SCHEDULE 8DEEMED MARINE LICENCE UNDER THE 2009 ACT
PART 2CONDITIONS
MaintenanceI17
1
Unless otherwise agreed by the MMO, the licenced activities may not commence until a maintenance plan has been approved in writing by the MMO.
2
The maintenance plan must be submitted at least 6 weeks prior to the commencement of any maintenance activity, and must include details of the maintenance activities required including location, duration, timings, methodology and materials to be used.
3
Maintenance activities must be undertaken in accordance with the agreed plan.