Application

1.  This Schedule applies in relation to every mining waste operation.

Interpretation

2.(1)  In this Schedule—

“relevant emergency planner” means, in relation to an application for a mining waste facility that is located in—

(a)

London, the London Fire and Emergency Planning Authority;

(b)

an area where there is a fire and civil defence authority, that authority;

(c)

the Isles of Scilly, the Council of the Isles of Scilly;

(d)

an area in the rest of England, the county council for that area or where there is no county council for that area, the district council for that area;

(e)

an area in Wales, the county council or county borough council for that area.”;

“waste management plan” means a plan of the type described in Article 5(1) of the Mining Waste Directive which has the objectives in Article 5(2) and contains the elements and information set out in Article 5(3) of that Directive.

(2) When interpreting the Mining Waste Directive for the purposes of this Schedule—

(a)except where otherwise defined in this paragraph, an expression defined in Part 1 of these Regulations has the meaning given in that Part;

(b)“permit” means an environmental permit; and

(c)the competent authority is the regulator.

Applications for an environmental permit

3.(1)  The regulator must require that every application for the grant or variation of an environmental permit in relation to a mining waste operation involving a mining waste facility to which Article 7 of the Mining Waste Directive applies includes—

(a)the information specified in Article 7(2) of that Directive; and

(b)where Article 6 of the Directive applies, the information mentioned in the second sentence of the third paragraph of Article 6(3).

(2) Where the regulator receives an application for the grant or variation of an environmental permit and that application includes the information required under sub-paragraph (1)(b), the regulator must immediately forward the information to the relevant emergency planner.

(3) The regulator must require that every application for the grant or variation of an environmental permit in relation to any other mining waste operation includes a waste management plan.

(4) For the purposes of this paragraph, the regulator may accept a waste management plan produced pursuant to other legislation which complies with Articles 5(1) to (4) of the Mining Waste Directive if it has been reviewed and amended in accordance with Article 5(4) of that Directive.

(5) In this paragraph—

“application for the grant of an environmental permit” means an application made under regulation 13(1) of these Regulations;

“application for the variation of an environmental permit” means an application made by an operator under regulation 20(1) of these Regulations.

Review of environmental permits

4.  The regulator must periodically review an environmental permit relating to a mining waste facility if Article 7 of the Mining Waste Directive applies in respect of that facility and any of the circumstances in Article 7(4) of the Directive apply in relation to it.

Classification of mining waste facilities

5.  The regulator must exercise its functions so as to ensure compliance with Article 9 of the Mining Waste Directive in respect of any mining waste facility to which Article 7 does not apply.

Inspections

6.  The regulator must inspect every mining waste facility to which Article 7 of the Mining Waste Directive applies so as to comply with the requirements of Article 17(1) of that Directive.

Exercise of relevant functions

7.  The regulator must exercise its relevant functions so as to ensure compliance with the following requirements of the Mining Waste Directive—

(a)Article 2(4);

(b)Article 4;

(c)Article 5(4) and (6);

(d)Article 6(2), the first and second paragraphs of Article 6(3), the first paragraph of Article 6(4) to the extent that it relates to plans prepared under the first paragraph of Article 6(3) and the second paragraph of Article 6(4) to the extent that it relates to the regulator’s functions;

(e)Article 7(1) and Article 7(3)(a);

(f)Article 10;

(g)Article 11;

(h)Article 12;

(i)Article 13;

(j)Article 14 (1) to (3);

(k)Article 17(2);

(l)Article 24(1).

Public participation

8.(1)  The regulator must exercise its functions under the public participation provisions in relation to mining waste facilities to which Article 7 of the Mining Waste Directive applies so as to meet the requirements of Article 8 of that Directive.

(2) In this paragraph, “public participation provisions” means regulations 26, 29 and 59, and paragraphs 6 and 8 of Schedule 5 to these Regulations.

Derogation from requirements

9.(1)  The regulator must exercise its functions to ensure that the requirements mentioned in the first paragraph of Article 2(3) of the Mining Waste Directive do not apply to the substances mentioned in that paragraph where they result from an operation mentioned in that paragraph, to the extent allowed by that paragraph.

(2) The regulator must waive the requirements of the Mining Waste Directive in relation to the deposit of the substances mentioned in the second paragraph of Article 2(3) of that Directive as long as the regulator is satisfied that the requirements of Article 4 of that Directive are met.

(3) The regulator must waive the requirements mentioned in the third paragraph of Article 2(3) of the Mining Waste Directive in relation to the waste mentioned in that paragraph to the extent allowed by that paragraph.

Closure of a mining waste facility

10.(1)  The regulator must set out any reasoned decision under Article 12(2)(c) of the Mining Waste Directive in a closure notice served on the operator.

(2) A closure notice must, in addition to stating the regulator’s reasons for requiring initiation of the closure procedure, specify —

(a)the steps the operator is required to take to initiate the procedure; and

(b)the period within which they must be taken.

(3) The regulator may withdraw a closure notice at any time by further notice served on the operator.

(4) Closure of a mining waste facility does not relieve the operator of liability under the conditions of the environmental permit in relation to the facility.

(5) The regulator must exercise its functions so as to ensure compliance with Article 14(4) of the Mining Waste Directive.

Inventory of closed mining waste facilities

11.  The regulator must maintain and make available to the public an inventory of closed mining waste facilities so as to ensure compliance with Article 20 of the Mining Waste Directive.

Developments in best available techniques

12.(1)  The regulator must ensure that it is informed of developments in best available techniques.

(2) In this paragraph, “best available techniques” has the meaning given in Article 2(11) of the IPPC Directive.

Planning permission requirements and conditions

13.(1)  Following an application under regulation 13(1), the regulator must not grant an environmental permit in relation to a mining waste facility to which Article 7 applies if use of the site as a mining waste facility requires a planning permission and no such permission is in force.

(2) Where—

(a)a mining waste operation is the subject of an environmental permit;

(b)that operation has been granted planning permission subject to conditions (“planning conditions”), and

(c)there is an inconsistency between the conditions imposed by the environmental permit (“environmental permit conditions”) and those imposed by the planning conditions,

the environmental permit conditions prevail.

(3) In this paragraph, “planning permission” means planning permission under the Town and Country Planning Act 1990(1) and includes—

(a)a certificate under section 191 of that Act, and

(b)an established use certificate under section 192 of that Act, as originally enacted, which continues to have effect for the purposes of subsection (4) of that section.

Applications for an environmental permit for a Category A mining waste facility

14.(1)  The regulator must not grant an application for an environmental permit relating to a Category A mining waste facility until it has been notified by the relevant emergency planner that it has the information necessary to enable it to draw up an external emergency plan.

(2) The regulator must refuse an application for an environmental permit relating to a Category A mining waste facility that is an existing mining waste facility upon receipt of a notice by the relevant emergency planner stating that the operator has not provided the information necessary to enable the relevant emergency planner to draw up an external emergency plan.

(3) In this paragraph, “external emergency plan” means a plan as required under the third paragraph of Article 6(3) of the Mining Waste Directive that has the objectives specified in the first paragraph of Article 6(4) of that Directive.

Regulation 28

SCHEDULE 2Consequential amendments

Environmental Protection Act 1990

1.—(1) The Environmental Protection Act 1990(2) is amended as follows.

(2) In section 29 (interpretation)—

(a)in subsection (3) after “controlled waste” (in each place where it occurs) insert “or extractive waste”,

(b)in subsection (4) after “controlled waste” (in each place where it occurs) insert “or extractive waste”,

(c)in subsection (8) after “controlled waste” insert “or extractive waste”, and

(d)in subsection (13)(3) after “exempt waste operation” insert—

“extractive waste”;

“mining waste operation”;

“the Mining Waste Directive”.

(3) In section 33 (prohibition on unauthorised or harmful depositing, treatment or disposal etc of waste), in subsection (1)—

(a)in paragraph (a), after “controlled waste” (in each place where it occurs) insert “or extractive waste”, and

(b)in paragraph (c) after “controlled waste” insert “or extractive waste”.

(4) In section 33A (section 33 offences: investigation and enforcement costs), as inserted by section 42(1) of the Clean Neighbourhoods and Environment Act 2005(4), in subsection (1)(5), at the end of paragraph (b) insert “or a mining waste operation”.

(5) In section 33B (section 33 offences: clean up costs), in subsection (1)(a), after “controlled waste” insert “or extractive waste”.

(6) In section 34 (duty of care)—

(a)after subsection (1) insert—

(1A) It shall be the duty of any person who is responsible for the management of extractive waste to take all such measures applicable to him in that capacity as are reasonable in the circumstances —

(a)to prevent any contravention by any other person of section 33 above;

(b)to prevent any contravention by another person of regulation 12 of the 2007 Regulations or of a condition of an environmental permit; and

(c)to prevent the escape of the waste from his control or that of any other person., and

(b)in subsection (6), after “subsection (1)” insert “, (1A).”.

(7) In section 59 (powers to require removal of waste unlawfully deposited), in subsection (1), after “controlled waste” insert “or extractive waste”.

Water Resources Act 1991

2.—(1) The Water Resources Act 1991(6) is amended as follows.

(2) In section 85 (offences of polluting controlled waters) for subsection (7) substitute—

(7) For the purposes of subsection (1), “waste” in the term “waste matter” includes—

(a)anything that is waste for the purposes of Directive 2006/12/EC of the European Parliament and of the Council on waste, and that is not excluded from the scope of that Directive by Article 2(1) of that Directive;

(b)anything that is waste for the purposes of Directive 2006/21/EC of the European Parliament and of the Council on the management of waste from extractive industries and amending Directive 2004/35/EC, and that is not excluded from the scope of that Directive by Article 2(2) of that Directive..

Clean Air Act 1993

3.—(1) The Clean Air Act 1993(7) is amended as follows.

(2) In section 41A (relation to the Pollution Prevention and Control Act 1999) in subsection (4) for the definition of “activity” substitute—

activity” includes—

(a)

a waste operation within the meaning of the 2007 Regulations, and

(b)

a mining waste operation within the meaning of those Regulations;.

(1)

1990 c. 8. Sections 191 and 192 were amended by the Planning and Compensation Act 1991, section 10(1), c.34.

(3)

Section 29(13) was inserted by S.I. 2007/3538.

(5)

Section 33A(1) was substituted by S.I. 2007/3538.

(6)

1991, c. 57. Section 85 was amended by S.I. 2007/3538.

(7)

1993, c. 11. Section 41A was inserted by S.I. 2000/1973 and amended by S.I. 2007/3538.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill