37.—(1) The Company must notify National Highways of the intended date of opening to the public of the railway authorised by the Order not less than 56 days in advance of the intended date and the Company must notify National Highways of the actual date the NH works will be brought into operation within 14 days of that date.
(2) The level crossing must not be opened for traffic until all such works as are set out in any agreement entered into pursuant to paragraph 30 are completed in accordance with the terms of the agreement and any traffic regulation measures pursuant to paragraph 31(1)(d) are in force.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: