Search Legislation

The Knottingley Power Plant Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Article 3

SCHEDULE 1AUTHORISED DEVELOPMENT

PART 1Authorised Development

A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act, comprising—

  • Work No. 1 – an electricity generating station located on a site off Common Lane east of Knottingley, West Yorkshire which includes the site of a former chemical works, with a nominal net electrical output capacity of up to 1,500 MWe at ISO Conditions (with a tolerance of up to 5 per cent) fuelled by natural gas, comprising—

    (1)

    Work No. 1A – up to three separate generating units, with each generating unit including—

    (a)

    gas turbine and steam turbine within a turbine building;

    (b)

    one or two electricity generators within a turbine building;

    (c)

    heat recovery steam generator;

    (d)

    condenser;

    (e)

    main stack;

    (f)

    main and auxiliary transformer;

    (g)

    auxiliary cooling building;

    (h)

    condensate polisher;

    (i)

    oil water separator;

    (j)

    dosing system skid;

    (k)

    boiler feed pump building;

    (l)

    auxiliary electrical modules;

    (m)

    emission and ambient monitoring system;

    (n)

    blow down tank;

    (o)

    fuel gas coalescing filter;

    (p)

    fuel gas drains tank;

    (q)

    fuel gas flow measurement system;

    (r)

    fuel gas performance heater;

    (s)

    hydrogen storage;

    (t)

    condensate storage tank and make-up pump; and

    (u)

    pipe racks.

    (2)

    In addition to the generating units, Work No. 1A may comprise any of the following further elements—

    (a)

    cooling water pump house;

    (b)

    hybrid cooling towers;

    (c)

    chemical dosing station with electrical modules;

    (d)

    cooling water treatment;

    (e)

    general and unit services main control centre container;

    (f)

    fire protection pump house;

    (g)

    fire fighting and raw storage water tank;

    (h)

    de-mineralised water storage tank;

    (i)

    water treatment plant;

    (j)

    workshop and store building;

    (k)

    administration and control building;

    (l)

    water pre-treatment area;

    (m)

    water intake structure;

    (n)

    auxiliary boilers and associated stacks;

    (o)

    grease and oil storage building;

    (p)

    hazardous materials storage building;

    (q)

    emergency diesel generators and associated stacks;

    (r)

    gas receiving station;

    (s)

    gas boiler;

    (t)

    gas compressor building/area;

    (u)

    above Ground Installation/pig trap system;

    (v)

    gas compressor utility rooms;

    (w)

    water pre-treatment building; and

    (x)

    waste water treatment.

    (3)

    Work No. 1B – an electricity sub-station with gas insulated switchgear.

    (4)

    Associated development within the meaning of section 115(2) of the 2008 Act within the area comprised in Work No. 1A and Work No. 1B, namely—

    (a)

    lay down area;

    (b)

    car parking;

    (c)

    internal roadways and footpaths; and

    (d)

    lighting columns and lighting.

Associated development within the meaning of section 115(2) of the 2008 Act in connection with the Nationally Significant Infrastructure Project referred to in Work No. 1 comprising—

  • Work No. 2 – area reserved for carbon capture, compression and storage and laid out as parking and open storage, including—

    (a)

    lay down area;

    (b)

    car parking;

    (c)

    security gatehouse;

    (d)

    internal roadways and footpaths; and

    (e)

    lighting columns and lighting.

  • Work No. 3 – refurbishment of existing wharf on the Aire and Calder Navigation Canal and facilities to enable the offloading/unloading of equipment and materials from vessels moored at this wharf.

  • Work No. 4 – improvements to Common Lane from the junction with Weeland Road running in an easterly direction to the western boundary of Work No. 1.

  • Work No. 5 – National Grid upgrade works and new overhead line, including modification by way of alteration and repositioning of the existing 4YR Eggborough - Ferrybridge/Rochdale 400 kV overhead line route between towers 4YR001 and 4YR004 on land south and west of Kellingley Colliery, Knottingley, West Yorkshire, comprising—

    (a)

    construction and installation of a temporary pylon and temporary mast realignment through the temporary pylon and temporary mast of existing 400 kV overhead line, phase and earthwire conductors between pylon 4YR001 and pylon 4YR004 for the duration of construction;

    (b)

    construction and installation of two new transmission pylons, 4YR002R and 4YR003R, installation of new phase conductors, insulators, fittings and earthwire from pylon 4YR001 to pylon 4YR004;

    (c)

    removal of existing transmission pylon 4YR002 and pylon 4YR003 and the phase and earthwire conductors between pylon 4YR001 and pylon 4YR004;

    (d)

    installation of new connections from the new pylon 4YR003 to the electricity substation comprised in Work No. 1B;

    and in connection with such works comprised in Work No. 5, further associated development within the Order limits consisting of—

    (a)

    ramps, means of access and trackways;

    (b)

    drainage, wing walls, fencing and culverts;

    (c)

    works to alter the position of apparatus, including mains, sewers, drains and cables;

    (d)

    landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;

    (e)

    works for the benefit or protection of land affected by the authorised development;

    (f)

    works required for strengthening, improvement, maintenance, or reconstruction of any streets;

    (g)

    establishment of highway accesses, site construction compounds, crane pads, anchor points, temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction related buildings, welfare facilities, construction lighting and haulage roads;

    (h)

    installation of wires, cables, ducts, pipes, earthing strips and conductors;

    (i)

    installation of netted scaffold or any other form of third party asset protection as is deemed necessary for the duration of construction; and

    (j)

    such other works, including working sites storage areas, and works of demolition, as may be necessary or expedient for the purposes of or in connection with the construction of the authorised development.

  • Work No. 6 – cooling water pipelines and pumping station to convey water from the River Aire to the power plant for evaporative cooling and to convey purge water from the evaporative cooling system, treated wastewaters and rainwater to the River Aire comprising—

    (1)

    Work No. 6A – a water abstraction pipeline and intake screen arrangement to convey water from the river to the pumping station (Work No. 6C) including—

    (a)

    a passive wedge wire screen arrangement connected to the end of the pipeline at the intake point and installed to a depth of 1 m approximately above the river bed; and

    (b)

    a pipeline between the intake screen and the pumping station.

    (2)

    Work No. 6B – a water discharge pipeline to convey water from the pumping station to the river to the pumping station (Work No. 6C) including—

    (a)

    a dispersion device to distribute the discharged waters in the river; and

    (b)

    a pipeline between the dispersion device and the pumping station.

    (3)

    Work No. 6C – a pumping station containing a wet well sump and multiple pumps, including—

    (a)

    pump house building;

    (b)

    electrical supply and control equipment;

    (c)

    pipework and valves;

    (d)

    flow metering equipment;

    (e)

    power and control cables;

    (f)

    pump lifting equipment;

    (g)

    access track from Stocking Lane to Pumping Station compound; and

    (h)

    internal vehicular access, parking areas, pedestrian areas and landscaping, gated security fencing, close circuit television and intruder detection systems, lighting and rainwater drainage.

    (4)

    Work No. 6D – water abstraction and discharge pressure pipelines running in parallel from the Pumping Station to the southern boundary of Weeland Road.

    (5)

    Work No. 6E – water abstraction and discharge pressure pipelines running in parallel from the southern boundary of Weeland Road to the power plant site.

    The pipelines will be installed under Weeland Road and the Aire and Calder Canal using trenchless methods. The pipelines elsewhere in Work No. 6E will be laid in trench or using trenchless methods.

  • Work No. 7 – above ground installation comprising—

    (a)

    connection to National Grid Gas National Transmission System (NTS) No. 29 feeder pipeline including NTS Spur Pipeline and Minimum Offtake Connection (MOC);

    (b)

    above ground pipework;

    (c)

    emergency shutdown devices;

    (d)

    pipeline Internal Gauge (PIG) launcher for pipe inspection while maintaining normal gas flow;

    (e)

    gas vents;

    (f)

    instrumentation kiosks;

    (g)

    standby generator sockets;

    (h)

    access track;

    (i)

    hardstanding;

    (j)

    security fencing and gates; and

    (k)

    perimeter landscaping treatment.

  • Work No. 8 – a high pressure steel pipeline up to 600 mm (Nominal Bore) in diameter for the transport of gas. Its proposed route is shown by an indicative pink line (subject to the limits of deviation in article 6) on the works plan and comprises—

    (1)

    Work No. 8A – high pressure steel gas pipeline running from an indicative location within Work No. 7 near Gateforth in a southerly direction to the mid-point of Birkin Road where it connects with Work No. 8B.

