222.—(1) Before carrying out any works forming part of the authorised development on any part of the Sembcorp Protection Corridor, the undertaker (or any contractor carrying out such works on behalf of the undertaker) must put in place a policy of insurance with a reputable insurer for a sum not less than such level as may be agreed in writing between the undertaker and Sembcorp, and evidence of that insurance must be provided to Sembcorp on request.
(2) Not less than 90 days before carrying out any works forming part of the authorised development on any part of the Sembcorp Protection Corridor or before proposing to change the terms of the insurance policy, the undertaker must notify Sembcorp of details of the terms or cover of the insurance policy that it proposes to put in place including the proposed level of the cover to be provided.
(3) The undertaker (or any contractor carrying out such works on behalf of the undertaker) must maintain insurance in relation to works or the use of the authorised development affecting the Sembcorp Protection Corridor during the operation of the authorised development at such level as may be agreed in writing between the undertaker and Sembcorp.
(4) Any dispute between the undertaker and Sembcorp regarding the terms, cover or insured level of the insurance policy shall be resolved in accordance with paragraph 226.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: