority or another person is required under a requirement, that approval, agreement or confirmation must be given in writing.

Commencement Information

I28Sch. 1 Pt. 3 para. 25 in force at 22.1.2021, see art. 1

Amendments to approved detailsE+W

26.—(1) With respect to any requirement which requires the authorised project to be carried out in accordance with the details approved by the relevant planning authority or another person, the approved details must be carried out as approved unless an amendment or variation is previously agreed in writing by the relevant planning authority or that other person in accordance with sub-paragraph (2).

(2) Any amendments to or variations from the approved details must be in accordance with the principles and assessments set out in the environmental statement. Such agreement may only be given in relation to immaterial changes where it has been demonstrated to the satisfaction of the relevant planning authority or that other person that the subject matter of the agreement sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

(3) The approved details must be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority or that other person.

Commencement Information

I29Sch. 1 Pt. 3 para. 26 in force at 22.1.2021, see art. 1