    (2)

    Work No. 8B – high pressure steel gas pipeline running from Work No. 8A in the mid-point of Birkin Road in a predominantly southerly direction crossing the Fleet to a point on the northern bank of the River Aire where it meets Work No. 8C.

    (3)

    Work No. 8C – a high pressure steel gas pipeline running from the northern bank of the River Aire from Work No. 8B to the southern bank of the River Aire where it connects with Work No. 8D.

    (4)

    Work No. 8D – a high pressure steel gas pipeline running from the southern bank of the River Aire from Work No. 8C in a south and south westerly direction to the mid-point of Beal Lane where it connects with Work No. 8E. The pipeline will be installed under Marsh Drain using trenchless methods.

    (5)

    Work No. 8E – a high pressure steel gas pipeline running from the mid-point of Beal Lane from Work No. 8D in a westerly direction crossing New Lane to the mid-point of Common Lane where it connects with Work No. 8F.

    (6)

    Work No. 8F – high pressure steel gas pipeline running from the mid-point of Common Lane from Work No. 8E to the southern boundary of Weeland Road where it connects with Work No. 8G.

    (7)

    Work No. 8G – a high pressure steel gas pipeline running from the southern boundary of Weeland Road from Work No. 8F to Work No. 1A. The termination point shown on the works plan is indicative only.

    The gas pipeline will be laid using either trenched or trenchless methods except for—

    (a)

    all adopted highway crossings;

    (b)

    the River Aire crossing;

    (c)

    the Aire and Calder Canal crossing;

    (d)

    the Marsh Drain crossing (comprised in Work No. 8D); and

    (e)

    the Fleet crossing (comprised in Work No. 8B)

    where the pipeline will be installed using trenchless methods as shown on the works plan.

  • Work No. 9 – alternative private track/temporary bridleway along the southern boundary of Work No. 1 from Blackburn Lane to Southmoor Lane, at least five metres wide and being gated at either end.

    In connection with Work Nos. 1 to 9 and to the extent that they do not otherwise form part of any such work, further associated development whether or not shown on the plan referred to in the requirements including—

    (a)

    bunds, embankments, landscaping, fencing and boundary treatments;

    (b)

    connection to the electricity network for the purpose of supply to the authorised development;

    (c)

    connection to the telecommunications network for the purpose of supply to the authorised development;

    (d)

    temporary construction site offices;

    (e)

    haul roads and hardstandings on site for the parking of construction vehicles plant and machinery or for the vehicles of construction workers;

    (f)

    construction of temporary lay down storage areas and compounds and their restoration;

    (g)

    water supply works, foul drainage provision, surface water management systems, channelling and culverting;

    (h)

    habitat creation;

    (i)

    temporary footpaths;

    (j)

    marker posts;

    (k)

    telecommunication cables to be laid alongside pipeline;

    (l)

    cathodic protection posts;

    (m)

    site preparation works, site clearance (including fencing, vegetation removal, demolition of existing structures and the creation of alternative footpaths);

    (n)

    earthworks (including soil stripping and storage, site levelling);

    (o)

    piling;

    and to the extent that they do not form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and which fall within the scope of the works assessed by the environmental statement.

PART 2Requirements

Interpretation

1.  In this Part of this Schedule—

“the AGI” means the above ground installation comprised in Work No. 7;

“the Canal and River Trust” means the private company limited by guarantee of that name (company number 07807276) whose registered office is at First Floor, North Station House, 500 Elder Gate, Milton Keynes, MK9 1BB;

“the capture equipment” means the plant and equipment required to capture and compress the target carbon dioxide and identified as such in the current CCS proposal;

“CCS” means carbon capture and storage;

“the CCS proposal” means a proposal for the capture, transport and storage of the target carbon dioxide, which identifies the proposed technology, transport route and storage location for the authorised development;

“the CCS site” means an area within the area hatched pink on the works plan and described as Work No. 2 in Part 1 of this Schedule, which satisfies relevant legal and policy requirements as in force from time to time;

“CEMP” means a construction and environmental management plan relating to the construction of the relevant part of the authorised development;

“the Common Lane upgrade” means Work No. 4 in Part 1 of this Schedule;

“the cooling water pipelines” means Work No. 6 in Part 1 of this Schedule;

“current CCS proposal” means—

(a)

the CCS proposal contained in appendix F.2 of the environmental statement, set out in a feasibility study and assessed in accordance with the guidance entitled “Carbon Capture Readiness (CCR) A guidance note for section 36 Electricity Act 1986 consent applications”; or

(b)

if a revised CCS proposal has been identified under Requirement 29, the proposal which has most recently been so identified;

“the gas pipeline” means Work No. 8 in Part 1 of this Schedule;

“the generating station” means Work No. 1 in Part 1 of this Schedule;

“heavy commercial vehicles” means any vehicles or mobile plant exceeding 3 tonnes in weight employed by the undertaker or its contractors or their subcontractors for the purpose of movement of aggregates plant and materials to and from the construction site during the construction period for the purposes of construction of the authorised development;

“the Lead Local Flood Authority” means the Lead Local Flood Authority as defined by section 6(7) of the Flood and Water Management Act 2010(1);

“NRIL” means Network Rail Infrastructure Limited, company number 02904587 registered at Kings Place, 90 York Way, London, N1 9AG;

“the overhead lines and pylons” means Work No. 5 in Part 1 of this Schedule as shown on the works plan;

“part of the authorised development” means any part of Work Nos. 1 to 9 as listed in Part 1 of this Schedule;

“the relevant highway authority” means the relevant highway authority for the area in which the land to which the relevant provision of this Order applies is situated;

“the remediation permission” means the planning permission granted by Wakefield Metropolitan District Council in relation to engineering and remediation works at the former Oxiris chemical works site in Knottingley, WF11 8BN and allocated the reference number 12/02488/FUL or any such variation as may be permitted by the relevant planning authority;

“Requirement consultee” means any person whom the relevant planning authority is required to consult when discharging any of the requirements in this Part of this Schedule; and

“Requirements” means the requirements under this Part of this Schedule.

Time limits

2.  The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.

Detailed design

3.—(1) No part of the authorised development comprising the generating station may commence until details of the following have been submitted to and approved in writing by the relevant planning authority—

(a)details of the siting, design, external appearance and dimensions of all new or modified buildings and structures, including fencing or other means of enclosure, which are to be retained following commissioning;

(b)details of the colour, materials and surface finishes in respect of those buildings and structures referred to in paragraph (a);

(c)details of all external lighting;

(d)details of vehicular access and circulation roads, parking, hardstanding, loading and unloading facilities and turning facilities;

(e)details of drainage, storage tanks and silos;

(f)details of ground levels and heights of all permanent buildings and structures together with cross-sections through the site showing existing and proposed ground levels; and

(g)details of an operational travel plan, which must include details of the expected means of travel to and from the authorised development and any parking to be provided during the operational phase, and must be implemented within one month of the authorised development becoming operational.

(2) The details approved under sub-paragraph (1) must be in accordance with the following thresholds—

Maximum number of main stacks3
Maximum height of main stacks75 metres
Maximum height of turbine buildings and heat recovery steam generator45 metres
Maximum height of auxiliary boiler stacks30 metres
Maximum height of cooling towers20 metres
Maximum height of other buildings and structures15 metres

(3) The relevant planning authority must consult NRIL in respect of the details of fencing and external lighting approved under sub-paragraph (1) to the extent that they affect any railway belonging to NRIL.

(4) The authorised development comprising the generating station must be carried out in accordance with the approved details.

(5) A facility must be provided and maintained within Work No. 1 to enable steam pass-outs and/or hot water pass-outs and reserve space for the provision of water pressurisation, heating and pumping systems for off-site users of process and space heating and its later connection to such systems should a commercial arrangement be identified for combined heat and power which is economically viable.

(6) The generating station may not be brought into operation until an operational traffic management plan has been submitted to and approved by the relevant planning authority. The operational traffic management plan must be implemented as approved.

Overhead lines and pylons

4.—(1) No part of the authorised development comprising the overhead lines and pylons may commence until details of the overhead lines and pylons have been submitted to and approved in writing by the relevant planning authority.

(2) The details approved under sub-paragraph (1) must be in accordance with the following thresholds—

Maximum height of transmission towers65 metres

(3) Prior to the commencement of development comprising the part of the overhead lines and pylons affecting a railway belonging to NRIL, the undertaker must enter into an Outside Parties Basic Asset Protection Agreement (BAPA) (terms of which should be reasonable and proportionate to the routine works and technical standards required for reconductoring powerlines) with NRIL in accordance with National Grid Electricity Transmission Limited’s NGET Master Wayleave Agreement dated 12th September 1961 and supplemental agreement 4YR/9 dated 3rd February 1967.

(4) The authorised development comprising the overhead lines and pylons must be implemented in accordance with the approved details and, insofar as it affects any railway belonging to NRIL, the BAPA entered into with NRIL.

Cooling water pipelines and pumping station

5.—(1) No part of the authorised development comprising the cooling water pipelines or pumping station may commence until details of the cooling water pipelines and pumping station, including fencing or other means of enclosure, have been submitted to and approved in writing by the relevant planning authority.

(2) The details approved under sub-paragraph (1) must be in accordance with the following thresholds—

Number of cooling water pipelines2 (one abstraction and one discharge)
Maximum diameter700 mm (nominal bore)
Maximum height of buildings, including security fence5 metres

(3) The authorised development comprising the cooling water pipelines and pumping station must be implemented in accordance with the approved details.

Gas pipeline and AGI

6.—(1) No part of the authorised development comprising the gas pipeline and above ground installation may commence until—

(a)details of the gas pipeline, and

(b)details of the AGI, including in respect of fencing or other means of enclosure,

have been submitted to and approved in writing by the relevant planning authority.

(2) The details approved under sub-paragraph (1) in relation to the gas pipeline must be implemented in accordance with the following thresholds—

Maximum diameter600 mm (nominal bore)

(3) The details approved under sub-paragraph (1) in relation to the AGI must be implemented in accordance with the following thresholds—

Maximum height of buildings, including security fence3 metres

Provision of landscaping

7.—(1) No part of the authorised development may commence until a written landscaping scheme for that part has been submitted to and approved in writing by the relevant planning authority. The landscaping scheme must include details of all proposed hard and soft landscaping works, including—

(a)location, number, species, size and planting density of any proposed planting;

(b)cultivation, importing of materials and other operations to ensure plant establishment;

(c)proposed finished ground levels;

(d)hard surfacing materials;

(e)vehicular and pedestrian access, parking and circulation areas;

(f)minor structures, such as furniture, refuse or other storage units, signs and lighting;

(g)proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports;

(h)details of existing trees to be retained, with measures for their protection during the construction period;

(i)retained historic landscape features and proposals for restoration, where relevant;

(j)a tree and scrub buffer zone around the generating station and CCS areas, in accordance with the principles of the landscaping plan; and

(k)implementation timetables for all landscaping works.

(2) The relevant planning authority must consult NRIL in respect of landscaping details around the generating station that are adjacent to any railway belonging to NRIL.

Implementation and maintenance of landscaping

8.—(1) All landscaping works must be carried out in accordance with the landscaping scheme approved under Requirement 7 and to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.

(2) The landscaping works must be implemented in accordance with implementation timetables approved under Requirement 7.

(3) Any tree or shrub planted as part of an approved landscaping scheme that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted.

Footpath/Public Rights of Way diversions

9.—(1) No part of the authorised development may commence until a written public rights of way management plan for any sections of public rights of way shown to be extinguished or temporarily closed on the public rights of way temporary closures and permanent stopping up plan for that part has been approved in writing by the relevant planning authority in consultation with the relevant highway authority.

(2) The public rights of way management plan for the relevant part must include details of and a specification for the provisions of the temporary bridleway to be provided as part of Work No. 9.

(3) The public rights of way management plan and the provision of the temporary bridleway must thereafter be implemented as approved.

Highway accesses

10.—(1) No part of the authorised development may commence until written details of the siting, design and layout of any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, has, for that part, been submitted to and approved in writing by the relevant planning authority in consultation with the relevant highway authority.

(2) The highway accesses must be constructed in accordance with the approved details prior to commencement of the relevant part of the authorised development.

(3) No part of the authorised development may commence until, for that part, a written Access Management Scheme has been submitted to and approved in writing by the relevant planning authority.

(4) The Access Management Scheme must be implemented in accordance with the approved details.

Temporary buildings, structures and roads

11.—(1) No part of the authorised development comprising the generating station, the overhead lines and pylons, the pumping station or the AGI may commence until for that part a written scheme in accordance with sub-paragraph (2) has been submitted to and approved in writing by the relevant planning authority.

(2) The scheme must include details of—

(a)the siting, design and external appearance of temporary buildings and structures, artificial lighting and fencing to be erected and used during the period of construction;

(b)temporary vehicular roads, parking hardstandings, laydown areas and turning facilities to be used during the period of construction; and

(c)the secure fencing of construction sites.

(3) The scheme under sub-paragraph (2) must be implemented as approved.

(4) All temporary works must be removed within a period of twelve calendar months following commencement of the operational phase of the authorised development.

Surface and foul water drainage

12.—(1) No part of the authorised development may commence until, for that part, written details of the surface and foul water drainage systems (including means of pollution control) have been submitted to and approved in writing by the relevant planning authority in consultation with the internal drainage board, the Environment Agency, the Lead Local Flood Authority, the Canal and River Trust, and NRIL, as appropriate.

(2) The surface and foul water drainage system must thereafter be constructed in accordance with the approved details before the operational phase of that part of the authorised development commences.

Contaminated land and groundwater – general

13.—(1) No part of the authorised development may commence until, for that part, a written scheme produced in line with CLR11 Model Procedures (which may be included in the CEMP) to deal with the contamination of any land, including groundwater, within the Order limits has been submitted to and approved in writing by the relevant planning authority in consultation with the Environment Agency.

(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant and approved in writing by the relevant planning authority, to identify the extent of any contamination and a risk based remedial strategy to be produced and fully implemented, based on the findings of the investigation, to render the land fit for its intended purpose, together with a management plan which sets out long-term monitoring measures with respect to any contaminants remaining on the site.

(3) If during construction of the authorised development contaminated land or groundwater is encountered in excavations of Order land that was not identified in the initial investigation and assessment, then work in the vicinity of that contamination must be suspended, additional investigation and assessment carried out, and the scheme produced under sub-paragraph (1) amended to reflect the results. The amendments and any additional remediation required must be approved by the relevant planning authority in consultation with the Environment Agency prior to any works resuming.

(4) Remediation must be implemented in accordance with the approved scheme.

(5) Prior to commencement of the authorised development (or resumption of works following additional investigation and assessment under sub-paragraph (3)), a verification report demonstrating completion of the remediation works and the effectiveness of the remediation must be submitted to and approved, in writing, by the relevant planning authority in consultation with the Environment Agency. The report must include results of the sampling and monitoring carried out in accordance with the approved remedial strategy to demonstrate that the site remediation criteria have been met.

Contaminated land and groundwater – known contamination on the site of the generating station

14.  The part of the authorised development comprising the generating station must not commence until the remediation permission has been implemented in full and a verification report under Requirement 13(5) has been submitted to and approved in writing by the relevant planning authority.

Archaeology

15.—(1) No part of the authorised development may commence until for that part a written scheme for the investigation of areas of archaeological interest has been submitted to and approved in writing by the relevant planning authority.

(2) The scheme must identify areas where field work and/or a watching brief are required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.

(3) Any archaeological works or watching brief implemented under the scheme must be by a suitably qualified person or body approved in writing by the relevant planning authority.

(4) Any archaeological works or watching brief must be implemented in accordance with the approved scheme.

Ecological management plan

16.—(1) No part of the authorised development may commence until a written ecological management plan (which may form part of the construction environment management plan approved under Requirement 17) for that part has been submitted to and approved in writing by the relevant planning authority in consultation with the Canal and River Trust, the Yorkshire Wildlife Trust, West Yorkshire Ecology and North Yorkshire County Council Ecologist as appropriate.

(2) No part of the gas pipeline or water pipelines may commence, or material construction works on any part of them continue, between the months of October and February in any given year unless a wintering birds survey and, if appropriate, a proposed scheme of mitigation, is first submitted to and approved in writing by the relevant planning authority in consultation with Natural England. Any approved scheme of mitigation must be incorporated into the ecological management plan.

