xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

PART 2 E+WWORK PROVISIONS

Supplementary powersE+W

Discharge of waterE+W

18.—(1) Subject to sub–paragraphs (3) and (4), the undertaker may use any watercourse, public sewer or drain for the drainage of water in connection with the construction or maintenance of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker pursuant to paragraph (1) is to be determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 1991 M1.

(3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs, whose consent may be given subject to such terms and conditions as that person may reasonably impose, but must not be unreasonably withheld or delayed.

(4) The undertaker must not make any opening into any public sewer or drain except—

(a)in accordance with plans approved by the person to whom the sewer or drain belongs, but approval must not be unreasonably withheld or delayed; and

(b)where that person has been given the opportunity to supervise the making of the opening.

(5) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.

(6) Nothing in this article overrides the requirement for an environmental permit under regulation 12(1)(b) of the Environmental Permitting (England and Wales) Regulations 2016.

(7) In this article—

(a)public sewer or drain” means a sewer or drain which belongs to Homes England, the Environment Agency, a harbour authority within the meaning of section 57 (interpretation) of the Harbours Act 1964 M2, an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation; and

(b)other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991 M3 have the same meaning as in that Act.

Commencement Information

I1Art. 18 in force at 1.5.2020, see art. 1

Marginal Citations

M11991 c.56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43) and sections 99(2), (4), (5)(a), (5)(b),(5)(c) and 36(2) of the Water Act 2003 (c.37) and section 32, Schedule 3, paragraph 16(1) of the Flood and Water Management Act 2010 c.29.

Authority to survey and investigate the landE+W

19.—(1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or enter on any land which may be affected by the authorised development and—

(a)survey or investigate the land;

(b)without limitation to the generality of sub-paragraph (a), make trial holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;

(c)without limitation to the generality of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and

(d)place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes.

(2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days' notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker—

(a)must, if so required before entering the land, produce written evidence of their authority to do so; and

(b)may take onto the land such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.

(4) No trial holes are to be made under this article—

(a)in land located within the highway boundary without the consent of the highway authority; or

(b)in a private street without the consent of the street authority,

but such consent must not be unreasonably withheld.

(5) The undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land once it has ceased to use the land for the purposes authorised by this article.

(6) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act M4.

Commencement Information

I2Art. 19 in force at 1.5.2020, see art. 1

Marginal Citations

M4The functions of the Lands Tribunal under the 1961 Act are transferred to the Upper Tribunal under the Tribunals, Courts and Enforcement Act 2007 (c.15).

Protective work to buildingsE+W

20.—(1) Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building or structure lying within the Order limits as the undertaker considers necessary or expedient.

(2) Protective works may be carried out—

(a)at any time before or during the construction of any part of the authorised development in the vicinity of the building or structure; or

(b)after the completion of that part of the authorised development in the vicinity of the building or structure at any time up to the end of the period of 5 years beginning with the date of final commissioning.

(3) For the purpose of determining how the powers under this article are to be exercised the undertaker may enter and survey any building or structure falling within paragraph (1) and any land within its curtilage.

(4) For the purpose of carrying out protective works under this article to a building or structure the undertaker may (subject to paragraphs (5) and (6))—

(a)enter the building or structure and any land within its curtilage; and

(b)where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building or structure but outside its curtilage, enter the adjacent land (but not any building erected on it) within the Order limits.

(5) Before exercising—

(a)a power under paragraph (1) to carry out protective works under this article to a building or structure;

(b)a power under paragraph (3) to enter a building or structure and land within its curtilage;

(c)a power under paragraph (4)(a) to enter a building or structure and land within its curtilage; or

(d)a power under paragraph (4)(b) to enter and take possession of land,

the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building, structure or land not less than 14 days' notice of its intention to exercise that power and, in a case falling within sub-paragraph (a), (c) or (d) specifying the protective works proposed to be carried out.

(6) Where a notice is served under paragraph (5)(a), F1... (5)(c) or (5)(d), the owner or occupier of the building, structure or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question of whether it is necessary or expedient to carry out the protective works or to enter the building, structure or land to be referred to arbitration under article 42(3) (procedures in relation to certain approvals etc.).

(7) The undertaker must compensate the owners and occupiers of any building, structure or land in relation to which powers under this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.

(8) Where—

(a)protective works are carried out to a building or structure under this article; and

(b)within 5 years beginning with the date of final commissioning for that part of the authorised development in the vicinity of the building or structure it appears that the protective works are inadequate to protect the building or structure against damage caused by the construction, on operation or maintenance of that part of the authorised development,

the undertaker must compensate the owners and occupiers of the building or structure for any loss or damage sustained by them.

(9) Nothing in this article relieves the undertaker from any liability to pay compensation under section 10(2) (further provision as to compensation for injurious affection) of the 1965 Act.

(10) Any compensation payable under paragraph (7) or (8) must be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(11) In this article “protective works” in relation to a building means—

(a)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building or structure by the construction, operation or maintenance of the authorised development; and

(b)any works the purpose of which is to remedy any damage which has been caused to the building by the construction, operation or maintenance of the authorised development.

Textual Amendments

Commencement Information

I3Art. 20 in force at 1.5.2020, see art. 1

Felling or lopping of treesE+W

21.—(1) The undertaker may fell or lop any tree or shrub within or overhanging land within the Order limits, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b)from constituting a danger to persons using the authorised development; or

(c)from obstructing or interfering with the passage of construction vehicles to the extent necessary for the purposes of construction of the authorised development.

(2) In carrying out any activity authorised by paragraph (1) the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.

(3) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

Commencement Information

I4Art. 21 in force at 1.5.2020, see art. 1