Article 42

SCHEDULE 10E+W+SProtective Provisions

PART 1E+W+SProtection for electricity, gas, water and sewerage undertakers

ApplicationE+W+S

1.  For the protection of the affected undertakers referred to in this part of this Schedule the following provisions have effect unless otherwise agreed in writing between the undertaker and the affected undertaker concerned.

Commencement Information

I1Sch. 10 Pt. 1 para. 1 in force at 22.4.2022, see art. 1(2)

2.  In this part of this Schedule—

affected undertaker” means—

(a)

any licence holder within the meaning of Part 1 (electricity supply) of the 1989 Act (an “electricity undertaker”);

(b)

a gas transporter within the meaning of Part 1 (gas supply) of the Gas Act 1986 (1) (a “gas undertaker”);

(c)

a water undertaker within the meaning of Part 1 (preliminary) of the Water Industry Act 1991(2) (a “water undertaker”); and

(d)

a sewerage undertaker within the meaning of Part 1 (preliminary) of the Water Industry Act 1991 (a “sewerage undertaker”),

for the area of the authorised development but, for the avoidance of doubt, does not include the undertakers specified in Part 3, Part 4, Part 5, Part 6, Part 7 or Part 8 of this Schedule, and in relation to any apparatus, means the undertaker to whom it belongs or by whom it is maintained;

alternative apparatus” means alternative apparatus adequate to enable the affected undertaker in question to fulfil its statutory functions in a manner not less efficient than previously;

apparatus” means—

(a)

in the case of an electricity undertaker, electric lines or electrical plant (as defined in the 1989 Act), belonging to or maintained by that affected undertaker;

(b)

in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or maintained by a gas transporter for the purposes of gas supply;

(c)

in the case of a water undertaker, mains, pipes or other apparatus belonging to or maintained by that affected undertaker for the purposes of water supply; and

(d)

in the case of a sewerage undertaker—

(i)

any drain or works vested in the affected undertaker under the Water Industry Act 1991; and

(ii)

any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) of that Act or an agreement to adopt made under section 104 of that Act,

and includes a sludge main, disposal main (within the meaning of section 219 of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;

functions” includes powers and duties; and

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land.

Commencement Information

I2Sch. 10 Pt. 1 para. 2 in force at 22.4.2022, see art. 1(2)

Precedence of the 1991 Act in respect of apparatus in the streetsE+W+S

3.  This part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the affected undertaker are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.

Commencement Information

I3Sch. 10 Pt. 1 para. 3 in force at 22.4.2022, see art. 1(2)

No acquisition etc. except by agreementE+W+S

4.  Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.

Commencement Information

I4Sch. 10 Pt. 1 para. 4 in force at 22.4.2022, see art. 1(2)

Removal of apparatusE+W+S

5.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be removed under this part of this Schedule and any right of an affected undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the affected undertaker in question.

(2) If, for the purpose of executing any works in, on or under any land purchased, held, or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to the affected undertaker in question written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order an affected undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the affected undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the affected undertaker in question must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use all reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.

(4) Any alternative apparatus to be constructed in land of the undertaker under this part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the affected undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 37 (arbitration).

(5) The affected undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 37 (arbitration), and after the grant to the affected undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this part of this Schedule.

(6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the affected undertaker in question that it desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land controlled by the undertaker, that work, instead of being executed by the affected undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the affected undertaker.

(7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 300 millimetres of the apparatus.

Commencement Information

I5Sch. 10 Pt. 1 para. 5 in force at 22.4.2022, see art. 1(2)

Facilities and rights for alternative apparatusE+W+S

6.—(1) Where, in accordance with the provisions of this part of this Schedule, the undertaker affords to an affected undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and the affected undertaker in question or in default of agreement settled by arbitration in accordance with article 37 (arbitration).

(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the affected undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that affected undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Commencement Information

I6Sch. 10 Pt. 1 para. 6 in force at 22.4.2022, see art. 1(2)

Retained apparatusE+W+S

7.—(1) Not less than 28 days before starting the execution of any works of the type referred to in paragraph 5(2) that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 5(2), the undertaker must submit to the affected undertaker in question a plan, section and description of the works to be executed.

(2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the affected undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the affected undertaker is entitled to watch and inspect the execution of those works.

(3) Any requirements made by an affected undertaker under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.

(4) If an affected undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 1 to 6 apply as if the removal of the apparatus had been required by the undertaker under paragraph 5(2).

(5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.

(6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the affected undertaker in question notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.

Commencement Information

I7Sch. 10 Pt. 1 para. 7 in force at 22.4.2022, see art. 1(2)

8.—(1) Subject to the following provisions of this paragraph, the undertaker must repay to an affected undertaker the reasonable expenses incurred by that affected undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus (including costs or compensation payable in connection with the acquisition of land for that purpose) which may be required in consequence of the execution of any such works as are referred to in paragraph 5(2).

(2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this part of this Schedule, that value being calculated after removal.

(3) If in accordance with the provisions of this part of this Schedule—

(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 37 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the affected undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess.

(4) For the purposes of sub-paragraph (3)—

(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.

(5) An amount which apart from this sub-paragraph would be payable to an affected undertaker in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the affected undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Commencement Information

I8Sch. 10 Pt. 1 para. 8 in force at 22.4.2022, see art. 1(2)

Expenses and costsE+W+S

9.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraph 5(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of an affected undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any affected undertaker, the undertaker must—

(a)bear and pay the cost reasonably incurred by that affected undertaker in making good such damage or restoring the supply; and

(b)make reasonable compensation to that affected undertaker for any other expenses, loss, damages, penalty or costs incurred by the affected undertaker,

by reason or in consequence of any such damage or interruption.

(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an affected undertaker, its officers, servants, contractors or agents.

(3) An affected undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without the consent of the undertaker which, if it withholds such consent, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.

Commencement Information

I9Sch. 10 Pt. 1 para. 9 in force at 22.4.2022, see art. 1(2)

10.  Nothing in this part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an affected undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

Commencement Information

I10Sch. 10 Pt. 1 para. 10 in force at 22.4.2022, see art. 1(2)

PART 2E+W+SProtection for operators of electronic communications code networks

1.—(1) For the protection of any operator, the following provisions have effect unless otherwise agreed in writing between the undertaker and the operator.E+W+S

(2) In this part of this Schedule—

electronic communications apparatus” has the same meaning as in the electronic communications code;

the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003 Act;

electronic communications code network” means—

(a)

so much of an electronic communications network or infrastructure system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 (application of the electronics communications code) of the 2003 Act; and

(b)

an electronic communications network which the Secretary of State is providing or proposing to provide;

electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;

infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7 of that code; and

operator” means the operator of an electronic communications code network.

Commencement Information

I11Sch. 10 Pt. 2 para. 1 in force at 22.4.2022, see art. 1(2)

2.  The exercise of the powers of article 28 (statutory undertakers) are subject to Part 10 of Schedule 3A (the electronics communications code) to the Communications Act 2003.E+W+S

Commencement Information

I12Sch. 10 Pt. 2 para. 2 in force at 22.4.2022, see art. 1(2)

3.—(1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or their construction, or of any subsidence resulting from any of those works—E+W+S

(a)any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works, or other property of an operator); or

(b)there is any interruption in the supply of the service provided by an operator, the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and must—

(i)make reasonable compensation to an operator for loss sustained by it; and

(ii)indemnify an operator against claims, demands, proceedings, costs, damages and expenses which may be made or taken against, or recovered from, or incurred by, an operator by reason, or in consequence of, any such damage or interruption.

(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.

(3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand may be made without the consent of the undertaker which, if it withholds such consent, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.

(4) Any difference arising between the undertaker and the operator under this paragraph must be referred to and settled by arbitration under article 37 (arbitration).

Commencement Information

I13Sch. 10 Pt. 2 para. 3 in force at 22.4.2022, see art. 1(2)

4.  This part of this Schedule does not apply to—E+W+S

(a)any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act; or

(b)any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised development.

Commencement Information

I14Sch. 10 Pt. 2 para. 4 in force at 22.4.2022, see art. 1(2)

5.  Nothing in this part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.E+W+S

Commencement Information

I15Sch. 10 Pt. 2 para. 5 in force at 22.4.2022, see art. 1(2)

PART 3E+W+SProtection for Anglian Water Services Limited

1.  For the protection of Anglian Water, the following provisions of this Schedule have effect unless otherwise agreed in writing between the undertaker and Anglian Water.E+W+S

Commencement Information

I16Sch. 10 Pt. 3 para. 1 in force at 22.4.2022, see art. 1(2)

2.  In this part of this schedule—E+W+S

alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in not less efficient a manner than previously;

Anglian Water” means Anglian Water Services Limited (company number 02366656);

apparatus” means any works, mains, pipes or other apparatus belonging to or maintained by Anglian Water for the purposes of water supply and sewerage; and

(a)

any drain or works vested in Anglian Water under The Water Industry Act 1991,

(b)

any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102 (4) of The Water Industry Act 1991 or an agreement to adopt made under section 104 of that Act,

and includes a sludge main, disposal main or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any sewer, drain, or works (within the meaning of section 219 of that Act) and any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus.

functions” includes powers and duties.

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land; and

plan” includes sections, drawings, specifications and method statements.

Commencement Information

I17Sch. 10 Pt. 3 para. 2 in force at 22.4.2022, see art. 1(2)

3.  This Part does not apply to apparatus in respect of which the relations between the undertaker and Anglian Water are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.E+W+S

Commencement Information

I18Sch. 10 Pt. 3 para. 3 in force at 22.4.2022, see art. 1(2)

4.  The undertaker must not interfere with, build over or near to any apparatus within the Order land or execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within the standard protection strips which are the strips of land falling, the following distances to either side of the medial line of any apparatus—E+W+S

(a)2.25 metres where the diameter of the pipe is less than 150 millimetres;

(b)3 metres where the diameter of the pipe is between 150 and 450 millimetres;

(c)4.5 metres where the diameter of the pipe is between 450 and 750 millimetres;

(d)6 metres where the diameter of the pipe exceeds 750 millimetres;

unless otherwise agreed in writing with Anglian Water, such agreement not to be unreasonably withheld or delayed, and such provision being brought to the attention of any agent or contractor responsible for carrying out any work on behalf of the undertaker.

Commencement Information

I19Sch. 10 Pt. 3 para. 4 in force at 22.4.2022, see art. 1(2)

5.  The alteration, extension, removal or re-location of any apparatus may not be implemented until—E+W+S

(a)any requirement for any permits under the Environmental Permitting (England and Wales) Regulations 2016 or other legislations and any other associated consents are obtained, and any approval or agreement required from Anglian Water on alternative outfall locations as a result of such re-location are approved, such approvals or agreement from Anglian Water not to be unreasonably withheld or delayed; and

(b)the undertaker has made the appropriate application required under the Water Industry Act 1991 together with a plan and description of the works proposed and Anglian Water has agreed all of the contractual documentation required under the Water Industry Act 1991, such agreement not to be unreasonably withheld or delayed; and such works to be executed only in accordance with the plan and description submitted and in accordance with such reasonable requirements as may be made by Anglian Water without delay for the alteration or otherwise for the protection of the apparatus, or for securing access to it.

Commencement Information

I20Sch. 10 Pt. 3 para. 5 in force at 22.4.2022, see art. 1(2)

6.  In the situation, where in exercise of the powers conferred by the Order, the undertaker acquires any interest in any land in which apparatus is placed and such apparatus is to be relocated, extended, removed or altered in any way, no alteration or extension may take place until Anglian Water has established to its reasonable satisfaction, contingency arrangements in order to conduct its functions for the duration of the works to relocate, extend, remove or alter the apparatus. Anglian Water must use reasonable endeavours to establish contingency arrangements in a timely manner.E+W+S

Commencement Information

I21Sch. 10 Pt. 3 para. 6 in force at 22.4.2022, see art. 1(2)

7.  Regardless of any provision in this Order or anything shown on any plan, the undertaker must not acquire any apparatus otherwise than by agreement, and before extinguishing any existing rights for Anglian Water to use, keep, inspect, renew and maintain its apparatus in the Order land, the undertaker must, with the agreement of Anglian Water, create a new right to use, keep, inspect, renew and maintain the apparatus that is reasonably convenient for Anglian Water such agreement not to be unreasonably withheld or delayed, and to be subject to arbitration under article 37 (arbitration).E+W+S

Commencement Information

I22Sch. 10 Pt. 3 para. 7 in force at 22.4.2022, see art. 1(2)

8.  If the undertaker is unable to create the new rights referred to in paragraph 7, Anglian Water must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible, use its reasonable endeavours to obtain the necessary rights.E+W+S

Commencement Information

I23Sch. 10 Pt. 3 para. 8 in force at 22.4.2022, see art. 1(2)

9.  If in consequence of the exercise of the powers conferred by the Order the access to any apparatus is materially obstructed the undertaker must provide such alternative means of access to such apparatus as enables Anglian Water to maintain or use the apparatus no less effectively than was possible before such obstruction.E+W+S

Commencement Information

I24Sch. 10 Pt. 3 para. 9 in force at 22.4.2022, see art. 1(2)

10.  If in consequence of the exercise of the powers conferred by the Order, previously unmapped sewers, lateral drains or other apparatus are identified by the undertaker, notification of the location of such assets will immediately be given to Anglian Water and afforded the same protection as other Anglian Water assets.E+W+S

Commencement Information

I25Sch. 10 Pt. 3 para. 10 in force at 22.4.2022, see art. 1(2)

11.  If for any reason or in consequence of the construction of any of the works referred to in paragraphs 5 to 7 and 10 above any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must—E+W+S

(a)bear and pay the cost reasonably incurred by Anglian Water in making good any damage or restoring the supply; and

(b)make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs properly and reasonably incurred by Anglian Water

by reason or in consequence of any such damage or interruption.

Commencement Information

I26Sch. 10 Pt. 3 para. 11 in force at 22.4.2022, see art. 1(2)

12.  Nothing in paragraph 11 above imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Anglian Water, its officer, servants, contractors or agents.E+W+S

Commencement Information

I27Sch. 10 Pt. 3 para. 12 in force at 22.4.2022, see art. 1(2)

13.  Anglian Water must give the undertaker reasonable notice of any claim or demand pursuant to paragraph 11 and must consider its representations before proceeding further in respect of the claim or demand.E+W+S

Commencement Information

I28Sch. 10 Pt. 3 para. 13 in force at 22.4.2022, see art. 1(2)

14.  Anglian Water must use its reasonable endeavours to mitigate in whole or in part and to minimise any claim, costs, expenses, loss, demands and penalties pursuant to paragraph 11. If requested to do so by the undertaker, Anglian Water shall provide an explanation of how the claim has been minimisedE+W+S

Commencement Information

I29Sch. 10 Pt. 3 para. 14 in force at 22.4.2022, see art. 1(2)

15.  Any difference or dispute arising between the undertaker and Anglian Water under this Schedule must, unless otherwise agreed in writing between the undertaker and Anglian Water, be determined by arbitration in accordance with article 37 (arbitration).E+W+S

Commencement Information

I30Sch. 10 Pt. 3 para. 15 in force at 22.4.2022, see art. 1(2)

PART 4E+W+SProtection for National Grid as electricity undertaker

ApplicationE+W+S

1.—(1) For the protection of National Grid, the statutory undertaker referred to in this Part of this Schedule, the following provisions have effect unless otherwise agreed in writing between the undertaker and the statutory undertaker.

