SCHEDULE 1
PART 1 Authorised Works
PART 2 Further Works
CHAPTER 1
1.The undertaker may within the offshore Order limits construct maintain...
2.The undertaker may within the onshore Order limits construct maintain...
CHAPTER 2
PART 3 Area for Tidal Works
Array Area, export cable corridor, and restricted areas
PART 4 Documents to be submitted and approved by the Welsh Ministers
SCHEDULE 2
Additional land which may be acquired or used
SCHEDULE 3
Streets Subject to Street Works
SCHEDULE 4
Streets to be Temporarily Stopped Up
SCHEDULE 5
Access to Works
SCHEDULE 6
PART 1 Land in which only new rights may be acquired
PART 2 Land over which restrictive covenants may be imposed
SCHEDULE 7
Modification of Compensation and Compulsory Purchase Enactments for Creation of New Rights and the Imposition of Restrictive Covenants
1.Compensation enactments
2.(1) Without limitation on the scope of paragraph 1, the...
3.(1) Without prejudice to the generality of paragraph 1, the...
4.Application of the 1965 Act
5.(1) For section 7 of the 1965 Act (measure of...
6.The 1981 Act
7.(1) The modifications referred to in paragraph 6(1)(a) are as...
SCHEDULE 8
Land of which only subsoil more than 9 metres beneath surface may be acquired
SCHEDULE 9
Land of which Temporary Possession may be taken
SCHEDULE 10
Provisions relating to Statutory Undertakers etc
1.Apparatus of statutory undertakers etc on land acquired
2.Apparatus of statutory undertakers etc in stopped up streets
3.Railway and navigation undertakings
SCHEDULE 11
Protective Provisions
PART 1 Protection of electricity, gas, water and sewerage undertakers
1.The provisions of this Part have effect unless otherwise agreed...
2.In this Part— “alternative apparatus” means alternative apparatus adequate to...
3.This Part does not apply to— (a) apparatus in respect...
4.Despite any provision in this Order or anything shown on...
5.(1) If, in the exercise of the powers conferred by...
6.(1) Where, in accordance with this Part, the undertaker affords...
7.(1) Not less than 28 days before starting the execution...
8.(1) Subject to the provisions of this paragraph, the undertaker...
9.(1) Subject to sub-paragraphs (2) and (3), if by reason...
10.Nothing in this Part affects the provisions of any enactment...
PART 2 Protection of Network Rail Infrastructure Limited
11.The provisions of this Part have effect unless otherwise agreed...
12.In this Part— “construction” includes execution, placing, alteration and reconstruction...
13.(1) Where under this Part Network Rail is required to...
14.(1) The undertaker must not exercise the powers conferred by—...
15.(1) The undertaker must before commencing construction of any specified...
16.(1) Any specified work and any protective works to be...
17.The undertaker must— (a) at all times afford reasonable facilities...
18.Network Rail must at all times afford reasonable facilities to...
19.(1) If any permanent or temporary alterations or additions to...
20.The undertaker must repay to Network Rail all reasonable fees,...
21.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
22.If at any time after the completion of a specified...
23.The undertaker must not provide any illumination or illuminated sign...
24.Any additional expenses that Network Rail may reasonably incur in...
25.(1) The undertaker must pay to Network Rail all reasonable...
26.Network Rail must, on receipt of a request from the...
27.In the assessment of any sums payable to Network Rail...
28.The undertaker and Network Rail may, subject in the case...
29.Nothing in this Order, or in any enactment incorporated with...
30.The undertaker must, no later than 28 days from the...
PART 3 Protection of operators of electronic communications code networks
31.(1) The provisions of this Part have effect unless otherwise...
32.The temporary stopping up or diversion of any street under...
33.(1) Subject to sub-paragraphs (2) to (4), if as the...