(3) The ecological management plan must contain on-site biodiversity mitigation to address the biodiversity loss resulting from the construction of the generating station (subsequent to the implementation of the remediation permission), unless off-site compensation or “offsetting” is provided to address this biodiversity loss (in full or in part) to the satisfaction of the relevant planning authority.

(4) The ecological management plan must include an implementation timetable and be implemented as approved.

Construction environment management plan

17.—(1) No part of the authorised development may commence until a CEMP relating to that part, which accords with the principles set out in the environmental statement (section 27 – Framework for a CEMP), has been submitted to and approved in writing by the relevant planning authority in consultation with the relevant highway authority.

(2) The CEMP must in particular include—

(a)a code of construction practice, specifying measures designed to minimised the impacts of construction works, addressing—

(i)external lighting;

(ii)noise and vibration;

(iii)air quality including dust;

(iv)construction hours, subject always to paragraph (e), being, between 0700 and 1900 hours on weekdays and 0800 and 1800 hours on Saturdays and no working on Sunday or public holidays, except during such periods and in such locations as are previously agreed by the relevant planning authority; save in relation to Work No. 5 to which no restriction applies under this sub-paragraph (iv);

(b)a site waste management plan;

(c)a traffic management plan addressing construction traffic to and materials storage on the authorised development, including any road closures, site access and a construction travel plan;

(d)a scheme for the notification of any significant construction impacts on local residents to local residents and the relevant planning authority;

(e)a scheme for impact piling, or other means of pile driving, addressing methods and duration of piling and stating the criteria according to which pile driving is chosen, which must require impact piling to be limited to the following times—

(i)Monday to Friday: 0900–1800 hours;

(ii)Saturday: 0900–1300 hours; and

(iii)no impact piling on Sunday or Bank Holidays

unless such impact piling is required because of an emergency;

(f)a water management assessment (assessment of the risks to and mitigation measures designed to protect controlled waters (surface and groundwater) including pollution control); and

(g)a review of the impact of the authorised development on the River Aire in a water body action plan.

(3) The relevant planning authority must consult NRIL in respect of the elements of the CEMP concerning—

(a)temporary external lighting around the generating station and overhead lines and pylons, to the extent that it affects any railway belonging to NRIL, and

(b)the construction traffic management plan in respect of the generating station and overhead lines and pylons.

(4) All construction works must be implemented in accordance with the CEMP.

Common Lane improvement

18.  Prior to commencement of the part of the authorised development comprising the generating station, Work No. 4 (improvements to Common Lane) must be implemented to the satisfaction of the relevant planning authority.

Air Safety

19.—(1) No part of the authorised development comprising the generating station may commence until the undertaker has notified the Ministry of Defence – Defence Geographic Centre in relation to the generating station of—

(a)the precise location of the authorised development with grid coordinates;

(b)the proposed date of commencement of construction;

(c)the height above ground level in metres of the tallest structure;

(d)the maximum extension height in metres of any construction equipment.

(2) The undertaker must ensure that any stacks are fitted with aviation warning lighting with a minimum intensity of 25 candela omni directional red light or equivalent infra-red light fitted at the highest practicable point of the structure.

(3) Within 28 days of completion of the construction of the generating station the undertaker must notify the Ministry of Defence – Defence Geographic Centre of the date of such completion of construction.

Flooding – mitigation

20.—(1) No part of the authorised development may commence until for that part there has been submitted to and approved in writing by (and deposited with) the relevant planning authority, in consultation with the Environment Agency and the relevant internal drainage board, a scheme for mitigation of flood risk during the construction and operation of the authorised development prepared in accordance with the principles set out in the flood risk assessment.

(2) The scheme approved must thereafter be fully implemented and adhered to throughout the period of the construction and operation of the relevant part of the authorised development.

Fire prevention

21.—(1) No part of the authorised development may commence until for that part there has been submitted to and approved in writing by the relevant planning authority a fire prevention method statement providing details of fire detection measures, fire suppression measures and the location of accesses to all fire appliances in all of the major building structures and storage areas within the authorised development such method statement to be prepared, including measures to contain and treat water used to suppress any fire.

(2) The authorised development must be implemented in accordance with the approved details and all the relevant fire suppression measures and fire appliances must be maintained to the reasonable satisfaction of the relevant planning authority at all times when the authorised development is operational.

Waste management on site – operational phase

22.—(1) No part of the authorised development may be brought into operation until the relevant planning authority has received and approved in writing a waste management plan for the operational phase for that part of the authorised development incorporating the principles in the environmental statement. The site waste management plan must address and include at least the following—

(a)the storage of waste materials on site;

(b)removal of waste materials from the site for recovery/disposal at appropriately licensed sites;

(c)the return/disposal of general engineering wastes (such as spent filters and used parts).

(2) The authorised development must thereafter be operated fully in accordance with the approved details.

Control of noise – operational phase

23.—(1) The part of the authorised development comprising the generating station may not be brought into operation until a written scheme for noise management including monitoring and attenuation for the use of the authorised development has been submitted to and approved in writing by the relevant planning authority in consultation with Selby District Council.

(2) Noise from the operation of the generating station must be no greater than the existing background level (expressed as LA90 dB) when monitored in accordance with BS4142: 1997 Method for Rating Industrial Noise Affecting Mixed Residential and Industrial Areas, adjacent to the nearest residential properties at such locations as are agreed with the relevant planning authority. The noise levels must be monitored across 1 hour in the day-time and 5 minutes at night-time.

(3) The noise management scheme must be implemented as approved.

European protected species

24.—(1) No part of the authorised development may commence until further survey work for that part has been carried out to establish whether any European protected species is present on any of the land affected, or likely to be affected, by that part of the authorised development or in any of the trees to be lopped or felled or buildings to be demolished in connection with that part of the authorised development.

(2) Where a European protected species is shown to be present, no authorised development of that part may be begun until, after consultation with Natural England, a scheme of protection and mitigation measures has been submitted to and approved in writing by the relevant planning authority.

(3) The authorised development must be implemented in accordance with the approved scheme.

(4) The part of the authorised development comprising the generating station may not be commenced until great crested newts have been removed in accordance with the relevant condition of the remediation permission.

(5) “European protected species” has the same meaning as in regulations 40 and 44 of the Conservation of Habitats and Species Regulations 2010(2).

Restoration of land used temporarily for construction

25.—(1) Any land within the Order limits which is used temporarily for construction must be reinstated to its former condition, or such condition as the relevant planning authority may approve in writing (or which may be provided for under an approved landscaping scheme).

(2) Reinstatement works must be commenced promptly following completion of the relevant part of the authorised development, and within three months of any required approval by the relevant planning authority. The reinstatement must be implemented in accordance with any timetable included in any relevant approved landscaping scheme.

Air quality monitoring

26.—(1) The authorised development comprising the generating station may not become operational until there has been submitted to and approved in writing by Wakefield Metropolitan District Council in consultation with Selby District Council a scheme for the monitoring of nitrogen oxides (NOx) in the area.

(2) The scheme must—

(a)include the measurement locations from which air pollution is required to be monitored,

(b)specify the equipment and methods to be used,

(c)specify the frequency of measurement,

(d)require the first measurement to be taken not less than 24 months prior to the generating station becoming operational, and

(e)require the final measurement to be taken not more than 12 months after the cessation of operation.

(3) The undertaker must supply to Wakefield Metropolitan District Council and Selby District Council the full details of the measurements obtained in accordance with the scheme as soon as possible after they become available.

Combined heat and power

27.  A facility must be provided and maintained within Work No. 1 to enable steam pass-outs and/or hot water pass-outs and reserve space for the provision of water pressurisation, heating and pumping systems for off-site users of process and space heating and its later connection to such systems should a commercial arrangement be identified for combined heat and power which is economically viable.

28.—(1) Prior to the operation of Work No, 1, a review of potential opportunities for the use of heat from the authorised development must be submitted to and approved by the relevant planning authority.

(2) The review shall provide for the on-going monitoring and full exploration of potential opportunities to use heat from the authorised development as part of a good quality CHP scheme in accordance with the principles set out in the CHPQA Standard Issue 3, and for the provision of subsequent reviews of such opportunities as necessary.

(3) Where viable opportunities for the use of heat are identified, a scheme for the provision of the necessary Plant and pipework to the boundary of the site shall be submitted to and approved by the relevant planning authority; any plant and pipework installed up to the Order limits to enable the use of heat shall be installed in accordance with the agreed details.

(4) In this requirement, ‘CHPQ Standard Issued 3’refers to the document of that name prepared by the Department for Environment, Food and Rural Affairs and published in January 2009, and the reference to a ‘good quality CHP scheme ‘should be interpreted in accordance with that document.

CCS site

29.  Until such time as the generating station is decommissioned, the undertaker must not, without the written consent of the Secretary of State—

(a)dispose of any interest in the CCS site; or

(b)do anything, or allow anything to be done or to occur, which may reasonably be expected to diminish the undertaker’s ability, within two years of such occurrence, to prepare the CCS site for the installation and operation of the capture equipment.

CCS monitoring report

30.—(1) The undertaker must make a report (“CCS monitoring report”) to the Secretary of State—

(a)on or before the date on which three months have passed from commencement of operation of the authorised development; and

(b)within one month of the second anniversary, and each subsequent even-numbered anniversary, of that date.

(2) Each CCS monitoring report must provide evidence that the undertaker has complied with Requirement 29—

(a)in the case of the first CCS monitoring report, since this Order was made; and

(b)in the case of any subsequent report, since the making of the previous CCS monitoring report,

and explain how the undertaker expects to continue to comply with Requirement 29 over the next two years.

(3) Each CCS monitoring report must state whether the undertaker considers that some or all of the technology referred to in the current CCS proposals will not work and identify any other impediment to the technical feasibility of the current CCS proposal, explaining the reasons for any such conclusion and whether such impediments could be overcome. If the undertaker considers that technical impediments could be overcome by putting forward a revised CCS proposal, this should be included in the CCS monitoring report.

(4) Each CCS monitoring report must state, with reasons, whether the undertaker has decided to seek any additional regulatory clearances, or to modify any existing regulatory clearances, in respect of its current CCS proposals.

Applicability of Requirements 29 and 30

31.—(1) Requirements 29 and 30 will cease to have effect as soon as any of the following events occurs—

(a)the capture equipment is installed; or

(b)the generating station is decommissioned; or

(c)the Secretary of State’s agreement to the undertaker not installing capture equipment and having no current CCS proposals has been obtained in writing.

(2) Requirement 29 will cease to have effect if the requirement to hold land for the installation of capture equipment ceases to be included in law or planning policy as from time to time in force.

(3) Requirement 30 will cease to have effect if the requirement to submit a CCS report ceases to be included in law or planning policy as from time to time in force.

Decommissioning

32.—(1) Within 12 months of the generating station ceasing to be used for the purposes of generating electricity, a site closure and restoration plan for the demolition and removal of the generating station and pumping station must be submitted for approval by the relevant planning authority. The scheme must include—

(a)details of all structures and buildings to be demolished;

(b)details of the means of removal of the materials resulting from decommissioning works;

(c)details of the phasing of the demolition and removal works;

(d)details of the restoration works to restore the operations area to a condition agreed with the relevant planning authority;

(e)details of any restoration works and their phasing;

(f)a timetable in which the scheme must be carried out; and

(g)an environment management plan for the demolition and decommissioning works addressing the matters listed in Requirement 17 (construction environment management plan).

(2) The demolition and removal of the generating station must be implemented in accordance with the approved scheme.

Requirement for written approval

33.  Where under any of the above Requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.

Approved details

34.—(1) All details submitted for the approval of the relevant planning authority under these Requirements must be in accordance with the parameters of the environmental statement and reflect the principles set out in the documents certified under article 37.

(2) The authorised development must be carried out in accordance with the design drawings subject to such non-material amendments as are approved in writing by the relevant planning authority; provided that such approval is not given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

(3) The authorised development must be carried out in accordance with the details approved.

(4) Where the approval or agreement of the relevant planning authority or another person is required under any of the Requirements, that approval or agreement must be given in writing.

Local liaison committee

35.  The authorised development may not commence until the undertaker has established a committee to liaise with local residents and organisations about matters relating to the authorised development (a “local liaison committee”). The local liaison committee must include representatives of the undertaker. The undertaker must invite Wakefield Metropolitan District Council, Selby District Council, North Yorkshire County Council, the Environment Agency, West Yorkshire Police and other relevant interest groups, as may be agreed with Wakefield Metropolitan District Council, to nominate representatives to join the local liaison committee. The undertaker must provide a full secretariat service and supply an appropriate venue. The local liaison committee must meet every other month, starting in the month prior to commencement of the authorised development, until the completion of construction, testing and commissioning works unless otherwise agreed in writing by the majority of the members of the local liaison committee. During the operational phase of the authorised development, the local liaison committee must meet once a year unless otherwise agreed in writing by the majority of the members of the local liaison committee.

Employment and Skills plan

36.  The authorised development comprised in Work No. 1 shall not commence until an employment and skills plan detailing arrangements to promote employment and skills development opportunities has been submitted to and approved in writing by the relevant planning authority. The plan must include proposals for promoting such opportunities for local residents and the approved employment and skills plan must be implemented and maintained during the construction and operation of the authorised development comprised in Work No.1.

Notice of start and completion of commissioning

37.—(1) Notice of the intended start of commissioning must be given to the relevant planning authority where practicable prior to such commencement and in any event within seven (7) days from the date that commissioning is commenced.

(2) Notice of the intended completion of commissioning must be given to the relevant planning authority where practicable prior to such completion and in any event within seven (7) days from the date that commissioning is completed.

Notice of commencement of operation

38.  Notice of the intended start of operation must be given to the relevant planning authority and the Environment Agency, by means of an operational phase notice, where practicable prior to such commencement and in any event within seven (7) days from the date that operation is commenced.

Article 10

SCHEDULE 2STREETS SUBJECT TO STREET WORKS

(1)(2)
AreaStreet subject to street works
Wakefield Metropolitan DistrictCommon Lane
Wakefield Metropolitan DistrictWeeland Road (A645)
Selby DistrictWeeland Road (A645)
Selby DistrictFarmer’s track near Kellingley Farm
Selby DistrictCommon Lane
Selby DistrictNew Lane
Selby DistrictBeal Lane
Selby DistrictFarmer’s Track in Beal Carrs
Selby DistrictMarsh Lane
Selby DistrictBirkin Road
Selby DistrictRoyd’s Road
Selby DistrictPale Lane

Article 11

SCHEDULE 3STREETS TO BE STOPPED UP

STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

(1)(2)(3)(4)
AreaStreet to be stopped upExtent of stopping upTemporary alternative route to be provided
Wakefield Metropolitan DistrictCommon LaneSo much of Common Lane (private accommodation road) as is within Work Nos. 1 and 2 as shown on the works planThe temporary bridleway described in Work No. 9 in Part 1 of Schedule 1 and shown coloured yellow on the plan

Article 12

SCHEDULE 4PUBLIC RIGHT OF WAY TO BE TEMPORARILY CLOSED AND PERMANENTLY STOPPED UP

PART 1Claimed public right of way to be extinguished for which a replacement will be provided

(1)(2)(3)(4)
AreaPublic right of way to be stopped upExtent of stopping upTemporary bridleway
Wakefield MetropolitanClaimed public bridleway along Common LaneSo much of Common Lane as is shown market by a green dashed line on the public rights of way temporary closures and permanent stopping up planThe temporary bridleway described in Work No. 9 in Part 1 of Schedule 1 and shown coloured yellow on the plan

PART 2Rights of way for which a replacement will be provided during temporary closure

(1)(2)(3)
AreaFootpath to be temporarily closedExtent of temporary closure
Selby DistrictFootpath 35.30/7/1 off Pale LaneAs shown marked by a black line on the public rights of way temporary closures and permanent stopping up plan
Selby DistrictFootpath 35.72/3/1 off Marsh Lane
Selby DistrictFootpath 35.41/5/1 south of the River Aire
Selby DistrictFootpath 35.7/6/1 along River Aire at pumping station
Selby DistrictFootpath 35.7/8/1 north of Kellingley Farm
Selby DistrictFootpath 35.7/9/1 west of Kellingley Farm

PART 3Rights of way for which no replacement will be provided during temporary closure

(1)(2)(3)
AreaFootpath to be temporarily closedExtent of temporary closure
Wakefield DistrictClaimed public bridleway along Common Lane and leading onto a track connecting to Beal LaneAs shown marked by a pink dashed line on the public rights of way temporary closures and permanent stopping up plan
Wakefield DistrictClaimed public bridleway along Southmoor LaneAs shown marked by a pink dashed line on the public rights of way temporary closures and permanent stopping up plan

Article 13

SCHEDULE 5ACCESS TO WORKS

(1)(2)(3)
AreaAccess number on access to works planDescription of access
Selby District1Pale Lane (N) – permanent access
Selby District2Pale Lane (S) – indicative temporary access
Selby District3Birkin Road (N) – indicative temporary access
Selby District4Marsh Lane – indicative temporary access
Selby District5Low Road – indicative temporary access
Selby District6Beal Lane (N) – indicative temporary access
Selby District7Beal Lane (S) – indicative temporary access
Selby District8New Lane (E) – indicative temporary access
Selby District9New Lane (W) – indicative temporary access
Selby District10Common Lane (E) – indicative temporary access
Selby District11Common Lane (W) – indicative temporary access
Selby District12Stocking Lane – indicative temporary access
Selby District13Weeland Road (N) – indicative temporary access
Wakefield District14Weeland Road (S) – indicative temporary access
Wakefield District15Common Lane – permanent access
Wakefield District16Southmoor Lane (E) – indicative temporary access
Wakefield District17Blackburn Lane (E) – permanent Access

Article 21

SCHEDULE 6MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS

Compensation enactments

1.  The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right or the imposition of a restrictive covenant as they apply as respects compensation on the compulsory purchase of land and interests in land.

2.—(1) Without prejudice to the generality of paragraph 1, the Land Compensation Act 1973(3) has effect subject to the modifications set out in sub-paragraphs (2) and (3).

(2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—

(a)for the words “land is acquired or taken” there is substituted the words “a right or restrictive covenant over land is purchased from or imposed on”; and

(b)for the words “acquired or taken from him” there is substituted the words “over which the right is exercisable or the restrictive covenant enforceable”.

(3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—

(a)for the word “part” in paragraphs (a) and (b) there is substituted the words “a right over or restrictive covenant affecting land consisting”;

(b)for the word “severance” there is substituted the words “right or restrictive covenant over or affecting the whole of the house, building or manufactory or of the house and the park or garden”;

(c)for the words “part proposed” there is substituted the words “right or restrictive covenant proposed”; and

(d)for the words “part is” there is substituted the words “right or restrictive covenant is”.

Application of the 1965 Act

3.—(1) The 1965 Act has effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right, or to the imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are read (according to the requirements of the particular context) as referring to, or as including references to—

(a)the right acquired or to be acquired; or

(b)the land over which the right is or is to be exercisable; or

(c)the land over which the restrictive covenant is enforceable.

(2) Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act applies in relation to the compulsory acquisition under this Order of a right by the creation of a new right, or the imposition of a restrictive covenant, with the modifications specified in the following provisions of this Schedule.

4.  For section 7 of the 1965 Act (measure of compensation) there is substituted the following section—

7.  In assessing the compensation to be paid by the acquiring authority under this Act, regard is had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act..

5.  For section 8 of the 1965 Act (provisions as to divided land) there is substituted the following section—

8.(1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)—

(a)a question of disputed compensation in respect of the purchase of the right or the imposition of the restrictive covenant would apart from this section fall to be determined by the Upper Tribunal (“the tribunal”); and

(b)before the tribunal has determined that question the tribunal is satisfied that the person has an interest in the whole of the relevant land and is able and willing to sell that land and—

(i)where that land consists of a house, building or manufactory, that the right cannot be purchased or the restrictive covenant imposed without material detriment to that land; or

(ii)where that land consists of such a park or garden, that the right cannot be purchased or the restrictive covenant imposed without seriously affecting the amenity or convenience of the house to which that land belongs,

in relation to that person, the Order ceases to authorise the purchase of the right and is deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice is deemed to have been served in respect of that interest on such date as the tribunal directs.

(2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section is determined by the tribunal.

(3) Where in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1) of this section the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice..

6.  The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—

(a)section 9(4) (failure by owners to convey);

(b)paragraph 10(3) of Schedule 1 (owners under incapacity);

(c)paragraph 2(3) of Schedule 2 (absent and untraced owners); and

(d)paragraphs 2(3) and 7(2) of Schedule 4 (common land),

are so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.

7.  Section 11 of the 1965 Act (powers of entry) is so modified as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the date of service of the notice); and sections 12 (unauthorised entry) and 13 (refusal to give possession to acquiring authority) of the 1965 Act are modified correspondingly.

8.  Section 20 of the 1965 Act (tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.

9.  Section 22 of the 1965 Act (interests omitted from purchase) is so modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.

10.  In this Schedule, “acquiring authority” has the same meaning as “the undertaker” in article 2(1) (Interpretation) of this Order.

Article 37

SCHEDULE 7PROCEDURE FOR DISCHARGE OF REQUIREMENTS

Applications made under requirement

1.—(1) Where an application has been made to a relevant planning authority for any agreement or approval required by any requirement included in this Order, the relevant planning authority must give notice to the undertaker of its decision on the application before the end of the decision period.

(2) For the purposes of sub-paragraph (1), the decision period is—

(a)where no further information is requested under paragraph 2, 8 weeks from the day immediately following that on which the application is received by the authority or the day on which the fee under paragraph 3(1) of this Schedule is received, whichever is the later;

(b)where further information is requested under paragraph 2, 8 weeks from the day immediately following that on which further information has been supplied by the undertaker under paragraph 2; or

(c)such longer period as may be agreed by the undertaker and the relevant planning authority in writing before the end of the period in sub-paragraph (a) or (b).

(3) For the avoidance of doubt, the relevant planning authority remains seized of the application after the decision period elapses and pending an appeal by the undertaker for non-determination under paragraph 4(1)(b).

Further information

2.—(1) In relation to any application to which this Schedule applies, the relevant planning authority has the right to request such further information from the undertaker as is necessary to enable it to consider the application.

(2) If the relevant planning authority considers such further information to be necessary and the requirement does not specify that consultation with a requirement consultee is required, it must, within 7 business days of receipt of the application, notify the undertaker in writing specifying the further information required.

(3) If the requirement specifies that consultation with a requirement consultee is required, the relevant planning authority must issue the consultation to the requirement consultee within 3 business days of receipt of the application, and must notify the undertaker in writing specifying any further information requested by the requirement consultee within 3 business days of receipt of such a request and in any event within 35 days of receipt of the application.

(4) If the relevant planning authority does not give such notification as specified in sub-paragraph (2) or (3) it is deemed to have sufficient information to consider the application and is not thereafter be entitled to request further information without the prior agreement of the undertaker.

Fees

3.—(1) Where an application is made to the relevant planning authority for agreement or approval in respect of a requirement, a fee of £97, or such greater sum as applies by regulations for the discharge of planning conditions, must be paid to that authority.

(2) Any fee paid under this Schedule must be refunded to the undertaker within 8 weeks of the relevant planning authority failing to determine the application within the decision period as determined under paragraph 1, unless within that period the undertaker agrees, in writing, that the fee may be retained by the relevant planning authority and credited in respect of a future application.

Appeals

4.—(1) The undertaker may appeal in the event that—

(a)the relevant planning authority refuses an application for any agreement or approval required by a requirement included in this Order or grants it subject to conditions;

(b)the relevant planning authority does not give notice of its decision to the undertaker within the decision period as determined in paragraph 1;

(c)on receipt of a request for further information pursuant to paragraph 2 the undertaker considers that either the whole or part of the specified information requested by the relevant planning authority is not necessary for consideration of the application; or

(d)on receipt of any further information requested, the relevant planning authority notifies the undertaker that the information provide is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.

(2) The appeal process is as follows—

(a)the undertaker must submit the appeal documentation to the Secretary of State, a copy of the application submitted to the relevant planning authority and any supporting documentation which the undertaker may wish to provide (“the appeal documentation”);

(b)the undertaker must on the same day provide copies of the appeal documentation to the relevant planning authority and the requirement consultee (if applicable);

(c)as soon as is practicable after receiving the appeal documentation, but in any event within 10 business days of receiving the appeal documentation, the Secretary of State must appoint a person and forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person’s attention should be sent;

(d)the relevant planning authority and the requirement consultee (if applicable) must submit written representations to the appointed person in respect of the appeal within 20 business days of the date on which the appeal parties are notified of the appointment of a person under paragraph (c) and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;

(e)the appeal parties must make any counter-submissions to the appointed person within 10 business days of receipt of written representations pursuant to paragraph (d) above.

(3) The appointed person must make his decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable. If the appointed person considers that further information is necessary to enable him to consider the appeal he must, as soon as practicable, notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.

(4) Any further information required pursuant to sub-paragraph (3) must be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person. Any written representations concerning matters contained in the further information must be submitted to the appointed person, and made available to all appeal parties within 10 business days of that date.

(5) On an appeal under this paragraph, the appointed person may—

(a)allow or dismiss the appeal; or

(b)reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not),

and may deal with the application as if it had been made to the appointed person in the first instance.

(6) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the time limits prescribed, or set by the appointed person, under this paragraph.

(7) The appointed person may proceed to a decision even though no written representations have been made within those time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.

(8) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.

(9) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of the relevant Requirement in Schedule 1 Part 2 as if it had been given by the relevant planning authority. The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) may not be taken to affect or invalidate the effect of the appointed person’s determination.

(10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the appointed person to be paid by the relevant planning authority, the reasonable costs of the appointed person must be met by the undertaker.

(11) On application by the relevant planning authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Communities and Local Government Circular 03/2009 or any circular or guidance which may from time to time replace it.

Interpretation of Schedule 7

5.  In this Schedule—

“the appeal parties” means the relevant planning authority, the requirement consultee and the undertaker;

“business day” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 1971; and

“requirement consultee” means anybody named in a requirement which is the subject of an appeal as a body to be consulted by the relevant planning authority in discharging that requirement.

Article 29

SCHEDULE 8PROTECTIVE PROVISIONS

For the protection of Canal and River Trust

Interpretation

1.—(1) For the protection of CRT the following provisions of this Schedule shall, unless otherwise agreed in writing between the undertaker and CRT, have effect.

(2) In this Schedule—

“construction”, in relation to any specified work or protective work, includes—

(a)

the execution and placing of that work; and

(b)

any relaying, renewal, or maintenance of that work as may be carried out during the period of 24 months from the completion of that work; and “construct” and “constructed” have corresponding meanings;

“CRT” means the Canal & River Trust;

“CRT’s network” means CRT’s network of waterways;

“detriment” means any damage to the waterway or any other property of CRT caused by the presence of the authorised works and, without prejudice to the generality of that meaning, includes—

(a)

any obstruction of, or interference with, or hindrance or danger to, navigation or to any use of the waterway (including towing paths);

(b)

the erosion of the bed or banks of the waterway, or the impairment of the stability of any works, lands or premises forming part of the waterway;

(c)

the deposit of materials or the siltation of the waterway so as to damage the waterway;

(d)

the pollution of the waterway;

(e)

any significant alteration in the water level of the waterway, or significant interference with the supply of water thereto, or drainage of water therefrom;

(f)

any harm to the ecology of the waterway (including any adverse impact on any site of special scientific interest comprised in CRT’s network);

(g)

any interference with the exercise by any person of rights over CRT’s network;

“the engineer” means an engineer appointed by CRT for the purpose in question;

“plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction) and programmes;

“practical completion” means practical completion of all of the specified work notwithstanding that items which would ordinarily be considered snagging items remain outstanding, and the expression “practically complete” and “practically completed” shall be construed accordingly;

“protective work” means a work constructed under paragraph 6(3)(a);

“specified work” means so much of Work Nos. 3, 6 and 8G as are situated upon, across, under, over or within 15 metres of, or may in any way affect the waterway;

“towing path” means the towing path forming part of the waterway;

“the waterway” means the Aire & Calder Navigation, and includes any works, lands or premises belonging to CRT, or under its management or control, and held or used by CRT in connection with that canal.

Powers requiring CRT’s consent

2.—(1) The undertaker shall not in the exercise of the powers conferred by this Order obstruct or interfere with pedestrian or vehicular access to the waterway unless such obstruction or interference with such access is with the consent of CRT.

(2) The undertaker shall not exercise any power conferred by this Order to discharge water into the waterway under article 15 (discharge of water) or in any way interfere with the supply of water to or the drainage of water from the waterway unless such exercise is with the consent of CRT, save as to surface water discharge which will not require the consent of CRT.

(3) The undertaker shall not exercise the powers conferred article 16 (authority to survey and investigate land) or section 11(3) of the 1965 Act, in relation to the waterway unless such exercise is with the consent of CRT.

(4) The undertaker shall not exercise the powers conferred by section 271 or 272 of the Town and Country Planning Act 1990, as applied by Schedule 3 to this Order (streets to be stopped up), so as to divert any right of access to the waterway but such right of access may be diverted with the consent of CRT.

(5) The consent of CRT pursuant to sub-paragraphs (1) to (4) shall not be unreasonably withheld or delayed but may be given subject to reasonable terms and conditions which in the case of article 15 (discharge of water) may include conditions—

(a)specifying the maximum volume of water which may be discharged in any period; and

(b)authorising CRT on giving reasonable notice (except in an emergency, when CRT may require immediate suspension) to the undertaker to require the undertaker to suspend the discharge of water or reduce the flow of water where this is necessary by reason of any operational or environmental requirement of CRT,

to the extent that any discharge of water by the undertaker is into the waterway.

Vehicles, plant and machinery

3.  The undertaker shall not use any land or property of CRT forming part of the waterway for the passage or siting of vehicles, plant or machinery employed in the construction of the specified works other than—

(a)with the consent in writing of the engineer whose consent shall not be unreasonably withheld; and

(b)subject to compliance with such reasonable requirements as the engineer may from time to time specify—

(i)for the prevention of detriment; or

(ii)in order to avoid or reduce any inconvenience to CRT, its officers and agents and all other persons lawfully on such land or property, but nothing in this paragraph shall apply in relation to anything done in accordance with any approval given by CRT under paragraph 6.

Fencing

4.  Where so required by the engineer the undertaker shall to the reasonable satisfaction of the engineer fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis or both.

Survey of waterway

5.—(1) Before the commencement of the initial construction of any part of the specified works and again following practical completion of the specified works the undertaker shall bear the reasonable cost of the carrying out by a qualified engineer (the “surveyor”), to be approved by CRT and the undertaker, of a survey including a dip-survey to measure the depth of the waterway (“the survey”) of so much of the waterway and of any land and existing works of the undertaker which may provide support for the waterway as will or may be affected by the specified works.

(2) For the purposes of the survey the undertaker shall—

(a)on being given reasonable notice (save in case of emergency, when immediate access shall be afforded) afford reasonable facilities to the surveyor for access to the site of the specified works and to any land and existing works of the undertaker which may provide support for the waterway as will or may be affected by the specified works; and

(b)supply the surveyor as soon as reasonably practicable with all such information as he may reasonably require with regard to such existing works of the undertaker and to the specified works or the method of their construction.

(3) The reasonable costs of the survey shall include the costs of any dewatering or reduction of the water level of any part of the waterway (where reasonably required) which may be effected to facilitate the carrying out of the survey and the provisions of this Schedule shall apply with all necessary modifications to any such dewatering or reduction in the water level as though the same were specified works.

(4) Copies of the survey shall be provided to both CRT and the undertaker at no cost to CRT.

Approval of plans, protective works etc.

6.—(1) The undertaker shall before commencing construction of any specified work within the boundaries of the specified works including any temporary works supply to CRT proper and sufficient plans of that work and such further particulars available to it as CRT may within 14 days of the submission of the plans reasonably require for the approval of the engineer and shall not commence such construction of a specified work until plans of that work have been approved in writing by the engineer or settled by arbitration.

(2) The approval of the engineer under sub-paragraph (1) shall not be unreasonably withheld or delayed, and if within 35 days after such plans (including any other particulars reasonably required under sub-paragraph (1)) have been supplied to CRT the engineer has not intimated his disapproval of those plans and the grounds of his disapproval he shall be deemed to have approved the plans as submitted.

