The Net Zero Teesside Order 2024

Consent of restricted works under this Part

90.—(1) Unless a shorter period is otherwise agreed in writing between the undertaker and Exolum, not less than thirty five (35) days before commencing the execution of any restricted works, the undertaker must submit to Exolum the works details for the restricted works and such further particulars as Exolum may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

(2) No restricted works are to be commenced until the works details in respect of those works submitted under sub-paragraph (1) have been approved by Exolum.

(3) Any approval of Exolum required under this paragraph 90 must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as Exolum may require to be made for—

(a)the continuing safety and operational viability of the Exolum operations; and

(b)the requirement for Exolum to have reasonable access with or without vehicles to inspect, repair, replace and maintain and ensure the continuing safety and operation or viability of the Exolum operations.

(4) Any approval of Exolum required under this paragraph 90 including any reasonable requirements required by Exolum under sub-paragraph (3), must be made in writing within a period of 21 days (unless a shorter period is otherwise agreed in writing between the undertaker and Exolum) beginning with the date on which the works details were submitted to Exolum under sub-paragraph (1) or the date on which any further particulars requested by Exolum under sub-paragraph (1) were submitted to Exolum (whichever is the later).

(5) The authorised development must be executed only in accordance with the works details approved by Exolum under this paragraph 90 including any reasonable requirements notified to the undertaker in accordance with sub-paragraph (3) and Exolum shall be entitled to watch and inspect the execution of those works.

(6) If Exolum in accordance with sub-paragraph (3) and in consequence of the restricted works proposed by the undertaker, reasonably requires the removal of any of the Exolum operations and gives written notice to the undertaker of that requirement, this Order applies as if the removal of the apparatus had been required by the undertaker under sub-paragraph (1).

(7) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but (unless otherwise agreed in writing between the undertaker and Exolum) in no case less than 28 days before commencing the execution of any restricted works, new works details, instead of the works details previously submitted, and having done so the provisions of this paragraph 90 apply to and in respect of the new works details.