(2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the undertaker and the statutory undertakers, where the benefit of this Order is transferred or granted to another person under article 5 (benefit of Order)—

(a)any agreement of the type mentioned in sub-paragraph (1) has effect as if it had been made between the statutory undertaker and the transferee or grantee (as the case may be) in all cases where the transfer of the benefit relates to any specified works; and

(b)written notice of the transfer or grant must be given to the statutory undertaker on or before the date of that transfer or grant.

(3) Without prejudice to paragraph 10(3)(b) below, sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to the statutory undertaker.

Commencement Information

I31Sch. 10 Pt. 4 para. 1 in force at 22.4.2022, see art. 1(2)

InterpretationE+W+S

2.  In this Part of this Schedule—

alternative apparatus” means appropriate alternative apparatus to the satisfaction of the statutory undertaker to enable the statutory undertaker to fulfil its statutory functions in a manner no less efficient than previously;

apparatus” means any electric lines or electrical plant as defined in the Electricity Act 1989, belonging to or maintained by the statutory undertaker together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of the statutory undertaker for the purposes of transmission, distribution and/or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;

authorised works” has the same meaning as is given to the term “authorised development” in article 2 of this Order and includes any associated development authorised by the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;

“commence” and “commencement” in paragraph 8 of this Part of this Schedule shall, to the extent that at the relevant time there is subterranean apparatus, include any below ground surveys or monitoring, ground work operations or the receipt and erection of construction plant and equipment “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary and/or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;

functions” includes powers and duties;

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;

“maintain” and “maintenance” includes the ability and right to do any of the following in relation to any apparatus or alternative apparatus of the statutory undertaker including construct, use, repair, alter, inspect, renew or remove the apparatus;

“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;

parent company” means a parent company of the undertaker acceptable to and which shall have been approved by the statutory undertaker acting reasonably;

statutory undertaker” means National Grid Electricity Transmission PLC (Company No. 2366977) whose registered office is at 1-3 Strand, London, WC2N 5EH, an electricity undertaker being a licence holder within the meaning of Part 1 of the Electricity Act 1989;

specified works” means any of the authorised works or activities undertaken in association with the authorised works which will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under paragraph 7(2) or otherwise; and/or may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph ‎6(2) or otherwise “undertaker” means the undertaker as defined in article 2 of this Order.

Commencement Information

I32Sch. 10 Pt. 4 para. 2 in force at 22.4.2022, see art. 1(2)

3.  Except for paragraphs 4 (apparatus of statutory undertakers in stopped up streets), 8 (retained apparatus: protection of National Grid as electricity undertaker), 9 (expenses) and 10 (indemnity) of this Schedule which apply in respect of the exercise of all or any powers under the Order affecting the rights and apparatus of the statutory undertaker, the other provisions of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and the statutory undertaker are regulated by the provisions of Part 3 of the 1991 Act.

Commencement Information

I33Sch. 10 Pt. 4 para. 3 in force at 22.4.2022, see art. 1(2)

Apparatus of statutory undertakers in stopped up streetsE+W+S

4.  Without prejudice to the generality of any other protection afforded to the statutory undertaker elsewhere in the Order, where any street is stopped up under article 10 (public rights of way), if the statutory undertaker has any apparatus in the street or accessed via that street the statutory undertaker will be entitled to the same rights in respect of such apparatus as it enjoyed immediately before the stopping up and the undertaker will grant to the statutory undertaker, or will procure the granting to the statutory undertaker of, legal easements reasonably satisfactory to the specified statutory undertaker in respect of such apparatus and access to it prior to the stopping up of any such street but nothing in this paragraph affects any right of the undertaker or the statutory undertaker to require the removal of that apparatus under paragraph 7. Notwithstanding the temporary stopping up or diversion of any streets under the powers of articles 11 (temporary stopping up of public rights of way) and 12 (temporary stopping up of streets), the statutory undertaker will be at liberty at all times to take all necessary access across any such stopped up street and/or to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that street.

Commencement Information

I34Sch. 10 Pt. 4 para. 4 in force at 22.4.2022, see art. 1(2)

Acquisition of landE+W+S

5.—(1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not acquire any land interest or apparatus or override any easement and/or other interest of the statutory undertaker otherwise than by agreement.

(2) As a condition of agreement between the parties in paragraph 5(1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between the statutory undertaker and the undertaker) that are subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement and/or other legal or land interest of the statutory undertaker and/or affects the provisions of any enactment or agreement regulating the relations between the statutory undertaker and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as the statutory undertaker reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between the statutory undertaker and the undertaker acting reasonably and which must be no less favourable on the whole to the statutory undertaker unless otherwise agreed by the statutory undertaker, and it will be the responsibility of the undertaker to procure and/or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.

(3) The undertaker and the statutory undertaker agree that where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation and/or removal of apparatus/including but not limited to the payment of costs and expenses relating to such relocation and/or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by the statutory undertaker and/or other enactments relied upon by the statutory undertaker as of right or other use in relation to the apparatus, then the provisions in this Schedule shall prevail.

(4) Any agreement or consent granted by the statutory undertaker under paragraph 8 or any other paragraph of this Part of this Schedule, shall not be taken to constitute agreement under sub-paragraph 5(1).

Commencement Information

I35Sch. 10 Pt. 4 para. 5 in force at 22.4.2022, see art. 1(2)

Removal of apparatusE+W+S

6.—(1) If, in the exercise of the agreement reached in accordance with paragraph ‎5 or in any other authorised manner, the undertaker acquires any interest in or possesses temporarily any land in which any apparatus is placed, that apparatus must not be removed under this Part of this Schedule and any right of the statutory undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of the statutory undertaker in question in accordance with sub-paragraph ‎(2) to (5) inclusive.

(2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to the statutory undertaker advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order the statutory undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph ‎(3), afford to the statutory undertaker to its satisfaction (taking into account paragraph 7(1) below) the necessary facilities and rights—

(a)for the construction of alternative apparatus in other land of or land secured by the undertaker; and

(b)subsequently for the maintenance of that apparatus.

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the statutory undertaker must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to the requirement for the statutory undertaker to use its compulsory purchase powers to this end unless it elects to so do.

(4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the statutory undertaker and the undertaker.

(5) The statutory undertaker must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to the statutory undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.

Commencement Information

I36Sch. 10 Pt. 4 para. 6 in force at 22.4.2022, see art. 1(2)

Facilities and rights for alternative apparatusE+W+S

7.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for the statutory undertaker facilities and rights in land for the construction, use, maintenance and protection of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and the statutory undertaker and must be no less favourable on the whole to the statutory undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by the statutory undertaker.

