The A303 Sparkford to Ilchester Dualling Development Consent Order 2021

58.—(1) Where the undertaker carries out any Works to any local highway it must make good any defects in those Works notified to it by the local highway authority within the period of 52 weeks after the date of the completion of the Works to that area of local highway to the reasonable satisfaction of the local highway authority.E+W

(2) The carrying out of any remedial works required under sub-paragraph (1) are Works under this Order.

(3) The carrying out of any remedial works required under sub-paragraph (1) requires the submission of such items of Detailed Information to the local highway authority as the undertaker deems to be reasonable in the circumstances but always including a description of the works to be carried out, a schedule of timings for the works, including dates and durations for any closures of any part of the local highway and traffic management proposals.

Commencement Information

I1Sch. 8 para. 58 in force at 19.2.2021, see art. 1