(3) When signifying approval of the plans the engineer may specify on land held or controlled by CRT or the undertaker and subject to such works being authorised by the order or being development permitted by an Act of Parliament or general development order made under the 1990 Act

(a)any protective work (whether temporary or permanent) which in the reasonable opinion of the engineer should be carried out before the commencement of a specified work to prevent detriment; and

(b)such other requirements as may be reasonably necessary to prevent detriment; and such protective works shall be constructed by the undertaker or by CRT at the undertaker’s request with all reasonable dispatch and the undertaker shall not commence the construction of a specified work until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction such consent not to be unreasonably withheld or delayed.

(4) The undertaker shall pay to CRT a capitalised sum representing the reasonably increased or additional cost of maintaining and, when necessary, renewing any works, including any permanent protective works provided under sub-paragraph (3) above, and of carrying out any additional dredging of the waterway reasonably necessitated by the exercise of any of the powers under this Order but if the cost of maintaining the waterway, or of works of renewal of the waterway, is reduced in consequence of any such works, a capitalised sum representing such reasonable saving shall be set off against any sum payable by the undertaker to CRT under this paragraph.

(5) In the event that the undertaker fails to complete the construction of, or part of, the specified works CRT may, if it is reasonably required in order to avoid detriment, serve on the undertaker a notice in writing requesting that construction be completed. Any notice served under this sub-paragraph shall state the works that are to be completed by the undertaker and lay out a timetable for the works’ completion. If the undertaker fails to comply with this notice within 35 days, CRT may construct any of the specified works, or part of such works, (together with any adjoining works) in order to complete the construction of, or part of, the specified works or make such works and the undertaker shall reimburse CRT all costs, fees, charges and expenses it has reasonably incurred in carrying out such works.

Design of works

7.  Without prejudice to its obligations under the foregoing provisions of this Schedule the undertaker shall consult, collaborate and respond constructively to any approach, suggestion, proposal or initiative made by CRT on—

(a)the design and appearance of the specified works, including the materials to be used for their construction; and

(b)the environmental effects of those works;

and shall have regard to such views as may be expressed by CRT to the extent that these accord with the requirements of the local planning authority in response to such consultation pursuant in particular to the requirements imposed on CRT by section 22 (general environmental and recreational duties) of the British Waterways Act 1995 and to the interest of CRT in preserving and enhancing the environment of its waterways.

Notice of works

8.  The undertaker shall give to the engineer 30 days’ notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, CRT may where appropriate arrange for the publication of notices bringing those works to the attention of users of CRT’s network.

Lighting

9.  The undertaker shall provide and maintain at its own expense in the vicinity of the specified or protective works such temporary lighting and such signal lights for the control of navigation as the engineer may reasonably require during the construction or failure of the specified or protective works.

Construction of specified works

10.—(1) Any specified or protective works shall, when commenced, be constructed—

(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled as aforesaid and with any requirements made under paragraph 6(3) and paragraph 7;

(b)under the supervision (if given) and to the reasonable satisfaction of the engineer;

(c)in such manner as to cause as little detriment as is reasonably practicable;

(d)in such manner as to cause as little inconvenience as is reasonably practicable to CRT, its officers and agents and all other persons lawfully using the waterways, except to the extent that temporary obstruction has otherwise been agreed by CRT.

(2) Nothing in this Order shall authorise the undertaker to make or maintain any permanent works in or over the waterway so as to impede or prevent (whether by reducing the width of the waterway or otherwise) the passage of any vessel which is of a kind (as to its dimensions) for which CRT is required by section 105(1)(b) and (2) of the Transport Act 1968 to maintain the waterway.

(3) Following the completion of the construction of the specified works the undertaker shall restore the waterway to a condition no less satisfactory than its condition immediately prior to the commencement of those works unless otherwise agreed between the undertaker and CRT.

Prevention of pollution

11.  The undertaker shall not in the course of constructing a specified work or a protective work or otherwise in connection therewith do or permit anything which may result in the pollution of the waterway or the deposit of materials therein and shall take such steps as the engineer may reasonably require to avoid or make good any breach of its obligations under this paragraph.

Access to work – provision of information

12.—(1) The undertaker on being given reasonable notice shall—

(a)at all reasonable times allow reasonable facilities to the engineer for access to a specified work during its construction; and

(b)supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

(2) CRT on being given reasonable notice shall—

(a)at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by CRT under this Schedule during their construction; and

(b)supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker shall reimburse CRT’s reasonable costs in relation to the supply of such information.

Alterations to the waterway

13.—(1) If during the construction of a specified work or a protective work or during a period of twenty four (24) months after the completion of those works any alterations or additions, either permanent or temporary, to the waterway are reasonably necessary in consequence of the construction of the specified work or the protective work in order to avoid detriment, and CRT gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which shall be specified in the notice), the undertaker shall pay to CRT the reasonable costs of those alterations or additions including, in respect of any such alterations or additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by CRT in maintaining, working and, when necessary, renewing any such alterations or additions.

(2) If the cost of maintaining, working or renewing the waterway is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by the undertaker to CRT under this paragraph.

Maintenance of works

14.  If at any time after the completion of a specified work or a protective work, not being a work vested in CRT, CRT gives notice to the undertaker informing it that the state of maintenance of the work appears to be such that the work is causing or likely to cause detriment, the undertaker shall, on receipt of such notice, take such steps as may be reasonably necessary to put the work in such state of maintenance as not to cause such detriment.

Repayment of CRT’s fees, etc.

15.  The undertaker shall repay to CRT in accordance with CRT’s Code of Practice for Works affecting the Canal and River Trust (as amended from time to time) all fees, costs, charges and expenses reasonably incurred by CRT—

(a)in constructing any protective works under the provisions of paragraph 6(3)(a);

(b)in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction or repair of a specified work and any protective works;

(c)in respect of the employment during the construction of the specified works or any protective works of any inspectors, watchmen and other persons whom it shall be reasonably necessary to appoint for inspecting, watching and lighting any waterway and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified works or any protective works; and

(d)in bringing the specified works or any protective works to the notice of users of CRT’s network.

Costs of alterations, etc.

16.  Any additional expenses which CRT may reasonable incur in altering, reconstructing or maintaining the waterway under any powers existing at the date when this Order was made by reason of the existence of a specified work shall, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaired by the undertaker to CRT.

Making good of detriment; compensation and indemnity, etc.

17.—(1) If any detriment shall be caused by the construction or failure of the specified works or the protective works if carried out by the undertaker, the undertaker (if so required by CRT) shall make good such detriment and shall pay to CRT all reasonable expenses to which CRT may be put, and compensation for any loss which CRT may sustain, in making good or otherwise by reason of the detriment.

(2) The undertaker shall be responsible for and make good to CRT all costs, charges, damages, expenses and losses not otherwise provided for in this Schedule which may be occasioned to and reasonably incurred by CRT—

(a)by reason of the construction of a specified work or a protective work or the failure of such a work; or

(b)by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon the construction of a specified work or a protective work; and subject to sub-paragraph (4) the undertaker shall effectively indemnify and hold harmless CRT from and against all claims and demands arising out of or in connection with any of the matters referred to in paragraphs (a) and (b) (provided that, save as expressly set out in this paragraph, CRT shall not be entitled to recover any consequential losses from the undertaker).

(3) The fact that any act or thing may have been done by CRT on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision or in accordance with any directions or awards of an arbitrator shall not (if it was done without negligence on the part of CRT or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this paragraph.

(4) Nothing in sub-paragraph (2) shall impose any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the neglect or wilful default of CRT, its officers, servants, contractors or agents.

(5) CRT shall give the undertaker reasonable notice of any such claim or demand as aforesaid and no settlement or compromise of such a claim or demand shall be made without the prior consent of the undertaker.

(6) The aggregate cap of the undertaker’s gross liability for consequential loses shall be limited to £10,000,000 (ten million pounds) for any one occurrence or all occurrences of a series arising out of the one original cause.

Arbitration

18.  Any difference arising between the undertaker and CRT under this Schedule (other than a difference as to the meaning or construction of this Schedule) shall be referred to and settled by arbitration in accordance with article 36 (arbitration) of this Order.

Capitalised sums

19.  Any capitalised sum which is required to be paid under this Schedule shall be calculated by multiplying the cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.

(2)

S.I. 2010/490. There are amendments to these Regulations which are not relevant to this Order.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources