SCHEDULES

SCHEDULE 1E+WAUTHORISED PROJECT

PART 3E+WREQUIREMENTS

Implementation and maintenance of landscapingE+W

9.—(1) All landscape works must be carried out in accordance with the landscape plans approved under requirement 8 (provision of landscaping), and in accordance with the relevant recommendations of appropriate British Standards.

(2) Any tree or shrub planted as part of an approved landscape plan that, within a period of ten years after planting, is removed by the undertaker, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise approved in writing by the relevant planning authority.

Commencement Information

I1Sch. 1 Pt. 3 para. 9 in force at 22.1.2021, see art. 1