(2) If the facilities and rights to be afforded by the undertaker and agreed with the statutory undertaker under paragraph 7(1) above in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to the statutory undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject in the matter will be referred to arbitration in accordance with paragraph 14 (Arbitration) of this Part of this Schedule and the arbitrator shall make such provision for the payment of compensation by the undertaker to the statutory undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Commencement Information

I37Sch. 10 Pt. 4 para. 7 in force at 22.4.2022, see art. 1(2)

Retained apparatus: Protection of National Grid as electricity undertakerE+W+S

8.—(1) Not less than 56 days before the commencement of any authorised works that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 6(2) or otherwise, the undertaker must submit to the statutory undertaker a plan of the works to be executed and seek from the statutory undertaker details of the underground extent of their electricity tower foundations.

(2) In relation to works which will or may be situated on, over, under or within (i) 15 metres measured in any direction of any apparatus, or (ii) involve embankment works within 15 metres of any apparatus, the plan to be submitted to the statutory undertaker under sub-paragraph ‎(1) must include a method statement and describe—

(a)the exact position of the works;

(b)the level at which these are proposed to be constructed or renewed;

(c)the manner of their construction or renewal including details of excavation, positioning of plant;

(d)the position of all apparatus;

(e)by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;

(f)any intended maintenance regimes; and

(g)an assessment of risks of rise of earth issues.

(3) In relation to any works which will or may be situated on, over, under or within 10 metres of any part of the foundations of an electricity tower or between any two or more electricity towers, the plan to be submitted under sub-paragraph ‎(1) must, in addition to the matters set out in sub-paragraph ‎(2), include a method statement describing—

(a)details of any cable trench design including route, dimensions, clearance to pylon foundations;

(b)demonstration that pylon foundations will not be affected prior to, during and post construction;

(c)details of load bearing capacities of trenches;

(d)details of cable installation methodology including access arrangements, jointing bays and backfill methodology;

(e)a written management plan for high voltage hazard during construction and ongoing maintenance of the cable route;

(f)written details of the operations and maintenance regime for the cable, including frequency and method of access;

(g)assessment of earth rise potential if reasonably required by the statutory undertaker’s engineers;

(h)evidence that trench bearing capacity is to be designed to 26 tonnes to take the weight of overhead line construction traffic.

(4) The undertaker must not commence any works to which sub-paragraphs (2) or (3) apply until the statutory undertaker has given written approval of the plan so submitted.

(5) Any approval of the statutory undertaker required under sub-paragraphs (2) or (3)—

(a)may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (6) or (8); and,

(b)must not be unreasonably withheld.

(6) In relation to any work to which sub-paragraphs (2) or (3) apply, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.

(7) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (5), as approved or as amended from time to time by agreement between the undertaker and the statutory undertaker and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs (6) or (8) by the statutory undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the statutory undertaker will be entitled to watch and inspect the execution of those works.

(8) Where the statutory undertaker requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to the statutory undertakers’ satisfaction prior to the commencement of any authorised works (or any relevant part thereof) for which protective works are required and the statutory undertaker must give 56 days’ notice of such works from the date of submission of a plan pursuant to this paragraph (except in an emergency).

(9) If the statutory undertaker in accordance with sub-paragraphs (6) or (8) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, [F1paragraphs 1 to 3] and ‎5 to ‎7 apply as if the removal of the apparatus had been required by the undertaker under paragraph 7(2).

(10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.

(11) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works and must—

(a)comply with sub-paragraphs (6), (7) and (8) insofar as is reasonably practicable in the circumstances; and

(b)comply with sub-paragraph (12) at all times.

(12) At all times when carrying out any works authorised under the Order, the undertaker must comply with the statutory undertaker’s policies for development near overhead lines EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”.

Textual Amendments

Commencement Information

I38Sch. 10 Pt. 4 para. 8 in force at 22.4.2022, see art. 1(2)

ExpensesE+W+S

9.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to the statutory undertaker on demand all charges, costs and expenses reasonably anticipated or incurred by the statutory undertaker in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Part of this Schedule including without limitation—

(a)any costs reasonably incurred by or compensation properly paid by the statutory undertaker in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs incurred by the statutory undertaker as a consequence of the statutory undertaker;

(i)using its own compulsory purchase powers to acquire any necessary rights under paragraph ‎6(3); and/or

(ii)exercising any compulsory acquisition powers in the Order transferred to or benefitting the statutory undertaker;

(b)in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;

(c)the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;

(d)the approval of plans;

(e)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;

(f)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.

(2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.

(3) If in accordance with the provisions of this Part of this Schedule—

(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 37 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the statutory undertaker by virtue of sub-paragraph (1) will be reduced by the amount of that excess save where it is not possible in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.

(4) For the purposes of sub-paragraph (3)—

(a)an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.

(5) An amount which apart from this sub-paragraph would be payable to the statutory undertaker in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the statutory undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Commencement Information

I39Sch. 10 Pt. 4 para. 9 in force at 22.4.2022, see art. 1(2)

IndemnityE+W+S

10.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of the statutory undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the statutory undertaker, or the statutory undertaker becomes liable to pay any amount to any third party, the undertaker must—

(a)bear and pay on demand the cost reasonably incurred by the statutory undertaker in making good such damage or restoring the supply; and

(b)indemnify the statutory undertaker for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the statutory undertaker, by reason or in consequence of any such damage or interruption or the statutory undertaker becoming liable to any third party as aforesaid other than arising from any default of the statutory undertaker.

(2) The fact that any act or thing may have been done by the statutory undertaker on behalf of the undertaker or in accordance with a plan approved by the statutory undertaker or in accordance with any requirement of the statutory undertaker or under its supervision does not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless the statutory undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.

(3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—

(a)any damage or interruption to the extent that it is attributable to the neglect or default of the statutory undertaker, its officers, servants, contractors or agents; and

(b)any authorised works and/or any other works authorised by this Part of this Schedule carried out by the statutory undertaker as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 of the Planning Act 2008 or article 5 (benefit of the Order) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this sub-paragraph (3)(b) will be subject to the full terms of this Part of this Schedule including this paragraph 10.

(4) The statutory undertaker must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.

Commencement Information

I40Sch. 10 Pt. 4 para. 10 in force at 22.4.2022, see art. 1(2)

Enactments and agreementsE+W+S

11.  Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between the statutory undertaker and the undertaker, nothing in this Part of this Schedule shall affect the provisions of any enactment or agreement regulating the relations between the undertaker and the statutory undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

Commencement Information

I41Sch. 10 Pt. 4 para. 11 in force at 22.4.2022, see art. 1(2)

Co-operationE+W+S

12.—(1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or the statutory undertaker requires the removal of apparatus under paragraph ‎6(2) or the statutory undertaker makes requirements for the protection or alteration of apparatus under paragraph 8, the undertaker shall use reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the statutory undertaker’s undertaking and the statutory undertaker shall use reasonable endeavours to co-operate with the undertaker for that purpose.

(2) For the avoidance of doubt whenever the statutory undertaker’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.

Commencement Information

I42Sch. 10 Pt. 4 para. 12 in force at 22.4.2022, see art. 1(2)

AccessE+W+S

13.  If in consequence of the agreement reached in accordance with paragraph ‎5(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable the statutory undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.

Commencement Information

I43Sch. 10 Pt. 4 para. 13 in force at 22.4.2022, see art. 1(2)

ArbitrationE+W+S

14.  Save for differences or disputes arising under paragraph ‎6(2), ‎6(4), ‎7(1), and 8 any difference or dispute arising between the undertaker and the statutory undertaker under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and the statutory undertaker, be determined by arbitration in accordance with article 37 (arbitration).

Commencement Information

I44Sch. 10 Pt. 4 para. 14 in force at 22.4.2022, see art. 1(2)

NoticesE+W+S

15.  The plans submitted to the statutory undertaker by the undertaker pursuant to paragraph 8(1) must be sent to National Grid Plant Protection at plantprotection@nationalgrid.com or such other address as the statutory undertaker may from time to time appoint instead for that purpose and notify to the undertaker in writing.

Commencement Information

I45Sch. 10 Pt. 4 para. 15 in force at 22.4.2022, see art. 1(2)

PART 5E+W+SProtection for East Anglia ONE North Limited

1.  For the protection of the statutory undertaker, the following provisions of this Schedule have effect unless otherwise agreed in writing between the undertaker and the statutory undertaker.E+W+S

Commencement Information

I46Sch. 10 Pt. 5 para. 1 in force at 22.4.2022, see art. 1(2)

2.  In this part of this schedule—E+W+S

alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of the statutory undertaker to enable the statutory undertaker in question to fulfil its statutory functions in a manner no less efficient than previously;

apparatus” means, electric lines or electrical plant as defined in the 1989 Act, belonging to, maintained by, or to be constructed by the statutory undertaker;

cable route disposal area(s)” means the disposal site reference(s) provided by the MMO in accordance with Schedule 14 (deemed licence under the 2009 Act – offshore transmission assets) to this Order and in the deemed marine licence in accordance with Schedule 14 (deemed licence under the 2009 Act – offshore transmission assets) to the East Anglia ONE North Order;

construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;

East Anglia ONE North” means the offshore wind farm to be constructed pursuant to the East Anglia ONE North Order including, whether pursuant to the East Anglia ONE North Order or otherwise, all elements of the connection of the wind farm to the National Grid at Friston;

East Anglia ONE North Order land” means the land within the Order limits defined in the East Anglia ONE North Order;

functions” includes powers and duties;

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;

“maintain” and “maintenance” include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of the statutory undertaker including construct, use, repair, alter, inspect, renew or remove the apparatus;

“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the specified works to be executed;

proposed East Anglia ONE North cable route” means the proposed route for any cables to serve East Anglia ONE North as shown on plans produced to the undertaker by the statutory undertaker pursuant to paragraph 11;

specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission or marine licence intended to operate in conjunction with this Order)—

(a)

as is within the East Anglia ONE North Order land; or

(b)

is in, on, under, over or within 750 metres of a proposed East Anglia ONE North cable route or existing apparatus seaward of MHWS;

statutory undertaker” means, in respect of the order land, and in relation to any apparatus, the statutory undertaker who owns and/or operates or has the power to construct the transmission assets under the East Anglia ONE North Order.

Commencement Information

I47Sch. 10 Pt. 5 para. 2 in force at 22.4.2022, see art. 1(2)

3.  This part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the statutory undertaker are regulated by the provisions of Part 3 of the 1991 Act.E+W+S

Commencement Information

I48Sch. 10 Pt. 5 para. 3 in force at 22.4.2022, see art. 1(2)

4.  The consent of the statutory undertaker under this Part is not required where the East Anglia ONE North Order has expired without the authorised development having been commenced pursuant to requirement 1 of Part 3 of Schedule 1 (requirements) to the East Anglia ONE North Order.E+W+S

Commencement Information

I49Sch. 10 Pt. 5 para. 4 in force at 22.4.2022, see art. 1(2)

Apparatus of undertakers in stopped up streetsE+W+S

5.  Notwithstanding the temporary stopping up or diversion of any highway under the powers of article 12 (temporary stopping up of streets), a statutory undertaker may be at liberty at all times to take all necessary access across any such stopped up highway and/or to execute and do all such works and things in, upon or under any such highway as may be reasonably necessary or desirable to enable it to construct any apparatus within that highway or maintain any apparatus which at the time of the stopping up or diversion was in that highway subject always to the undertaking of works by the undertaker authorised by the Order.

Commencement Information

I50Sch. 10 Pt. 5 para. 5 in force at 22.4.2022, see art. 1(2)

Acquisition of landE+W+S

6.  Regardless of any provision in the Order or anything shown on the land plan or contained in the book of reference to the Order, the undertaker must not acquire any interest in land or any apparatus or override any easement or other interest of the statutory undertaker otherwise than by agreement, such agreement not to be unreasonably withheld or delayed.

Commencement Information

I51Sch. 10 Pt. 5 para. 6 in force at 22.4.2022, see art. 1(2)

Removal of apparatusE+W+S

7.—(1) If, in the exercise of the agreement reached in accordance with paragraph 6 or in any other authorised manner, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be removed and any right of a statutory undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of the statutory undertaker in accordance with sub-paragraph (2) to (5) inclusive.

(2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under the Order, the undertaker requires the removal of any apparatus placed in that land, it must give to the statutory undertaker 56 days’ advance written notice of that requirement (or such lesser period of notice agreed by the statutory undertaker, acting reasonably), together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by the Order a statutory undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the statutory undertaker to their reasonable satisfaction (taking into account paragraph 8(1) below) the necessary facilities and rights—

(a)for the construction of alternative apparatus in other land of the undertaker; and

(b)subsequently for the maintenance of that apparatus.

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the statutory undertaker must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed except that this obligation does not extend to the requirement for the statutory undertaker to use its compulsory purchase powers to this end unless it elects to so do.

(4) Any alternative apparatus to be constructed in land of the undertaker must be constructed in such manner and in such line or situation as may be reasonably agreed between the statutory undertaker and the undertaker.

(5) The statutory undertaker must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to the statutory undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions hereof.

Commencement Information

I52Sch. 10 Pt. 5 para. 7 in force at 22.4.2022, see art. 1(2)

Facilities and rights for alternative apparatusE+W+S

8.—(1) Where, in accordance with the provisions hereof, the undertaker affords to a statutory undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be reasonably agreed between the undertaker and the statutory undertaker and must be no less favourable on the whole to the statutory undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless agreed by the statutory undertaker (acting reasonably).

(2) If the facilities and rights to be afforded by the undertaker and agreed with the statutory undertaker under paragraph 8(1) above in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the statutory undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that statutory undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Commencement Information

I53Sch. 10 Pt. 5 para. 8 in force at 22.4.2022, see art. 1(2)

Retained apparatus: protectionE+W+S

9.—(1) Not less than 56 days (or such lesser period agreed by the statutory undertaker, acting reasonably) before commencing the execution of any specified works authorised by the Order which do not require the removal of apparatus in accordance with paragraph 7(2), the undertaker must submit to the statutory undertaker a plan.

(2) In relation to specified works which will or may be situated on, over, under or within five metres measured in any direction of any apparatus, or involve embankment works within 5 metres of any apparatus, the plan to be submitted to the statutory undertaker under sub-paragraph (1) must be detailed including a material statement and describing—

(a)the exact position of the works;

(b)the level at which these are proposed to be constructed or renewed;

(c)the manner of their construction or renewal including details of excavation and positioning of plant;

(d)the position of all apparatus; and

(e)by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus.

(3) The undertaker must not commence the construction or renewal of any specified works to which sub-paragraph (1) or (2) applies until the statutory undertaker has given written approval of the plan so submitted.

(4) Any approval of the statutory undertaker required under sub-paragraph (3)—

(a)may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (5), (7) or (8);

(b)must not be unreasonably withheld or delayed.

(5) In relation to a specified work to which sub-paragraph (1) or (2) applies, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus provided that such modifications are made within a period of 56 days beginning with the date on which the plan under sub-paragraph (1) is submitted to it (or such lesser period agreed by the statutory undertaker, acting reasonably). For the avoidance of doubt, provided that any further iterations of the plan submitted to the statutory undertaker for approval as a result of modifications required under this paragraph are not materially different to the modifications previously made by the statutory undertaker, any further required modifications will be made by the statutory undertaker as soon as reasonably practicable thereafter and in any event within 21 days of receipt of any further plans.

(6) Specified works executed under the Order must be executed only in accordance with the plan, submitted under sub-paragraph (1) or as [F2relevant sub-paragraph (2)], as amended from time to time by agreement between the undertaker and the statutory undertaker and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (5) or (7) by the statutory undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the statutory undertaker is entitled to watch and inspect the execution of those works.

(7) Where the statutory undertaker requires any protective works to be carried out either themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to the statutory undertaker’s satisfaction prior to the carrying out of any specified works authorised by the Order or any relevant part thereof (unless otherwise agreed by the statutory undertaker, acting reasonably) and the statutory undertaker must give notice of such works as soon as reasonably practicable and in any event within 56 days from the date of submission of a plan in line with sub-paragraph (1) or (2) (except in an emergency).

(8) In relation to a specified work to which sub-paragraph (1) or (2) applies, it is reasonable for a statutory undertaker to require as a condition of granting approval that the undertaker enter into a cable proximity agreement on reasonable terms reflecting industry good practice.

(9) If a statutory undertaker in accordance with sub-paragraph (5) or (7) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 6 to 8 apply as if the removal of the apparatus had been required by the undertaker under paragraph 7(2).

(10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any specified works (unless otherwise agreed by the statutory undertaker, acting reasonably), a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.

(11) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works and must comply with sub-paragraph (5), (6) and (7) insofar as is reasonably practicable in the circumstances.

Textual Amendments

Commencement Information

I54Sch. 10 Pt. 5 para. 9 in force at 22.4.2022, see art. 1(2)

Offshore disposalsE+W+S

10.—(1) The undertaker must—

(a)consult the statutory undertaker in relation to any draft disposal plan or similar which proposes to deposit material within the cable route disposal area(s) at least 56 days prior to the submission of the draft plan or similar to the MMO; and

(b)make such amendments as are reasonably requested by the statutory undertaker within 30 days following receipt of the draft plan by the statutory undertaker prior to submission of the draft disposal plan or similar to the MMO for approval.

(2) Subject to complying with all relevant health and safety considerations, the undertaker must permit representatives of the statutory undertaker on any vessel carrying out dredging or disposal activities related to the cable route disposal area(s) to monitor and verify the dredging and disposal carried out in terms of location, method, timing, quantity, nature of materials and other relevant matters.

(3) Unless otherwise agreed, the undertaker must give at least 21 days’ notice in writing to the statutory undertaker of the intended departure of all vessels referred to in sub-paragraph (2) together with written information concerning the proposed dredging and disposal activities and must comply with all reasonable requests from the statutory undertaker to enable the verification referred to in that sub-paragraph to be carried out effectively and efficiently.

(4) The undertaker must provide to the statutory undertaker a copy of each disposal return required to be submitted to the MMO pursuant to the approved disposal plan or similar under this Order relevant to the cable route disposal area(s) within ten days of submission to the MMO, such returns to include, without limitation, the actual volumes of materials disposed of, the disposal locations, the approved monitoring plan and the results of monitoring conducted.

Commencement Information

I55Sch. 10 Pt. 5 para. 10 in force at 22.4.2022, see art. 1(2)

Provision of informationE+W+S

11.—(1) To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order request up-to-date written confirmation from the statutory undertaker of the precise route of any existing installed apparatus and any proposed East Anglia ONE North cable route or other apparatus to be installed by the statutory undertaker.

(2) Within 56 days following receipt of a request under sub-paragraph (1), the statutory undertaker must provide the requested information to the extent that such information is available.

Commencement Information

I56Sch. 10 Pt. 5 para. 11 in force at 22.4.2022, see art. 1(2)

ExpensesE+W+S

12.—(1) Subject to the following provisions of this paragraph, the undertaker must repay to the statutory undertaker on demand all charges, costs and expenses reasonably and properly incurred by that statutory undertaker in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to herein including without limitation—

(a)any costs reasonably incurred or compensation properly paid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation in the event that the statutory undertaker elects to use powers of compulsory acquisition to acquire any necessary rights under paragraph 7(3) all costs incurred as a result of such action;

(b)in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;

(c)the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;

(d)the approval of plans;

(e)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;

(f)the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to herein.

(2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions hereof and which is not re-used as part of the alternative apparatus, that value being calculated after removal.

(3) If in accordance with the provisions hereof—

(a)apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or in default of agreement settled by arbitration in accordance with article 37 (arbitration) of the Order to be necessary, then, if such placing involves cost in the construction of works under the provisions hereof exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the statutory undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess save where it is not possible in the circumstances to obtain the existing type of operations, capacity, dimensions or place at the existing depth in which case full costs must be borne by the undertaker.

(4) For the purposes of sub-paragraph (3)—

(a)an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.

(5) An amount which apart from this sub-paragraph would be payable to the statutory undertaker in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the statutory undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Commencement Information

I57Sch. 10 Pt. 5 para. 12 in force at 22.4.2022, see art. 1(2)

CompensationE+W+S

13.—(1) Subject to sub-paragraphs (2), (3) and (4), if by reason or in consequence of the construction of any such works authorised herein or in consequence of the construction, use, maintenance or failure of any of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under the provisions herein or any subsidence resulting from any of these works), any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of the statutory undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the statutory undertaker, or the statutory undertaker becomes liable to pay any amount to any third party, the undertaker must—

(a)bear and pay on demand the cost reasonably incurred by the statutory undertaker in making good such damage or restoring the supply; and

(b)compensate the statutory undertaker for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the statutory undertaker, by reason or in consequence of any such damage or interruption or the statutory undertaker becoming liable to any third party in accordance with the provisions of this part.

(2) The fact that any act or thing may have been done by the statutory undertaker on behalf of the undertaker or in accordance with a plan approved by the statutory undertaker or in accordance with any requirement of the statutory undertaker or under its supervision does not (subject to sub-paragraph (3)), excuse the undertaker from liability under the provisions of this paragraph.

(3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the neglect or default of the statutory undertaker, its officers, servants, contractors or agents.

(4) The statutory undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without first consulting the undertaker and considering their representations (such representations not to be unreasonably withheld or delayed).

Commencement Information

I58Sch. 10 Pt. 5 para. 13 in force at 22.4.2022, see art. 1(2)

Enactments and agreementsE+W+S

14.  Nothing herein affects the provisions of any enactment or agreement regulating the relations between the undertaker and the statutory undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which the Order is made.

Commencement Information

I59Sch. 10 Pt. 5 para. 14 in force at 22.4.2022, see art. 1(2)

Co-operationE+W+S

15.  Where in consequence of the proposed construction of any of the authorised development, the undertaker or the statutory undertaker requires the removal of apparatus under paragraph 7(2) or a statutory undertaker makes requirements for the protection or alteration of apparatus under paragraph 9 the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the statutory undertaker’s undertaking and the statutory undertaker must use its best endeavours to co-operate with the undertaker for that purpose.

Commencement Information

I60Sch. 10 Pt. 5 para. 15 in force at 22.4.2022, see art. 1(2)

AccessE+W+S

16.  If in consequence of the agreement reached in accordance with paragraph 6 or the powers granted under the Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as enables the statutory undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.

Commencement Information

I61Sch. 10 Pt. 5 para. 16 in force at 22.4.2022, see art. 1(2)

ArbitrationE+W+S

17.  Any difference or dispute arising between the undertaker and the statutory undertaker must, unless otherwise agreed in writing between the undertaker and the statutory undertaker, be determined by arbitration in accordance with article 37 (arbitration) of the Order.

Commencement Information

I62Sch. 10 Pt. 5 para. 17 in force at 22.4.2022, see art. 1(2)

PART 6E+W+SProtection for East Anglia ONE Offshore Wind Farm and East Anglia THREE Offshore Wind Farm

1.  For the protection of the statutory undertakers referred to in this part of this Schedule the following provisions have effect unless otherwise agreed in writing between the undertaker and the statutory undertaker concerned.E+W+S

Commencement Information

I63Sch. 10 Pt. 6 para. 1 in force at 22.4.2022, see art. 1(2)

2.  In this part of this schedule—E+W+S

apparatus” means electric lines or electrical plant (as defined in the 1989 Act) belonging to or maintained by the statutory undertaker;

“plan” or “plans” includes all designs, drawings, specifications, method statements, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;

specified works” means works authorised by this Order (or authorised by any marine licence intended to operate in conjunction with this Order) that are to be carried out within 750 metres of apparatus belonging to a statutory undertaker; and

statutory undertaker” means, as appropriate—

(a)

the statutory undertaker who owns and/or operates the transmission assets under the East Anglia ONE Offshore Wind Farm Order 2014(3);

(b)

the statutory undertaker who owns and/or operates the transmission assets under the East Anglia THREE Offshore Wind Farm Order 2017(4).

Commencement Information

I64Sch. 10 Pt. 6 para. 2 in force at 22.4.2022, see art. 1(2)

3.—(1) Not less than 56 days (or such lesser period agreed by the statutory undertaker, acting reasonably) before commencing the execution of any specified works, the undertaker must submit to the statutory undertaker a plan.E+W+S

(2) The undertaker must not commence the construction or renewal of any works to which sub-paragraph (1) applies until the statutory undertaker has given written approval of the plan so submitted.

(3) Any approval of the statutory undertaker required under sub-paragraph (2)—

(a)may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (4), (6) or (7);

(b)must not be unreasonably withheld or delayed.

(4) In relation to a work to which sub-paragraph (1) applies, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus provided that such modifications are made within a period of 56 days beginning with the date on which the plan under sub-paragraph (1) is submitted to it (or such lesser period agreed by the statutory undertaker, acting reasonably). For the avoidance of doubt, provided that any further iterations of the plan submitted to the statutory undertaker for approval as a result of modifications required under this paragraph are not materially different to the modifications previously made by the statutory undertaker, any further required modifications will be made by the statutory undertaker as soon as reasonably practicable thereafter and in any event within 21 days of receipt of any further plans.

(5) Specified works executed under this Order must be executed only in accordance with the plan, submitted under sub-paragraph (1), as amended from time to time by agreement between the undertaker and the statutory undertaker and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (4) or (6) by the statutory undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the statutory undertaker is entitled to watch and inspect the execution of those works.

(6) Where the statutory undertaker requires any protective works to be carried out either themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to the statutory undertaker’s satisfaction prior to the carrying out of any specified works authorised by this Order or any relevant part thereof (unless otherwise agreed by the statutory undertaker, acting reasonably) and the statutory undertaker must give notice of such works as soon as reasonably practicable and in any event within 56 days from the date of submission of a plan in line with sub-paragraph (1) (except in an emergency).

(7) In relation to a specified work to which sub-paragraph (1) applies, it is reasonable for a statutory undertaker to require as a condition of granting approval that the undertaker enter into a cable proximity agreement on reasonable terms reflecting industry good practice.

(8) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any works (unless otherwise agreed by the statutory undertaker, acting reasonably), a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.

(9) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works and must comply with sub-paragraph (4) and (6) insofar as is reasonably practicable in the circumstances.

Commencement Information

I65Sch. 10 Pt. 6 para. 3 in force at 22.4.2022, see art. 1(2)

ExpensesE+W+S

4.  Subject to the following provisions of this paragraph, the undertaker must repay to the statutory undertaker on demand all charges, costs and expenses reasonably and properly incurred by that statutory undertaker in, or in connection with, the inspection, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to herein including without limitation—

(a)the approval of plans;

(b)the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;

(c)the survey of apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to herein.

Commencement Information

I66Sch. 10 Pt. 6 para. 4 in force at 22.4.2022, see art. 1(2)

CompensationE+W+S

5.—(1) Subject to sub-paragraphs (2), (3) and (4), if by reason or in consequence of the construction of any such works authorised herein or in consequence of the construction, use, maintenance or failure of any of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, including without limitation works carried out by the undertaker under the provisions herein or any subsidence resulting from any of these works), any damage is caused to any apparatus of the statutory undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the statutory undertaker, or the statutory undertaker becomes liable to pay any amount to any third party, the undertaker must—

(a)bear and pay on demand the cost reasonably incurred by the statutory undertaker in making good such damage or restoring the supply; and

(b)compensate the statutory undertaker for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the statutory undertaker, by reason or in consequence of any such damage or interruption or the statutory undertaker becoming liable to any third party in accordance with the provisions of this part.

(2) The fact that any act or thing may have been done by the statutory undertaker on behalf of the undertaker or in accordance with a plan approved by the statutory undertaker or in accordance with any requirement of the statutory undertaker or under its supervision does not (subject to sub-paragraph (3)), excuse the undertaker from liability under the provisions of this paragraph.

(3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the neglect or default of the statutory undertaker, its officers, servants, contractors or agents.

(4) The statutory undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without first consulting the undertaker and considering their representations (such representations not to be unreasonably withheld or delayed).

Commencement Information

I67Sch. 10 Pt. 6 para. 5 in force at 22.4.2022, see art. 1(2)

Co-operationE+W+S

6.  Where in consequence of the proposed construction of any of the authorised development, a statutory undertaker makes requirements for the protection or alteration of apparatus under paragraph 3 the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the statutory undertaker’s undertaking and the statutory undertaker must use its best endeavours to co-operate with the undertaker for that purpose.

Commencement Information

I68Sch. 10 Pt. 6 para. 6 in force at 22.4.2022, see art. 1(2)

ArbitrationE+W+S

7.  Any difference or dispute arising between the undertaker and the statutory undertaker must, unless otherwise agreed in writing between the undertaker and the statutory undertaker, be determined by arbitration in accordance with article 37 (arbitration) of the Order.

Commencement Information

I69Sch. 10 Pt. 6 para. 7 in force at 22.4.2022, see art. 1(2)

PART 7E+W+SProtection for EDF Energy

ApplicationE+W+S

1.  For the protection of EDF Energy the following provisions of this Schedule shall have effect unless otherwise agreed in writing between the undertaker and EDF Energy.

Commencement Information

I70Sch. 10 Pt. 7 para. 1 in force at 22.4.2022, see art. 1(2)

InterpretationE+W+S

2.  In this Part of this Schedule—

EDF Energy” means EDF Energy Nuclear Generation Limited (company number 03076445);

HDD punch out” means the location where the drilling bit associated with the HDD exits out of the pilot hole on the seabed;

utility apparatus” includes water mains, pipes, electricity or telecommunication cables, or other apparatus belonging to or maintained by a statutory undertaker.

Commencement Information

I71Sch. 10 Pt. 7 para. 2 in force at 22.4.2022, see art. 1(2)

Interaction at Sizewell GapE+W+S

3.—(1) The undertaker shall consult with EDF Energy in the preparation of the Sizewell Gap construction method statement prior to submission of the Sizewell Gap construction method statement to the relevant planning authority for approval in accordance with requirement 22.

(2) The undertaker shall consult with EDF Energy in the preparation of—

(a)the access management plan, to the extent that it relates to Work Nos. 10, 11 or 15; and

(b)the construction traffic management plan, to the extent that it relates to Work Nos. 10 or 15,

prior to the submission of each plan to the relevant highway authority for approval in accordance with requirements 16 and 28 respectively.

(3) Prior to carrying out any of Work Nos. 10, 11 and or 15, the undertaker shall carry out surveys to establish the location of all utility apparatus within these areas which has the potential to provide services to EDF Energy.

(4) In the event of any damage to any utility apparatus which provides services to EDF Energy within the area of Work Nos. 10, 11 and 15, the undertaker shall immediately inform EDF Energy and shall use best endeavours to secure the repair of any damage within 24 hours.

Commencement Information

I72Sch. 10 Pt. 7 para. 3 in force at 22.4.2022, see art. 1(2)

Quality of Sizewell B cooling water intakeE+W+S

4.—(1) Save for urgent reasons of vessel safety which mean there is insufficient time to comply with this sub-paragraph, in which case the undertaker shall use its reasonable endeavours to contact EDF Energy immediately to inform of non-compliance by a mechanism previously agreed in writing with EDF Energy, all operations carried out by the undertaker must avoid the area labelled “Sizewell B Tidally Restricted Shallow Water Area / [F3Vessel Transit and Loading] Exclusion Zone” and coloured purple on the Activity Exclusion Zones plan (Drawing No. EA2-DEV-DRG-IBR-001259).

(2) Sub-paragraph (1) applies unless EDF Energy otherwise agrees in writing either a modification of the procedure described above or an alternative protective measure and that alternative method is shown to be of no greater risk to the Sizewell B intake and its function (such agreement not to be unreasonably withheld or delayed).

Textual Amendments

Commencement Information

I73Sch. 10 Pt. 7 para. 4 in force at 22.4.2022, see art. 1(2)

Coralline CragE+W+S

5.—(1) The undertaker shall consult with EDF Energy in the preparation of the landfall construction method statement prior to submission of the landfall construction method statement to the relevant planning authority for approval in accordance with requirement 13.

(2) Prior to carrying out Work No. 6, the undertaker shall carry out geophysical surveys to confirm the visible extent of the Coralline Crag formation and shall provide the results of such surveys to the extent that they demonstrate the visible extent of the Coralline Crag to EDF Energy on completion.

(3) The undertaker must not undertake cable trenching activities or locate the HDD punch out within—

(a)the Punch Out and Trenching Restriction Area shown on the Activity Exclusion Zones plan (Drawing No. EA2-DEV-DRG-IBR-001259); or

(b)the visible extent of the Coralline Crag as confirmed by the surveys undertaken under sub-paragraph (2),

unless otherwise agreed with EDF Energy (such agreement not to be unreasonably withheld or delayed).

Commencement Information

I74Sch. 10 Pt. 7 para. 5 in force at 22.4.2022, see art. 1(2)

ArbitrationE+W+S

6.  Any difference or dispute arising between EDF Energy and the undertaker must, unless otherwise agreed in writing between EDF Energy and the undertaker, be determined by arbitration in accordance with article 37 (arbitration) of the Order.

Commencement Information

I75Sch. 10 Pt. 7 para. 6 in force at 22.4.2022, see art. 1(2)

PART 8E+W+SProtection of NNB Generation Company (SZC) Limited

ApplicationE+W+S

1.  For the protection of SZC Co. the following provisions of this Schedule have effect unless otherwise agreed in writing between the undertaker and SZC Co.

Commencement Information

I76Sch. 10 Pt. 8 para. 1 in force at 22.4.2022, see art. 1(2)

InterpretationE+W+S

2.  In this Part of this Schedule—

“SZC Co.” means NNB Generation Company (SZC) Limited (company number 09284825).

Commencement Information

I77Sch. 10 Pt. 8 para. 2 in force at 22.4.2022, see art. 1(2)

Interaction at Sizewell GapE+W+S

3.  The undertaker shall consult with SZC Co. in the preparation of the Sizewell Gap construction method statement, to the extent that it relates to Work No. 15, prior to submission of the Sizewell Gap construction method statement to the relevant planning authority for approval in accordance with requirement 22.

Commencement Information

I78Sch. 10 Pt. 8 para. 3 in force at 22.4.2022, see art. 1(2)

Interaction at Snape RoadE+W+S

4.  The undertaker shall consult with SZC Co. in the formulation of the proposed method of working and timing of execution of works within the area of Work No. 35, prior to Work No. 35 commencing.

Commencement Information

I79Sch. 10 Pt. 8 para. 4 in force at 22.4.2022, see art. 1(2)

Interaction at Friday StreetE+W+S

5.  The undertaker shall consult with SZC Co. in the formulation of the proposed method of working and timing of execution of works within the area of Work No. 36, prior to Work No.36 commencing.

Commencement Information

I80Sch. 10 Pt. 8 para. 5 in force at 22.4.2022, see art. 1(2)

Sizewell C proposed intake infrastructureE+W+S

6.—(1) Save for urgent reasons of vessel safety and subject to sub-paragraph (2), the undertaker shall not carry out any of the authorised project (including the placement temporary or otherwise of anchors or moorings) within the area labelled “Overlap of Sizewell C Order limits with East Anglia TWO Order limits” and hatched purple on the Sizewell C Order Limits Interaction – Offshore Plan (Drawing No. EA2-DEV-DRG-IBR-001284) without having first submitted to and secured approval from SZC Co. details of the proposed method of working within these areas (such approval not to be unreasonably withheld or delayed) and thereafter the undertaker shall implement the authorised project in full accordance with such approved details.

(2) Nothing in this paragraph shall prevent the passage of vessels within the area specified in sub-paragraph (1) prior to the construction of any works within that location by SZC Co. at any time.

Commencement Information

I81Sch. 10 Pt. 8 para. 6 in force at 22.4.2022, see art. 1(2)

Acquisition of landE+W+S

7.  Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not, to the extent that the exercise of such powers relates to the carrying out of Work Nos. 15, 35 or 36, acquire any land interest or rights or impose restrictive covenants over land belonging to SZC Co. and may not override or extinguish any easement and/or other rights or interests of SZC Co. otherwise than by agreement.

Commencement Information

I82Sch. 10 Pt. 8 para. 7 in force at 22.4.2022, see art. 1(2)

ArbitrationE+W+S

8.  Any difference or dispute arising between SZC Co. and the undertaker must, unless otherwise agreed in writing between SZC Co. and the undertaker, be determined by arbitration in accordance with article 37 (arbitration) of the Order.

Commencement Information

I83Sch. 10 Pt. 8 para. 8 in force at 22.4.2022, see art. 1(2)