xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 10Protective provisions

PART 4For the protection of National Gas Transmission plc as gas undertaker

Indemnity

41.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any works authorised by this Part of this Schedule or in consequence of the construction, use maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of National Gas Transmission, or there is any interruption in any service provided, or in the supply of any goods or energy, by National Gas Transmission, or National Gas Transmission becomes liable to pay any amount to any third party, and provided that at all times National Gas Transmission will be under an obligation to take reasonable steps to mitigate its loss, the undertaker will—

(a)bear and pay on demand accompanied by an appropriately detailed invoice or appropriately detailed claim from National Gas Transmission the cost reasonably and properly incurred by National Gas Transmission in making good such damage or restoring the supply; and

(b)indemnify National Gas Transmission for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from National Gas Transmission, by reason or in consequence of any such damage or interruption or National Gas Transmission becoming liable to any third party and including Network Code Claims other than arising from any default of National Gas Transmission.

(2) The fact that any act or thing may have been done by National Gas Transmission on behalf of the undertaker or in accordance with a plan approved by National Gas Transmission or in accordance with any requirement of National Gas Transmission or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless National Gas Transmission fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.

(3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of-

(a)any damage or interruption to the extent that it is attributable to the neglect or default of National Gas Transmission, its officers, servants, contractors or agents;

(b)any authorised works and/or any other works authorised by this Part of this Schedule carried out by National Gas Transmission as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 of the Planning Act 2008 or article 7 (benefit of the Order) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this sub-section 3(b) will be subject to the full terms of this Part of this Schedule including this paragraph 41; and/or

(c)any indirect or consequential loss of any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption, which is not reasonably foreseeable;

(4) National Gas Transmission must give the undertaker reasonable notice of any such third party claim or demand and no settlement, admission of liability or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.

(5) National Gas Transmission must, in respect of any matter covered by the indemnity given by the undertaker in this paragraph, at all times act reasonably and in the same manner as it would as if settling third party claims on its own behalf from its own funds.

(6) National Gas Transmission must use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies where it is within National Gas Transmission’s reasonable ability and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of National Gas Transmission’s control and if reasonably requested to do so by the undertaker National Gas Transmission must provide an explanation of how the claim has been minimised, where relevant.

(7) Not to commence construction (and not to permit the commencement of such construction) of the authorised works on any land owned by National Gas Transmission or in respect of which National Gas Transmission has an easement or wayleave for its apparatus or any other interest or to carry out any works within 15 metres of National Gas Transmission’s apparatus until the following conditions are satisfied:

(a)unless and until National Gas Transmission is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has first provided the acceptable security (and provided evidence that it shall maintain such acceptable security for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and National Gas Transmission has confirmed the same to the undertaker in writing; and

(b)unless and until National Gas Transmission is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has procured acceptable insurance (and provided evidence to National Gas Transmission that it shall maintain such acceptable insurance for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and National Gas Transmission has confirmed the same in writing to the undertaker.

(8) In the event that the undertaker fails to comply with 11(7) of this Part of this Schedule, nothing in this Part of this Schedule shall prevent National Gas Transmission from seeking injunctive relief (or any other equitable remedy) in any court of competent jurisdiction.