PART 12Development with Significant Transboundary Effects

Projects in F3an EEA State likely to have significant transboundary effects57

1

Where the Welsh Ministers receive from F4an EEA StateF5... information which that EEA State has gathered from the developer of a proposed project in that EEA State, which is likely to have significant effects on the environment in Wales, they mustF6...—

a

enter into consultations with that EEA State regarding the potential significant effects of the proposed project on the environment in Wales and the measures envisaged to reduce or eliminate such effects; and

b

determine in agreement with that EEA State a reasonable period, before development consent for the project is granted, during which members of the public in Wales may submit to the competent authority in that EEA State representations F7....

2

The Welsh Ministers must also—

a

arrange for the information referred to in paragraph (1) to be made available, within a reasonable time and for a time period of no less than 30 days, both to the authorities in Wales which are likely to be concerned by the project by reason of their specific environmental responsibilities, and to the public concerned in Wales;

b

ensure that those authorities and the public concerned are given an opportunity, before development consent for the project is granted, to forward to the F1authority in the relevant EEA State which that state has designated as responsible for performing the duties arising from the Directive, within a reasonable time, their opinion on the information supplied; and

c

make available to the public concerned any information received from the F2authority in the relevant EEA State which that state has designated as responsible for performing the duties arising from the Directive.