Amount of electricity to be stated in NIROCs issued for electricity generated using 2013/14 capacity, 2014/15 capacity, 2015/16 capacity or post-2016 capacity

This section has no associated Explanatory Memorandum

33.  After Part 2 of Schedule 2 to the 2009 Order insert—

Articles 25(5), (6) and (10)

PART 2AAMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING 2013/14 CAPACITY AND 2014/15 CAPACITY

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued for electricity generated using—
2013/14 capacity2014/15 capacity
AD
Advanced gasification/pyrolysis
Building mounted solar PV
Co-firing of regular bioliquid22
Dedicated biomass
Dedicated energy crops
Electricity generated from landfill gas11
Electricity generated from sewage gas22
Energy from waste with CHP11
Geopressure11
Geothermal
Ground mounted solar PV
High-range co-firing
Hydroelectric
Low-range co-firing22
Mid-range co-firing
Offshore wind
Onshore wind
Standard gasification/pyrolysis
Station conversion11
Tidal impoundment – tidal barrage
Tidal impoundment – tidal lagoon
Tidal stream
Unit conversion11
Wave

Articles 35(5), (6) and (10) and 31(3)

PART 2BAMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING 2015/16 CAPACITY OR POST-2016 CAPACITY

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued for electricity generated using—
2015/16 capacityPost-2016 capacity
AD
Advanced gasification/pyrolysis
Building mounted solar PV
Closed landfill gas55
Co-firing of regular bioliquid22
Dedicated biomass
Dedicated energy crops
Electricity generated from sewage gas22
Energy from waste with CHP11
Geopressure11
Geothermal
Ground mounted solar PV
High-range co-firing
Hydroelectric
Landfill gas heat recovery1010
Low-range co-firing22
Mid-range co-firing
Offshore wind
Onshore wind
Standard gasification/pyrolysis
Station conversion11
Tidal impoundment – tidal barrage
Tidal impoundment – tidal lagoon
Tidal stream
Unit conversion11
Wave

Article 26(3) and (4)

PART 2CAMOUNT OF ELECTRICITY TO BE STATED IN NIROCs ISSUED FOR ELECTRICITY GENERATED USING PRE-2013 CAPACITY OR 2013/15 CAPACITY WHERE ARTICLE 26(3) OR (4) APPLIES

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using pre-2013 capacity or 2013/15 capacityAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using pre-2013 capacity or 2013/15 capacity
Co-firing of regular bioliquid with CHP12
Dedicated biomass with CHP
High-range co-firing with CHP
Low-range co-firing with CHP12
Mid-range co-firing with CHP
Station conversion with CHP1
Unit conversion with CHP1

Article 26(5) and (6)

PART 2DAMOUNT OF ELECTRICITY TO BE STATED IN NIROCS ISSUED FOR ELECTRICITY GENERATED USING 2015/16 CAPACITY WHERE ARTICLE 26(5) OR (6)APPLIES

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using 2015/16 capacityAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using 2015/16 capacity
Co-firing of regular bioliquid with CHP12
Dedicated biomass with CHP
High-range co-firing with CHP
Low-range co-firing with CHP12
Mid-range co-firing with CHP
Station conversion with CHP1
Unit conversion with CHP1

Article 26(7)

PART 2EAMOUNT OF ELECTRICITY TO BE STATED IN NIROCS ISSUED FOR ELECTRICITY GENERATED USING POST-2016 CAPACITY WHERE ARTICLE 26(7) APPLIES

Generation typeAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the qualifying proportion of electricity generated using post-2016 capacityAmount of electricity (in megawatt hours) to be stated in a NIROC issued in respect of the remainder of the electricity generated using post-2016 capacity
Co-firing of regular bioliquid with CHP12
Dedicated biomass with CHP
High-range co-firing with CHP
Low-range co-firing with CHP12
Mid-range co-firing with CHP
Station conversion with CHP1
Unit conversion with CHP1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Rule and provides information about its policy objective and policy implications. They aim to make the Statutory Rule accessible to readers who are not legally qualified and accompany any Northern Ireland Statutory Rule or Draft Northern Ireland Statutory Rule laid before the UK Parliament during the suspension of the Northern Ireland Assembly.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources