The A63 (Castle Street Improvement, Hull) Development Consent Order 2020

Changes over time for: The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (without Schedules)

 Help about opening options

Version Superseded: 29/10/2020

Alternative versions:

Status:

Point in time view as at 18/06/2020.

Changes to legislation:

There are currently no known outstanding effects for the The A63 (Castle Street Improvement, Hull) Development Consent Order 2020. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1 E+WPRELIMINARY

Citation and commencementE+W

1.  This Order may be cited as the A63 (Castle Street Improvement, Hull) Development Consent Order 2020 and comes into force on 18th June 2020.

Commencement Information

I1Art. 1 in force at 18.6.2020, see art. 1

InterpretationE+W

2.—(1) In this Order—

the 1961 Act” means the Land Compensation Act 1961 M1;

the 1965 Act” means the Compulsory Purchase Act 1965 M2;

the 1980 Act” means the Highways Act 1980 M3;

the 1981 Act” means the Compulsory Purchase (Vesting Declarations) Act 1981 M4;

the 1984 Act” means the Road Traffic Regulation Act 1984 M5;

the 1990 Act” means the Town and Country Planning Act 1990 M6;

the 1991 Act” means the New Roads and Street Works Act 1991 M7;

the 2008 Act” means the Planning Act 2008 M8;

address” includes any number or address for the purposes of electronic transmission;

apparatus” has the same meaning as in Part 3 of the 1991 Act;

authorised development” means the development and associated development described in Schedule 1 (authorised development) or any part of it, which is development within the meaning of section 32 (meaning of development) of the 2008 Act;

the book of reference” means the document certified by the Secretary of State under article 41 (certification of documents etc.) as the book of reference for the purposes of this Order;

“British Telecommunications PLC” and “BT” means the company registered in England and Wales, company number 01800000, whose registered address is 81 Newgate Street, London EC1A 7AJ;

building” includes any structure or erection or any part of a building, structure or erection;

carriageway” has the same meaning as in the 1980 Act and includes part of a carriageway;

CEMP” means construction environmental management plan;

commence” means beginning to carry out any material operation (as defined in section 155 of the 2008 Act) forming part of the authorised development other than operations consisting of archaeological investigations, environmental surveys and monitoring, investigations for the purpose of assessing ground conditions, erection of any temporary means of enclosure or the temporary display of site notices or advertisements and “commencement” is to be construed accordingly;

cycle track” has the same meaning as in the 1980 Act and includes part of a cycle track M9;

electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

the engineering drawings and sections” means the drawings and sections certified by the Secretary of State under article 41 (certification of documents etc.) as the engineering drawings and sections for the purposes of this Order;

environmental statement” means the document of that description certified by the Secretary of State under article 41 (certification of documents etc.) as the environmental statement for the purposes of this Order;

footway” and “footpath” have the same meaning as in the 1980 Act and include part of a footway or footpath;

highway”, “highway authority” and “local highway authority” have the same meaning as in the 1980 Act and “highway” includes part of a highway;

Historic England” means the Historic Buildings and Monuments Commission for England;

“KCOM Group PLC” and “KCOM” means the company registered in England and Wales, company number 02150618, whose registered address is 37 Carr Lane, Hull, East Yorkshire, HU1 3RE;

the land plans” means the plans certified by the Secretary of State under article 41 (certification of documents etc.) as the land plans for the purposes of this Order;

limits of deviation” means the limits of deviation referred to in article 6 (limits of deviation);

maintain” in relation to the authorised development includes to inspect, repair, adjust, alter, remove or reconstruct to the extent that is unlikely to give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement and any derivative of “maintain” is to be construed accordingly;

Northern Gas Networks Limited” means the company registered in England and Wales, company number 05167070, whose registered address is 1100 Century Way, Thorpe Park Business Park, Colton, Leeds LS15 8TU;

Northern Powergrid Limited” means the company registered in England and Wales, company number 03271033, whose registered address is Lloyds Court, 78 Grey Street, Newcastle Upon Tyne NE1 6AF;

OEMP” means the outline CEMP certified by the Secretary of State under article 41 (certification of documents etc.) as the OEMP for the purposes of this Order;

Order land” means the land shown on the land plans which is within the Order limits and described in the book of reference;

the Order limits” means the limits of lands to be acquired or used permanently or temporarily shown on the land plans and the works plans within which the authorised development may be carried out;

owner”, in relation to land, has the same meaning as in section 7 (interpretation) of the Acquisition of Land Act 1981 M10;

relevant planning authority” means in any given provision of this Order, the planning authority for the area to which the provision relates;

statutory undertaker” means any statutory undertaker for the purposes of section 127(8), of the 2008 Act;

street” means a street within the meaning of section 48 (streets, street works and undertakers) of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes part of a street;

street authority”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act;

streets, rights of way and access plans” means the plans certified by the Secretary of State under article 41 (certification of documents etc.) as the streets, rights of way and access plans for the purposes of this Order;

traffic authority” has the same meaning as in section 121A M11 (traffic authorities) of the 1984 Act;

the tribunal” means the Lands Chamber of the Upper Tribunal;

trunk road” means a highway which is a trunk road by virtue of—

(a)

section 10 M12 (general provision as to trunk roads) or 19(1) M13 (certain special roads and other highways to become trunk roads) of the 1980 Act;

(b)

an order or direction under section 10 of that Act; or

(c)

an order granting development consent; or

(d)

any other enactment;

undertaker” means Highways England Company Limited (Company No. 09346363) whose registered office is Bridge House, 1 Walnut Tree Close, Guildford, Surrey, GU1 4LZ;

watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain;

the works plans” means the plans certified by the Secretary of State under article 41 (certification of documents etc.) as the works plans for the purposes of this Order; and

“Yorkshire Water Services Limited” and “YW” means the company registered in England and Wales, company number 02366682, whose registered address is Western House, Halifax Road, Bradford, West Yorkshire, BD6 2SZ.

(2) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the airspace above its surface and references in this Order to the imposition of restrictive covenants are references to the creation of rights over land which interfere with the interests or rights of another and are for the benefit of land which is acquired under this Order or is otherwise comprised in the Order land.

(3) All distances, directions and lengths referred to in this Order are approximate and distances between points on a work comprised in the authorised development are taken to be measured along that work.

(4) For the purposes of this Order, all areas described in square metres in the book of reference are approximate.

(5) References in this Order to points identified by letters or numbers are to be construed as references to points so lettered or numbered on the streets, rights of way and access plans.

(6) References in this Order to numbered works are references to works as numbered in Schedule 1 (authorised development).

Commencement Information

I2Art. 2 in force at 18.6.2020, see art. 1

Marginal Citations

M61990 c. 8. Section 206(1) was amended by section 192(8) of, and paragraphs 7 and 11 of Schedule 8 to, the Planning Act 2008 (c. 29) (date in force to be appointed see section 241(3), (4)(a) and (c) of the 2008 Act). There are other amendments to the 1990 Act which are not relevant to this Order.

M9The definition of “cycle track” (in section 329(1) of the 1980 Act) was amended by section 1 of the Cycle Tracks Act 1984 (c. 38) and section 4 of, and paragraph 21(2) of Schedule 3 to the Road Traffic (Consequential Provisions) Act 1988 (c. 54).

M101981 c. 67. The definition of “owner” was amended by paragraph 9 of Schedule 15 to the Planning and Compensation Act 1991 (c. 34). There are other amendments to section 7 which are not relevant to the Order.

M11Section 121A was inserted by section 168(1) of, and paragraph 70 of Schedule 8 to, the 1991 Act. It was amended by section 1(6) of, and paragraphs 70 and 95(2) and (3) of Schedule 1 to the Infrastructure Act 2015 (c. 7). There are other amendments to section 121A which are not relevant to this Order.

M12Section 10 was amended by section 22(2) of the 1991 Act, by section 36 of, and paragraph 22 of Schedule 2 to the 2008 Act, and by section 1(6) of, and paragraph 10 of Schedule 1 to, the Infrastructure Act 2015.

M13Section 19(1) was amended by section 1(6) of, and paragraph 15 of Schedule 1 to, the Infrastructure Act 2015.

PART 2 E+WPRINCIPAL POWERS

Development consent etc. granted by the OrderE+W

3.—(1) Subject to the provisions of this Order including the requirements in Schedule 2 (requirements), the undertaker is granted development consent for the authorised development to be carried out within the Order limits.

(2) Any enactment applying to land within or adjacent to the Order limits has effect subject to the provisions of this Order.

Commencement Information

I3Art. 3 in force at 18.6.2020, see art. 1

Maintenance of authorised developmentE+W

4.  The undertaker may at any time maintain the authorised development, except to the extent that this Order, or an agreement made under this Order, provides otherwise.

Commencement Information

I4Art. 4 in force at 18.6.2020, see art. 1

Maintenance of drainage worksE+W

5.—(1) Nothing in this Order, or the construction, maintenance or operation of the authorised development under it, affects any responsibility for the maintenance of any works connected with the drainage of land, whether that responsibility is imposed or allocated by or under any enactment, or otherwise, unless otherwise agreed in writing between the undertaker and the person responsible.

(2) In this article “drainage” has the same meaning as in section 72 (interpretation) of the Land Drainage Act 1991 M14.

Commencement Information

I5Art. 5 in force at 18.6.2020, see art. 1

Marginal Citations

M141991 c. 59. The definition was substituted by section 100(2) of the Environment Act 1995 (c. 25).

Limits of deviationE+W

6.  In carrying out the authorised development the undertaker may—

(a)deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation shown on those plans; and

(b)deviate vertically from the levels of the authorised development shown on the engineering drawings and sections to a maximum of 0.5 metres upwards or downwards,

except that these maximum limits of vertical deviation do not apply where it is demonstrated by the undertaker to the Secretary of State's satisfaction and the Secretary of State, following consultation with the relevant planning authority, certifies accordingly that a deviation in excess of these limits would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

Commencement Information

I6Art. 6 in force at 18.6.2020, see art. 1

Benefit of OrderE+W

7.—(1) Subject to paragraph (2) and article 8 (consent to transfer benefit of Order), the provisions of this Order conferring powers on the undertaker have effect solely for the benefit of the undertaker.

(2) Paragraph (1) does not apply to the works for which the consent is granted by this Order for the express benefit of owners and occupiers of land, statutory undertakers and other persons affected by the authorised development.

Commencement Information

I7Art. 7 in force at 18.6.2020, see art. 1

Consent to transfer benefit of OrderE+W

8.—(1) Subject to paragraph (4), the undertaker may—

(a)transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order and such related statutory rights as may be agreed between the undertaker and the transferee; or

(b)grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order and such related statutory rights as may be so agreed.

(2) Where an agreement has been made in accordance with paragraph (1) references in this Order to the undertaker, except in paragraph (3), includes references to the transferee or the lessee.

(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.

(4) The consent of the Secretary of State is required for a transfer or grant under this article, except where the transfer or grant is made to—

(a)British Telecommunications PLC for the purposes of undertaking works numbers 3, 6 and 11;

(b)KCOM Group PLC for the purposes of undertaking works numbers 8 and 11;

(c)Northern Gas Networks Limited for the purposes of undertaking works under parts (e) and (f) of Schedule 1;

(d)Northern Powergrid Limited for the purposes of undertaking works under parts (e) and (f) of Schedule 1; or

(e)Yorkshire Water Services Limited for the purposes of undertaking works numbers 10 and 23.

Commencement Information

I8Art. 8 in force at 18.6.2020, see art. 1

PART 3 E+WSTREETS

Application of the 1991 ActE+W

9.—(1) Works executed under this Order in relation to a highway which consists of or includes a carriageway are to be treated for the purposes of Part 3 (street works in England and Wales) of the 1991 Act as major highway works if—

(a)they are of a description mentioned in any of paragraphs (a), (c) to (e), (g) and (h) of section 86(3) of that Act (which defines what highway authority works are major highway works); or

(b)they are works which, had they been executed by the highway authority, might have been carried out in exercise of the powers conferred by section 64 M15 (dual carriageways and roundabouts) of the 1980 Act or section 184 M16 (vehicle crossings over footways and verges) of that Act.

(2) In Part 3 of the 1991 Act, in relation to works which are major highway works by virtue of paragraph (1), references to the highway authority concerned are to be construed as references to the undertaker.

(3) The following provisions of Part 3 the 1991 Act do not apply in relation to any works executed under the powers of this Order—

  • section 56 M17 (directions as to timing);

  • section 56A M18 (power to give directions as to placing of apparatus);

  • section 58 M19 (restrictions following substantial road works);

  • section 58A M20 (restriction on works following substantial street works);

  • section 73A M21 (power to require undertaker to re-surface street);

  • section 73B M22 (power to specify timing etc. of re-surfacing);

  • section 73C M23 (materials, workmanship and standard of re-surfacing);

  • section 78A M24 (contributions to costs of re-surfacing by undertaker); and

  • Schedule 3A M25 (restriction on works following substantial street works).

(4) The provisions of the 1991 Act mentioned in paragraph (5) (which, together with other provisions of that Act, apply in relation to the execution of street works) and any regulations made, or code of practice issued or approved under, those provisions apply (with the necessary modifications) in relation to any stopping up, alteration or diversion of a street of a temporary nature by the undertaker under the powers conferred by article 12 (temporary stopping up and restriction of use of streets), whether or not the stopping up, alteration or diversion constitutes street works within the meaning of that Act.

(5) The provisions of the 1991 Act M26 referred to in paragraph (4) are—

  • section 54 M27 (advance notice of certain works), subject to paragraph (6);

  • section 55 M28 (notice of starting date of works), subject to paragraph (6);

  • section 57 M29 (notice of emergency works);

  • section 59 M30 (general duty of street authority to co-ordinate works);

  • section 60 (general duty of undertakers to co-operate);

  • section 68 (facilities to be afforded to street authority);

  • section 69 (works likely to affect other apparatus in the street);

  • section 75 (inspection fees);

  • section 76 (liability for cost of temporary traffic regulation); and

  • section 77 (liability for cost of use of alternative route),

and all such other provisions as apply for the purposes of the provisions mentioned above.

(6) Sections 54 and 55 of the 1991 Act as applied by paragraph (4) have effect as if references in section 57 of that Act to emergency works were a reference to a stopping up, alteration or diversion (as the case may be) required in a case of emergency.

(7) Nothing in article 10 (construction and maintenance of new, altered or diverted streets and other structures)—

(a)affects the operation of section 87 (prospectively maintainable highways) of the 1991 Act, and the undertaker is not by reason of any duty under that article to maintain a street, to be taken to be the street authority in relation to that street for the purposes of Part 3 of that Act; or

(b)has effect in relation to maintenance works which are street works within the meaning of the 1991 Act, as respects which the provisions of Part 3 of the 1991 Act apply.

Commencement Information

I9Art. 9 in force at 18.6.2020, see art. 1

Marginal Citations

M15Section 64 was amended by section 102 of, and Schedule 17 to the Local Government Act 1985 (c. 51) and section 168(2) of, and Schedule 9 to the 1991 Act.

M16Section 184 was amended by section 4 of, and Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and Schedule 8 to the 1991 Act and by sections 35, 38 and 46 of the Criminal Justice Act 1982 (c. 48).

M17Section 56 was amended by sections 40 and 43 of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).

M18Section 56A was inserted by section 44 of the Traffic Management Act 2004.

M19Section 58 was amended by sections 40 and 51 of, and Schedule 1 to, the Traffic Management Act 2004.

M20Section 58A was inserted by section 52 of the Traffic Management Act 2004.

M21Section 73A was inserted by section 55 of the Traffic Management Act 2004.

M22Section 73B was inserted by section 55 of the Traffic Management Act 2004.

M23Section 73C was inserted by section 55 of the Traffic Management Act 2004.

M24Section 78A was inserted by section 57 of the Traffic Management Act 2004.

M25Schedule 3A was inserted by section 52 of, and Schedule 4 to the Traffic Management Act 2004.

M26Sections 54, 55, 57, 60, 68 and 69 were amended by section 40(1) and (2) of, and Schedule 1 to, the Traffic Management Act 2004.

M27Section 54 was also amended by section 49(1) of the Traffic Management Act 2004.

M28Section 55 was also amended by sections 49(2) and 51(9) of the Traffic Management Act 2004.

M29Section 57 was also amended by section 52(3) of the Traffic Management Act 2004.

M30Section 59 was amended by section 42 of the Traffic Management Act 2004.

Construction and maintenance of new, altered or diverted streets and other structuresE+W

10.—(1) Subject to paragraph (3), any street (other than a trunk road) to be constructed under this Order must be completed to the reasonable satisfaction of the local highway authority in whose area the street lies and, unless otherwise agreed in writing with the local highway authority, must be maintained by and at the expense of the local highway authority from its completion.

(2) Where a street (other than a trunk road) is altered or diverted under this Order, the altered or diverted part of the street must, when completed to the reasonable satisfaction of the street authority in whose area the street lies and, unless otherwise agreed in writing with the local street authority, be maintained by and at the expense of the local street authority from its completion.

(3) In the case of a bridge constructed under this Order to carry a highway (other than a trunk road) over a trunk road, the highway surface (being those elements over the waterproofing membrane) must be maintained by and at the expense of the local highway authority and the remainder of the bridge, including the waterproofing membrane and structure below, must be maintained by and at the expense of the undertaker.

(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.

(5) For the purposes of a defence under paragraph (4), the court must in particular have regard to the following matters—

(a)the character of the street and the traffic which was reasonably to be expected to use it;

(b)the standard of maintenance appropriate for a street of that character and used by such traffic;

(c)the state of repair in which a reasonable person would have expected to find the street;

(d)whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street; and

(e)where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed,

but for the purposes of such a defence it is not relevant to prove that the undertaker had arranged for a competent person to carry out or supervise the maintenance of the part of the street to which the action relates unless it is also proved that the undertaker had given the competent person proper instructions with regard to the maintenance of the street and that the competent person had carried out those instructions.

Commencement Information

I10Art. 10 in force at 18.6.2020, see art. 1

Classification of roads, etc.E+W

11.—(1) On the date on which the roads described in Parts 1 and 2 of Schedule 3 (classification of roads, etc.) are completed and open for traffic—

(a)the roads described in columns (1) and (2) of Part 1 (trunk roads) of Schedule 3 are to become trunk roads as if they had become so by virtue of an order under section 10(2) (general provision as to trunk roads) of the 1980 Act specifying that date as the date on which they were to become trunk roads;

(b)the roads described in column (1) of Part 2 (other road classifications) of Schedule 3 take the classification specified in column (3) of that Part, to the extent described in column (2) of that Part; and

(c)the roads given a classification in column (3) of Part 2 of Schedule 3 are to be classified roads for the purpose of any enactment or instrument which refers to highways classified as classified roads, as if such classification had been made under section 12(3) (general provision as to principal and classified roads) of the 1980 Act.

(2) From the date on which the roads specified in Part 3 (roads subject to 30 miles per hour limit) of Schedule 3 are open for traffic, no person is to drive any motor vehicle at a speed exceeding 30 miles per hour in the lengths of road identified in that Part of that Schedule.

(3) From the date on which the roads specified in Part 4 (roads subject to 40 miles per hour limit) of Schedule 3 are open for traffic, no person is to drive any motor vehicle at a speed exceeding 40 miles per hour in the lengths of road identified in that Part of that Schedule.

(4) From the date on which the road specified in column (1) of Part 5 (road subject to one way restriction) of Schedule 3 is open for traffic it will be subject to one way restrictions to the extent specified in column (2) of that Part of that Schedule.

(5) From the date on which the roads specified in column (1) of Part 6 (roads subject to two way traffic) of Schedule 3 are completed and open for traffic their one way restrictions will be removed to the extent specified in column (2) of that Part of that Schedule.

(6) From the date on which the roads specified in column (1) of Part 7 (roads subject to prohibition of parking – no waiting or loading at any time) of Schedule 3 are open for traffic they will be subject to the restrictions to the extent specified in column (2) of that Part of that Schedule.

(7) Unless otherwise agreed with the relevant planning authority, the cycle tracks and footways specified in column (2) of Part 8 (cycle tracks and footways) of Schedule 3 and as identified on the rights of way and access plans are to be constructed by the undertaker in the specified locations and open for use no later than the date on which the authorised development is open for traffic.

(8) Unless otherwise agreed with the relevant land owner, the private means of access specified in column (2) of Part 9 (private means of access) of Schedule 3 and as identified on the rights of way and access plans are to be constructed by the undertaker in the specified locations and open for use no later than the date on which the authorised development is open for traffic.

(9) Unless otherwise agreed with the relevant land owner, the public rights of way specified in column (2) of Part 10 (public rights of way) of Schedule 3 and as identified on the rights of way and access plans are to be constructed by the undertaker and open for use no later than the date on which the authorised development is open for traffic.

(10) Unless otherwise agreed with the relevant planning authority the uncontrolled crossing specified in column (2) of Part 11 (uncontrolled crossing) of Schedule 3 and as identified on the non-motorised user route plans are to be constructed by the undertaker in the specified locations and open for use no later than the date on which the authorised development is open for traffic.

(11) The application of paragraphs (1) to (10) may be varied or revoked by any instrument made under any enactment which provides for the variation or revocation of such matters.

Commencement Information

I11Art. 11 in force at 18.6.2020, see art. 1

Temporary stopping up and restriction of use of streetsE+W

12.—(1) The undertaker, during and for the purposes of carrying out the authorised development, may temporarily stop up, alter, divert or restrict the use of any street and may for any reasonable time—

(a)divert the traffic from the street; and

(b)subject to paragraph (3), prevent all persons from passing along the street.

(2) Without limitation on the scope of paragraph (1), the undertaker may use any street temporarily stopped up or restricted under the powers conferred by this article and which is within the Order limits as a temporary working site.

(3) The undertaker must provide reasonable access for pedestrians going to or from premises abutting a street affected by the temporary stopping up, alteration, diversion or restriction of a street under this article if there would otherwise be no such access.

(4) The undertaker must not temporarily stop up, alter, divert or restrict any street for which it is not the street authority without the consent of the street authority, which may attach reasonable conditions to any consent but such consent must not be unreasonably withheld or delayed.

(5) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) If a street authority which receives an application for consent under paragraph (4) fails to notify the undertaker of its decision before the end of the period of 28 days beginning with the date on which the application was made, it is deemed to have granted consent.

Commencement Information

I12Art. 12 in force at 18.6.2020, see art. 1

Permanent stopping up and restriction of use of streets and private means of accessE+W

13.—(1) Subject to the provisions of this article, the undertaker may, in connection with the carrying out of the authorised development, stop up each of the streets and private means of access specified in column (2) of Parts 1 and 2 of Schedule 4 (permanent stopping up of streets and private means of access), and column (1) of Parts 3 and 4 of that Schedule to the extent specified and described in column (3) of Parts 1 and 2 of that Schedule and column (2) of Parts 3 and 4 of that Schedule.

(2) No street or private means of access specified in column (2) of Part 1 and column (1) of Part 3 of Schedule 4 is to be wholly or partly stopped up under this article unless—

(a)the new street or private means of access to be constructed and substituted for it, which is specified in column (4) or (3) of those Parts of that Schedule respectively, has been completed to the reasonable satisfaction of the street authority and is open for use; or

(b)a temporary alternative route for the passage of such traffic as could have used the street or private means of access to be stopped up is first provided and subsequently maintained by the undertaker, to the reasonable satisfaction of the street authority, between the commencement and termination points for the stopping up of the street or private means of access until the completion and opening of the new street or private means of access in accordance with sub-paragraph (a).

(3) No street or private means of access specified in column (2) of Part 2 of Schedule 4 or column (1) of Part 4 of that Schedule is to be wholly or partly stopped up under this article unless the condition specified in paragraph (4) is satisfied in relation to all the land which abuts on either side of the street or private means of access to be stopped up.

(4) The condition referred to in paragraph (3) is that—

(a)the undertaker is in possession of the land; or

(b)there is no right of access to the land from the street or private means of access concerned; or

(c)there is reasonably convenient access to the land otherwise than from the street or private means of access concerned; or

(d)the owners and occupiers of the land have agreed to the stopping up.

(5) Where a street or private means of access has been stopped up under this article—

(a)all rights of way over or along the street or private means of access so stopped up are extinguished; and

(b)the undertaker may appropriate and use for the purposes of the authorised development so much of the site of the street or private means of access as is bounded on both sides by land owned by the undertaker.

(6) Any person who suffers loss by the suspension or extinguishment of any private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(7) This article is subject to article 32 (apparatus and rights of statutory undertakers in stopped up streets).

Commencement Information

I13Art. 13 in force at 18.6.2020, see art. 1

Access to worksE+W

14.  The undertaker may, for the purposes of the authorised development, form and lay out means of access, or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.

Commencement Information

I14Art. 14 in force at 18.6.2020, see art. 1

ClearwaysE+W

15.—(1) From the date on which the roads described in Part 1 of Schedule 3 (classification of roads, etc.) are open for traffic, except as provided in paragraph (2), no person is to cause or permit any vehicle to wait on any part of those roads, other than a lay-by, except upon the direction of, or with the permission of, a uniformed constable or uniformed traffic officer.

(2) Nothing in paragraph (1) may apply—

(a)to render it unlawful to cause or permit a vehicle to wait on any part of a road, for so long as may be necessary to enable that vehicle to be used in connection with—

(i)the removal of any obstruction to traffic;

(ii)the maintenance, improvement, reconstruction or operation of the road;

(iii)the laying, erection, maintenance or renewal in or near the road of any sewer, main pipe, conduit, wire, cable or other apparatus for the supply of gas, water, electricity or any electronic communications apparatus as defined in Schedule 3A (the electronic communications code) to the Communications Act 2003 M31; or

(iv)any building operation or demolition;

(b)in relation to a vehicle being used—

(i)for police, ambulance, fire and rescue authority or traffic officer purposes;

(ii)in the service of a local authority, safety camera partnership or Driver and Vehicle Standards Agency in pursuance of statutory powers or duties;

(iii)in the service of a water or sewerage undertaker within the meaning of the Water Industry Act 1991 M32; or

(iv)by a universal service provider for the purposes of providing a universal postal service as defined by the Postal Service Act 2000 M33; or

(c)in relation to a vehicle waiting when the person in control of it is—

(i)required by law to stop;

(ii)obliged to stop in order to avoid an accident; or

(iii)prevented from proceeding by circumstances outside the persons control.

(3) No person is to cause or permit any vehicle to wait on any part of the roads described in Part 1 of Schedule 3 for the purposes of selling, or dispensing of, goods from that vehicle, unless the goods are immediately delivered at, or taken into, premises adjacent to the land on which the vehicle stood when the goods were sold or dispensed.

(4) Paragraphs (1), (2) and (3) have effect as if made by order under the 1984 Act, and their application may be varied or revoked by an order made under that Act or any other enactment which provides for the variation or revocation of such orders.

(5) In this article, “traffic officer” means an individual designated under section 2 (designation of traffic officers) of the Traffic Management Act 2004 M34.

Commencement Information

I15Art. 15 in force at 18.6.2020, see art. 1

Marginal Citations

M312003 c. 21. Schedule 3A was inserted by section 4(2) of, and Schedule 1 to, the Digital Economy Act 2017 (c. 30).

Traffic regulationE+W

16.—(1) This article applies to roads in respect of which the undertaker is not the traffic authority.

(2) Subject to the provisions of this article, and the consent of the traffic authority in whose area the road concerned is situated, which consent must not be unreasonably withheld, the undertaker may, for the purposes of the authorised development—

(a)revoke, amend or suspend in whole or in part any order made, or having effect as if made, under the 1984 Act;

(b)permit, prohibit or restrict the stopping, waiting, loading or unloading of vehicles on any road;

(c)authorise the use as a parking place of any road;

(d)make provision as to the direction or priority of vehicular traffic on any road; and

(e)permit or prohibit vehicular access to any road,

either at all times or at times, on days or during such periods as may be specified by the undertaker.

(3) The power conferred by paragraph (2) may be exercised at any time prior to the expiry of 12 months from the opening of the authorised development for public use but subject to paragraph (7) any prohibition, restriction or other provision made under paragraph (2) may have effect both before and after the expiry of that period.

(4) The undertaker must consult the chief officer of police and the traffic authority in whose area the road is situated before complying with the provisions of paragraph (5).

(5) The undertaker must not exercise the powers conferred by paragraph (2) unless it has—

(a)given not less than—

(i)12 weeks' notice in writing of its intention so to do in the case of a prohibition, restriction or other provision intended to have effect permanently; or

(ii)4 weeks' notice in writing of its intention so to do in the case of a prohibition, restriction or other provision intended to have effect temporarily,

to the chief officer of police and to the traffic authority in whose area the road is situated; and

(b)advertised its intention in such manner as the traffic authority may specify in writing within 28 days of its receipt of notice of the undertaker's intention in the case of sub-paragraph (a)(i), or within 7 days of its receipt of notice of the undertaker's intention in the case of sub-paragraph (a)(ii).

(6) Any prohibition, restriction or other provision made by the undertaker under paragraph (2)—

(a)has effect as if duly made by, as the case may be—

(i)the traffic authority in whose area the road is situated, as a traffic regulation order under the 1984 Act; or

(ii)the local authority in whose area the road is situated, as an order under section 32 M35 (power of local authorities to provide parking spaces) of the 1984 Act,

and the instrument by which it is effected may specify savings and exemptions to which the prohibition, restriction or other provision is subject; and

(b)is deemed to be a traffic order for the purposes of Schedule 7 (road traffic contraventions subject to civil enforcement) to the Traffic Management Act 2004 M36.

(7) Any prohibition, restriction or other provision made under this article may be suspended, varied or revoked by the undertaker from time to time by subsequent exercise of the powers conferred by paragraph (2) within a period of 24 months from the opening of the authorised development.

(8) Before exercising the powers of paragraph (2) the undertaker must consult such persons as it considers necessary and appropriate and must take into consideration any representations made to it by any such person.

(9) Expressions used in this article and in the 1984 Act have the same meaning in this article as in that Act.

(10) The powers conferred on the undertaker by this article with respect to any road have effect subject to any agreement entered into by the undertaker with any person with an interest in (or who undertakes activities in relation to) premises served by the road.

(11) If the traffic authority fails to notify the undertaker of its decision within 28 days of receiving an application for consent under paragraph (2) the traffic authority is deemed to have granted consent.

Commencement Information

I16Art. 16 in force at 18.6.2020, see art. 1

Marginal Citations

M35Section 32 was amended by section 102 of, and Schedule 17 to, the Local Government Act 1985 (c. 51) and section 168(1) of, and paragraph 39 of Schedule 8 to, the 1991 Act.

PART 4 E+WSUPPLEMENTAL POWERS

Discharge of waterE+W

17.—(1) Subject to paragraphs (3) and (4) the undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out, maintenance or use of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker under paragraph (1) is to be determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 1991 M37.

(3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose, but must not be unreasonably withheld.

(4) The undertaker must not make any opening into any public sewer or drain except—

(a)in accordance with plans approved by the person to whom the sewer or drain belongs, but such approval must not be unreasonably withheld; and

(b)where that person has been given the opportunity to supervise the making of the opening.

(5) The undertaker must not, in carrying out or maintaining works under this article, damage or interfere with the bed or banks of any watercourse forming part of a main river.

(6) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is free from gravel, soil or other solid substance, oil or matter in suspension.

(7) Nothing in this article overrides the requirement for an environmental permit under regulation 12 (requirement for an environmental permit) of the Environmental Permitting (England and Wales) Regulations 2016 M38.

(8) In this article—

(a)public sewer or drain” means a sewer or drain which belongs to the Homes and Communities Agency, the Environment Agency, an internal drainage board, a joint planning board, a local authority, a sewerage undertaker or an urban development corporation; and

(b)other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991 M39 have the same meaning as in that Act.

(9) If a person who receives an application for consent under paragraph (3) or approval under paragraph (4)(a) fails to notify the undertaker of a decision within 28 days of receiving an application that person will be deemed to have granted consent or given approval, as the case may be.

Commencement Information

I17Art. 17 in force at 18.6.2020, see art. 1

Marginal Citations

M371991 c. 56. Section 106 was amended by section 35(1) and (8) of, and Schedule 2 to, the Competition and Service (Utilities) Act 1992 (c. 43), sections 36(2) and 99 of the Water Act 2003 (c. 37) and section 32 of, and paragraph 16(1) of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).

M38S.I. 2016/1154. Regulation 12 was amended by 2018/110.

Protective work to buildingsE+W

18.—(1) Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building which may be affected by the authorised development as the undertaker considers necessary or expedient.

(2) Protective works may be carried out—

(a)at any time before or during the carrying out in the vicinity of the building of any part of the authorised development; or

(b)after the completion of that part of the authorised development in the vicinity of the building at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised development is first opened for use.

(3) For the purpose of determining how the functions under this article are to be exercised the undertaker may enter and survey any building falling within paragraph (1) and any land within its curtilage.

(4) For the purpose of carrying out protective works under this article to a building the undertaker may (subject to paragraphs (5) and (6))—

(a)enter the building and any land within its curtilage; and

(b)where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building but outside its curtilage, enter the adjacent land (but not any building erected on it).

(5) Before exercising—

(a)a right under paragraph (1) to carry out protective works to a building;

(b)a right under paragraph (3) to enter a building and land within its curtilage;

(c)a right under paragraph (4)(a) to enter a building and land within its curtilage; or

(d)a right under paragraph (4)(b) to enter land,

the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days' notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specifying the protective works proposed to be carried out.

(6) Where a notice is served under paragraph (5)(a), (c) or (d), the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article 43 (arbitration).

(7) Where the proposed protective works would, but for the provisions of this Order, require consent under section 8 (authorisation of works: listed building consent) of the Planning (Listed Buildings and Conservation Areas) Act 1990 M40 (other than in respect of the buildings identified in Work No.30 of Schedule 1), the undertaker may not serve a notice under paragraph (5(a) until a description of the proposed protective works has been submitted to and approved in writing by the Secretary of State following consultation with—

(a)the relevant planning authority; and

(b)Historic England (if Historic England would have been required to be notified of the application for consent under section 8 by a direction given under section 15(5) of that Act) M41.

(8) The undertaker must compensate the owners and occupiers of any building or land in relation to which rights under this article have been exercised for any loss or damage arising to them by reason of the exercise of those rights.

(9) Where—

(a)protective works are carried out under this article to a building; and

(b)within the period of 5 years beginning with the day on which the part of the authorised development carried out in the vicinity of the building is first opened for use it appears that the protective works are inadequate to protect the building against damage caused by the carrying out or use of that part of the authorised development,

the undertaker must compensate the owners and occupiers of the building for any loss or damage sustained by them.

(10) Nothing in this article relieves the undertaker from any liability to pay compensation under section 152 M42 (compensation in case where no right to claim in nuisance) of the 2008 Act.

(11) Any compensation payable under paragraph (8) or (9) is to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(12) In this article “protective works” in relation to a building means—

(a)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the carrying out, maintenance or use of the authorised development; and

(b)any works the purpose of which is to remedy any damage which has been caused to the building by the carrying out, maintenance or use of the authorised development.

Commencement Information

I18Art. 18 in force at 18.6.2020, see art. 1

Marginal Citations

M401990 c. 9. Section 8 was modified in relation to buildings in conservation areas by S.I. 1990/1519.

M41See the Arrangements for Handling Heritage Applications – Notification to Historic England and National Amenity Societies and the Secretary of State (England) Direction 2015.

Authority to survey and investigate the landE+W

19.—(1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or which may be affected by the authorised development and—

(a)survey or investigate the land;

(b)without limitation to the scope of sub-paragraph (a), make trial holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;

(c)without limitation to the scope of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and

(d)place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes.

(2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days' notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker—

(a)must, if so required, before or after entering the land, produce written evidence of their authority to do so; and

(b)may take onto the land such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.

(4) No trial holes are to be made under this article—

(a)in land located within a highway boundary without the consent of the highway authority; or

(b)in a private street without the consent of the street authority,

but such consent must not be unreasonably withheld.

(5) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) If either a highway authority or street authority which receives an application for consent fails to notify the undertaker of its decision within 28 days of receiving the application for consent—

(a)under paragraph (4)(a) in the case of a highway authority; or

(b)under paragraph (4)(b) in the case of a street authority,

that authority will be deemed to have granted consent.

Commencement Information

I19Art. 19 in force at 18.6.2020, see art. 1

PART 5 E+WPOWERS OF ACQUISITION AND POSSESSION

Compulsory acquisition of landE+W

20.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development, or to facilitate it, or is incidental to it, or is required as replacement land.

(2) This article is subject to paragraph (2) of article 23 (compulsory acquisition of rights and restrictive covenants) and paragraph (9) of article 29 (temporary use of land for carrying out the authorised development).

Commencement Information

I20Art. 20 in force at 18.6.2020, see art. 1

Compulsory acquisition of land – incorporation of the mineral codeE+W

21.  Part 2 of Schedule 2 to the Acquisition of Land Act 1981 M43 (minerals) is incorporated in this Order subject to the modification that for “the acquiring authority” substitute “ the undertaker ”.

Commencement Information

I21Art. 21 in force at 18.6.2020, see art. 1

Marginal Citations

Time limit for exercise of authority to acquire land compulsorilyE+W

22.—(1) After the end of the period of 5 years beginning on the day on which this Order is made—

(a)no notice to treat is to be served under Part 1 of the 1965 Act; and

(b)no declaration is to be executed under section 4 (execution of declaration) of the 1981 Act as applied by article 26 (application of the 1981 Act).

(2) The authority conferred by article 29 (temporary use of land for carrying out the authorised development) ceases at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Commencement Information

I22Art. 22 in force at 18.6.2020, see art. 1

Compulsory acquisition of rights and restrictive covenantsE+W

23.—(1) Subject to paragraphs (2) to (4), the undertaker may acquire such rights over the Order land, or impose restrictive covenants affecting the Order land, as may be required for any purpose for which that land may be acquired under article 20 (compulsory acquisition of land) by creating them as well as acquiring rights already in existence.

(2) In the case of the Order land specified in column (1) of Schedule 5 (land in which only new rights etc. may be acquired) the undertaker's powers of compulsory acquisition are limited to the acquisition of such wayleaves, easements, new rights in the land or the imposition of restrictive covenants, as may be required for the purpose specified in relation to that land in column (2) of that Schedule.

(3) The power to impose restrictive covenants under paragraph (1) is exercisable only in respect of plots specified in column (1) of Schedule 5.

(4) Subject to Schedule 2A (counter-notice requiring purchase of land not in notice to treat) of the 1965 Act, as substituted by paragraph 5(8) of Schedule 6 (modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictive covenants), where the undertaker acquires a right over land or the benefit of a restrictive covenant affecting land under paragraph (1) or (2), the undertaker is not required to acquire a greater interest in that land.

(5) Schedule 6 has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restrictive covenant.

Commencement Information

I23Art. 23 in force at 18.6.2020, see art. 1

Private rights over landE+W

24.—(1) Subject to the provisions of this article, all private rights over land subject to compulsory acquisition under this Order are extinguished—

(a)as from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) M44 (powers of entry) of the 1965 Act,

whichever is the earlier.

(2) Subject to the provisions of this article, all private rights over land subject to the compulsory acquisition of the rights or the imposition of restrictive covenants under this Order are extinguished in so far as their continuance would be inconsistent with the exercise of the right or the burden of the restrictive covenant—

(a)as from the date of the acquisition of the right or the benefit of the restrictive covenant by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) (powers of entry) of the 1965 Act,

whichever is the earlier.

(3) Subject to the provisions of this article, all private rights over land owned by the undertaker that are within the Order limits are extinguished on commencement of any activity authorised by this Order which interferes with or breaches those rights.

(4) Subject to the provisions of this article, all private rights over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.

(5) Any person who suffers loss by the extinguishment or suspension of any private right under this article is entitled to compensation in accordance with the terms of section 152 (compensation in case where no right to claim compensation in nuisance) of the 2008 Act to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) This article does not apply in relation to any right to which section 138 M45 (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 31 (statutory undertakers) applies.

(7) Paragraphs (1) to (4) have effect subject to—

(a)any notice given by the undertaker before—

(i)the completion of the acquisition of the land or the acquisition of the rights over or the imposition of the restrictive covenant or affecting the land;

(ii)the undertaker's appropriation of it;

(iii)the undertaker's entry onto it; or

(iv)the undertaker's taking temporary possession of it,

that any or all of those paragraphs do not apply to any right specified in the notice; and

(b)any agreement made at any time between the undertaker and the person in or to whom the right in question is vested or belongs.

(8) If any such agreement as is referred to in paragraph (7)(b)—

(a)is made with a person in or to whom the right is vested or belongs; and

(b)is expressed to have effect also for the benefit of those deriving title from or under that person,

it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

(9) References in this article to private rights over land include any trust, incident, easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by virtue of a contract, agreement or undertaking having that effect.

Commencement Information

I24Art. 24 in force at 18.6.2020, see art. 1

Marginal Citations

M44Section 11(1) was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No. 1) and sections 186(1) and (2), 187 and 188 of the Housing and Planning Act 2016 (c. 22).

M45Section 138 was amended by section 23(1) and (4) of the Growth and Infrastructure Act 2013 (c.27) and S.I. 2017/1285.

Modification of Part 1 of the 1965 ActE+W

25.—(1) Part 1 of the 1965 Act, as applied to this Order by section 125 M46 (application of compulsory acquisition provisions) of the 2008 Act is modified as follows.

(2) In section 4A(1) M47 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008 , the five year period mentioned in article 22 (time limit for exercise of authority to acquire land compulsorily) of the A63 (Castle Street Improvement, Hull) Development Consent Order 2020 ”.

(3) In section 11A M48 (powers of entry: further notice of entry)—

(a)in subsection (1)(a), after “land” insert “ under that provision ”; and

(b)in subsection (2), after “land” insert “ under that provision ”.

(4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “ article 22 (time limit for exercise of authority to acquire land compulsorily) of the A63 (Castle Street Improvement, Hull) Development Consent Order 2020 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 27(3) (acquisition of subsoil or airspace only) of the A63 (Castle Street Improvement, Hull) Development Consent Order 2020, which excludes the acquisition of subsoil or airspace only from this Schedule; and

(b)after paragraph 29, insert—

PART 4 E+WINTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under article 18 (protective work to buildings), 29 (temporary use of land for carrying out the authorised development) or 30 (temporary use of land for maintaining the authorised development) of the A63 (Castle Street Improvement, Hull) Development Consent Order 2020..

Commencement Information

I25Art. 25 in force at 18.6.2020, see art. 1

Marginal Citations

M46Section 125 was amended by section 190 of, and paragraph 17 of Schedule 16 to, the Housing and Planning Act 2016 (c.22).

M47Section 4A(1) was inserted by section 202(1) of the Housing and Planning Act 2016.

M48Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016.

Application of the 1981 ActE+W

26.—(1) The 1981 Act applies as if this Order were a compulsory purchase order.

(2) The 1981 Act, as applied by paragraph (1), has effect with the following modifications.

(3) In section 1 (application of Act) for subsection 2 substitute—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order..

(4) In section 5 M49 (earliest date for execution of declaration), in subsection (2), omit the words from “, and this subsection” to the end.

(5) Omit section 5A M50 (time limit for general vesting declaration).

(6) In section 5B(1) M51 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A” substitute “ section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008 the five year period mentioned in article 22 (time limit for exercise of authority to acquire land compulsorily) of the A63 (Castle Street Improvement, Hull) Development Consent Order 2020 ”.

(7) In section 6 M52 (notices after execution of declaration) subsection (1)(b) for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “ section 134 M53 (notice of authorisation of compulsory acquisition) of the Planning Act 2018 ”.

(8) In section 7 M54 (constructive notice to treat) in subsection (1)(a), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(9) In Schedule A1 M55 (counter-notice requiring purchase of land not in general vesting declaration), omit paragraph 1(2).

(10) References to the 1965 Act in the 1981 Act are to be construed as references to the 1965 Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and as modified by article 25 (modification of Part 1 of the 1965 Act)) to the compulsory acquisition of land under this Order.

Commencement Information

I26Art. 26 in force at 18.6.2020, see art. 1

Marginal Citations

M49Section 5 was amended by Schedule 15 to the Housing and Planning Act 2016 (c. 22).

M50Section 5A was inserted by section 182(2) of the Housing and Planning Act 2016.

M51Section 5B was inserted by section 202(2) of the Housing and Planning Act 2016.

M52Section 6 was amended by section 4 of, and paragraph 52(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and paragraph 7 of Schedule 15 to the Housing and Planning Act 2016.

M53Section 134 was amended by section 142 of, and Part 21 of Schedule 25 to, the Localism Act 2011 (c. 20) and S.I. 2017/16.

M54Section 7(1) was substituted by paragraphs 1 and 3 of Schedule 18 to the Housing and Planning Act 2016.

M55Schedule A1 was inserted by paragraph 6 of Schedule 18 to the Housing and Planning Act 2016.

Acquisition of subsoil or airspace onlyE+W

27.—(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of or of the airspace over the land referred to in paragraph (1) of article 20 (compulsory acquisition of land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of, or rights in, the subsoil of or the airspace over land referred to in paragraph (1), the undertaker is not required to acquire an interest in any other part of the land.

(3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil or airspace only—

(a)Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act (as modified by article 25 (modification of Part 1 of the 1965 Act));

(b)Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and

(c)Section 153(4A) M56 (blighted land: proposed acquisition of part interest; material detriment test) of the 1990 Act.

(4) Paragraphs (2) and (3) are to be disregarded where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

Commencement Information

I27Art. 27 in force at 18.6.2020, see art. 1

Marginal Citations

M56Subsection (4A) of section 153 was inserted by section 200(1) and (2) of the Housing and Planning Act 2016.

Rights under or over streetsE+W

28.—(1) The undertaker may enter on and appropriate so much of the subsoil of, or airspace over, any street within the Order limits as may be required for the purposes of the authorised development and may use the subsoil or airspace for those purposes or any other purpose ancillary to the authorised development.

(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) does not apply in relation to—

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person's interest in the land, and who suffers loss as a result, will be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Commencement Information

I28Art. 28 in force at 18.6.2020, see art. 1

Temporary use of land for carrying out the authorised developmentE+W

29.—(1) The undertaker may, in connection with the carrying out of the authorised development, but subject to article 22(2) (time limit for exercise of authority to acquire land compulsorily)—

(a)enter on and take temporary possession of—

(i)the land specified in column (1) of Schedule 7 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (2) of that Schedule relating to the part of the authorised development specified in column (3) of that Schedule; and

(ii)any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;

(b)remove any buildings and vegetation from that land;

(c)construct temporary works (including the provision of means of access) and buildings on that land; and

(d)construct any works on that land as are mentioned in Schedule 1 (authorised development).

(2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land and explain the purpose for which entry is taken in respect of land specified under paragraph 1(a)(ii).

(3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (3) of Schedule 7, or

(b)in the case of any land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless the undertaker has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section (4) of the 1981 Act in relation to that land.

(4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—

(a)replace a building removed under this article;

(b)restore the land on which any permanent works have been constructed under paragraph (1)(d);

(c)remove any ground strengthening works which have been placed on the land to facilitate construction of the authorised development; or

(d)remove any measures installed over or around statutory undertakers' apparatus to protect that apparatus from the authorised development.

(5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(6) Any dispute as to a person's entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.

(7) Any dispute as to the satisfactory removal of temporary works and restoration of land under paragraph (4) does not prevent the undertaker giving up possession of the land.

(8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (5).

(9) The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i) except that the undertaker is not to be precluded from—

(a)acquiring new rights over any part of plots 3/1bf and 3/1bg under article 23 (compulsory acquisition of rights and restrictive covenants); or

(b)acquiring any part of the subsoil (or rights in the subsoil of or airspace over) that land under article 27 (acquisition of subsoil or airspace only).

(10) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(11) Section 13 M57 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act (application of compulsory acquisition provisions).

(12) The provisions of the Neighbourhood Planning Act 2017 M58 do not apply insofar as they relate to temporary possession of land under this article in relation to the construction of any work or the carrying out of any operation required for the purpose of, or in connection with, the construction of the authorised development.

Commencement Information

I29Art. 29 in force at 18.6.2020, see art. 1

Marginal Citations

M57Section 13 was amended by sections 62(3) and 139 of, and paragraphs 27 and 28 of Schedule 13, and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).

Temporary use of land for maintaining the authorised developmentE+W

30.—(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised development, the undertaker may—

(a)enter upon and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised development; and

(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land and explain the purpose for which entry is taken.

(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6).

(9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(10) Section 13 (refusal to give possession to the acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(11) In this article “the maintenance period”, in relation to any part of the authorised development means the period of 5 years beginning with the date on which that part of the authorised development is first opened for use.

(12) The provisions of the Neighbourhood Planning Act 2017 do not apply insofar as they relate to the temporary possession of land under this article in relation to the maintenance of any party of the authorised development within the maintenance period.

Commencement Information

I30Art. 30 in force at 18.6.2020, see art. 1

Statutory undertakersE+W

31.—(1) Subject to the provisions of Schedule 8 (protective provisions), article 23 (compulsory acquisition of rights and restrictive covenants) and paragraph (2), the undertaker may—

(a)acquire compulsorily, or acquire new rights or impose restrictive covenants over any Order land belonging to statutory undertakers; and

(b)extinguish the rights of, or remove or reposition the apparatus belonging to, statutory undertakers over or within the Order land.

(2) Paragraph (1)(b) has no effect in relation to apparatus in respect of which the following provisions apply—

(a)Part 3 (street works in England and Wales) of the 1991 Act; and

(b)article 32 of this Order (apparatus and rights of statutory undertakers in stopped up streets).

(3) Subject to paragraph (4), neither the undertaker nor any statutory undertaker may—

(a)carry out any part of the authorised development on; or

(b)for the purposes of carrying out, maintaining and operating any part of the authorised development enter upon, use or acquire any interest in,

the land to which this paragraph (3) applies pursuant to any Act or enactment, or any instrument or subordinate legislation made under any Act or enactment, other than this Order.

(4) Nothing in paragraph (3) applies to a statutory undertaker—

(a)carrying out any activity in relation to its apparatus existing on the date of this Order on the land to which paragraph (3) applies in the ordinary course of its statutory duties and which is necessary absent the proposals for the authorised development; or

(b)after the authorised development on the land to which paragraph (3) applies has been completed and opened for use for the purposes for which it was designed and any interest in the land required for the retention of that part of the authorised development has been acquired in accordance with that paragraph.

(5) The land to which paragraph (3)(b) applies comprises plots 3/1bd, 3/1bh, 3/1bi, 3/1bp, 3/1ca, 3/1cd, 3/1ce, 3/1cf, 3/1cg, 3/1ch, 3/1be, 3/1bf, 3/1bg, 3/1c, 3/1cb, 5/2a, 5/2i, 5/2f, 5/2g and 5/2j as set out in the book of reference and on the land plans.

(6) The land to which paragraph (3)(a) applies comprises the land to which paragraph (3)(b) applies and plots 3/1bv, 3/1by, 3/1cc and 3/2g as set out in the book of reference and on the land plans.

(7) In paragraphs (3) and (4) “statutory undertaker” includes the persons listed in article 8(4) (consent to transfer benefit of Order) and any utility undertaker or operator (which have the meanings given in Schedule 8 (protective provisions)).

Commencement Information

I31Art. 31 in force at 18.6.2020, see art. 1

Apparatus and rights of statutory undertakers in stopped up streetsE+W

32.—(1) Where a street is stopped up under article 13 (permanent stopping up and restriction of use of streets and private means of access), any statutory utility whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.

(2) Where a street is stopped up under article 13 any statutory utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested to do so by the undertaker must—

(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or

(b)provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).

(3) Subject to the following provisions of this article, the undertaker must pay to any statutory utility an amount equal to the cost reasonably incurred by the utility in or in connection with—

(a)the execution of the relocation works required in consequence of the stopping up of the street; and

(b)the doing of any other work or thing rendered necessary by the execution of the relocation works.

(4) If in the course of the execution of relocation works under paragraph (2)—

(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) is to be reduced by the amount of that excess.

(5) For the purposes of paragraph (4)—

(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.

(6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

(7) Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—

(a)the allowable costs of the relocation works are to be determined in accordance with section 85 (sharing of cost of necessary measures) of that Act and any regulations for the time being having effect under that section; and

(b)the allowable costs are to be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.

(8) In this article—

apparatus” has the same meaning as in Part 3 of the 1991 Act;

relocation works” means work executed, or apparatus provided, under paragraph (2); and

statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) (interpretation of Chapter 1) of the Communications Act 2003 M59.

Commencement Information

I32Art. 32 in force at 18.6.2020, see art. 1

Marginal Citations

M592003 c. 21. There are amendments to section 51 which are not relevant to this Order.

Recovery of costs of new connectionsE+W

33.—(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 31 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 31, any person who is—

(a)the owner or occupier of premises the drains of which communicated with that sewer; or

(b)the owner of a private sewer which communicated with that sewer,

is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) This article does not have effect in relation to apparatus to which article 32 (apparatus and rights of statutory undertakers in stopped up streets) or Part 3 of the 1991 Act applies.

(4) In this paragraph—

public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003; and

public utility undertaker” means a gas, water, electricity or sewerage undertaker.

Commencement Information

I33Art. 33 in force at 18.6.2020, see art. 1

Special category landE+W

34.—(1) On the exercise by the undertaker of the relevant Order powers, the special category land and any rights imposed over that land are not to vest in the undertaker until the undertaker has acquired the replacement land and the Secretary of State (in consultation with the relevant planning authority) has certified that a scheme for the provision of the replacement land as open space and a timetable for the implementation of the scheme has been received from the undertaker.

(2) On the requirements of paragraph (1) being satisfied, the special category land is to vest in the undertaker and be discharged from all rights, trusts and incidents to which it was previously subject.

(3) On the requirements of paragraph (1) being satisfied, the rights and the benefit of restrictive covenants to be acquired over the special category (rights) land are to vest in the undertaker and the special category (rights) land is to be discharged from all private rights to which it was previously subject in accordance with article 24 (private rights over land).

(4) On the date on which the replacement land is laid out and provided in accordance with the scheme requirements at paragraph (1), the replacement land is to vest in the person in whom the special category land was vested immediately before it was vested in the undertaker and is to be subject to the same rights, trusts and incidents as attached to the special category land.

(5) In this article—

the relevant Order powers” means the powers exercisable over the special category land by the undertaker under articles 20 (compulsory acquisition of land) and 23 (compulsory acquisition of rights and restrictive covenants);

the special category land” means the land numbered 3/1bd, 3/1be, 3/1zk, 3/1ag, 3/1zd, 3/1zg, 3/1zi and 3/1k in the book of reference and on the land plans and forming part of the open space which may be acquired compulsorily under this Order;

the special category (rights) land” means the land numbered 3/1af, 3/1zc, 3/1zf, and 3/1l in the book of reference and on the land plans and forming part of open space over which rights may be acquired and restrictive covenants imposed compulsorily under this Order;

the replacement land” means the land identified as such and numbered 3/1s, 3/1y, 3/1aa and 3/1za in the book of reference and on the land plans.

Commencement Information

I34Art. 34 in force at 18.6.2020, see art. 1

PART 6 E+WOPERATIONS

Felling or lopping of trees and removal of hedgerowsE+W

35.—(1) The undertaker may fell or lop any tree or shrub within or overhanging land within the Order limits, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b)from constituting a danger to persons using the authorised development.

(2) In carrying out any activity authorised by paragraph (1), the undertake—

(a)must do no unnecessary damage to any tree or shrub;

(b)must not fell or lop any tree or shrub within or overhanging land within the Order limits or cut back its roots if the tree or shrub is identified as being retained in the nvironmental statement unless the undertaker reasonably believes it to be necessary to do so for the purposes of the construction or operation of the authorised development and provided that the Secretary of State is satisfied that the felling, lopping or cutting back of roots would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement; and

(c)must pay compensation to any person for any loss or damage arising from such activity.

(3) The undertaker may, for the purposes of carrying out the authorised development but subject to paragraph (2), remove any hedgerow within the Order limits that is required to be removed.

(4) Any dispute as to a person's entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act.

(5) In this article “hedgerow” has the same meaning as in the Hedgerow Regulations 1997 M60 and includes important hedgerows for the purposes of those Regulations.

Commencement Information

I35Art. 35 in force at 18.6.2020, see art. 1

Marginal Citations

PART 7 E+WMISCELLANEOUS AND GENERAL

Removal of human remainsE+W

36.—(1) Before the undertaker carries out any development or works which are to or may disturb any human remains it is to remove those human remains, or cause them to be removed, in accordance with the following provisions of this article.

(2) Before any such remains are removed the undertaker is to give notice of the intended removal, describing the specified land and stating the general effect of the following provisions of this article, by—

(a)publishing a notice once in each of two successive weeks in a newspaper circulating in the area of the authorised development; and

(b)displaying a notice in a conspicuous place on or near to the land for a minimum of 28 days.

(3) As soon as reasonably practicable after the first publication of a notice under paragraph (2), the undertaker is to send a copy of the notice to Hull City Council.

(4) At any time within 56 days after the first publication of a notice under paragraph (2) any person who is a personal representative or relative of any deceased person whose remains are interred in the land specified in the notice may give notice in writing to the undertaker of that person's intention to undertake the removal of the remains.

(5) Where a person has given notice under paragraph (4), and the remains in question can be identified, that person may cause such remains to be—

(a)removed and re-interred in any burial ground or cemetery in which burials may legally take place; or

(b)removed to, and cremated in, any crematorium,

and that person is to, as soon as reasonably practicable after such re-interment or cremation, provide to the undertaker a certificate for the purpose of enabling compliance with paragraph (10).

(6) If the undertaker is not satisfied that any person giving notice under paragraph (4) is the personal representative or relative as that person claims to be, or that the remains in question can be identified, the question is to be determined on the application of either party in a summary manner by the county court, and the court may make an order specifying who is to remove the remains and as to the payment of the costs of the application.

(7) The undertaker is to pay the reasonable expenses of removing and re-interring or cremating the remains of any deceased person under powers conferred by this article.

(8) If—

(a)within the period of 56 days referred to in paragraph (4) no notice under that paragraph has been given to the undertaker in respect of any remains in the specified land; or

(b)such notice is given and no application is made under paragraph (6) within 56 days after the giving of the notice but the person who gave the notice fails to remove the remains within a further period of 56 days; or

(c)within 56 days after any order is made by the county court under paragraph (6) any person, other than the undertaker, specified in the order fails to remove the remains; or

(d)it is determined that the remains to which any such notice relates cannot be identified,

subject to paragraph (9) the undertaker is to remove the remains and cause them to be re-interred in Trinity Burial Ground or such burial ground or cemetery in which burials may legally take place as the undertaker thinks suitable for the purpose; and, so far as possible, remains from individual graves are to be re-interred in individual containers which are to be identifiable by a record prepared with reference to the original position of burial of the remains that they contain.

(9) If the undertaker is satisfied that any person giving notice under paragraph (4) is the personal representative or relative as that person claims to be and that the remains in question can be identified, but that person does not remove the remains, the undertaker is to comply with any reasonable request that person may make in relation to the removal and re-interment or cremation of the remains.

(10) On the re-interment or cremation of any remains under powers conferred by this article—

(a)a certificate of re-interment or cremation is to be sent by the undertaker to the Registrar General giving the date of re-interment or cremation and identifying the place from which the remains were removed and the place in which they were re-interred or cremated; and

(b)a copy of the certificate of re-interment or cremation and the record mentioned in paragraph (8) is to be sent by the undertaker to Hull City Council.

(11) The removal of the remains of any deceased person under powers conferred by this article is to be carried out in accordance with any directions which may be given by the Secretary of State.

(12) Any jurisdiction or function conferred on the county court by this article may be exercised by the district judge of the court.

(13) Section 25 (offence of removal of body from burial ground) of the Burial Act 1857 M61 does not apply to a removal carried out in accordance with this article.

(14) Section 3 (burial not to take place after Order in Council for discontinuance) of the Burial Act 1853 M62 does not apply to a removal carried out in accordance with this article.

Commencement Information

I36Art. 36 in force at 18.6.2020, see art. 1

Marginal Citations

M611857 c. 81. Section 25 was substituted by section 2 of the Church of England (Miscellaneous Provisions) 2014 (2014 No. 1) and amended by section 96(1) of and paragraph 1 in Schedule 3 to, the Ecclesiastical Jurisdiction and Care of Churches Measure 2018 (2018 No. 3).

Application of landlord and tenant lawE+W

37.—(1) This article applies to—

(a)any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and

(b)any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person's use.

(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.

(3) No such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—

(a)exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;

(b)confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or

(c)restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Commencement Information

I37Art. 37 in force at 18.6.2020, see art. 1

Operational land for purposes of the 1990 ActE+W

38.  Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3) (cases in which land is to be treated as operational land for the purposes of that Act) of the 1990 Act.

Commencement Information

I38Art. 38 in force at 18.6.2020, see art. 1

Defence to proceedings in respect of statutory nuisanceE+W

39.—(1) Where proceedings are brought under section 82(1) (summary proceedings by person aggrieved by statutory nuisance) of the Environmental Protection Act 1990 M63 in relation to a nuisance falling within paragraph (g) of section 79(1) (noise emitted from premises so as to be prejudicial to health or a nuisance) of that Act no order is to be made, and no fine may be imposed, under section 82(2) M64 of that Act if—

(a)the defendant shows that the nuisance—

(i)relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) of the Control of Pollution Act 1974 M65; or

(ii)is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or

(b)the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot reasonably be avoided.

(2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.

Commencement Information

I39Art. 39 in force at 18.6.2020, see art. 1

Marginal Citations

M631990 c. 43. There are amendments to section 82(1) which are not relevant to this Order.

M64Subsection (2) was amended by section 5(2) of the Noise and Statutory Nuisance Act 1993 (c. 40); there are other amendments to this subsection which are not relevant to this Order.

M651974 c. 40. Section 61(9) was amended by section 162 of, and paragraph 15 of Schedule 15 to, the Environmental Protection Act 1990 (c. 43). There are other amendments to section 61which are not relevant to this Order.

Protection of interestsE+W

40.  Schedule 8 (protective provisions) has effect.

Commencement Information

I40Art. 40 in force at 18.6.2020, see art. 1

Certification of documents, etc.E+W

41.—(1) As soon as practicable after the making of this Order, the undertaker must submit copies of each of the plans and documents set out in Schedule 9 (documents to be certified) to the Secretary of State for certification that they are true copies of those plans and documents.

(2) Where any plan or document set out in Schedule 9 requires to be amended to reflect the terms of the Secretary of State's decision to make the Order, that plan or document in the form amended to the Secretary of State's satisfaction is the version of the plan or document required to be certified under paragraph (1).

(3) A plan or document so certified will be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Commencement Information

I41Art. 41 in force at 18.6.2020, see art. 1

Service of noticesE+W

42.—(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a)by post;

(b)by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or

(c)with the consent of the recipient and subject to paragraphs (5) to (8) by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978 M66 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—

(a)in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and

(b)in any other case, the last known address of that person at the time of service.

(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—

(a)addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and

(b)either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement will be taken to be fulfilled only where—

(a)the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;

(b)the notice or document is capable of being accessed by the recipient;

(c)the notice or document is legible in all material respects; and

(d)in a form sufficiently permanent to be used for subsequent reference.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender will provide such a copy as soon as reasonably practicable.

(7) Any consent to the use of electronic communication given by a person may be revoked by that person in accordance with paragraph (8).

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a)that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and

(b)such revocation will be final and will take effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.

(9) This article will not be taken to exclude the employment of any method of service not expressly provided for by it.

(10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.

Commencement Information

I42Art. 42 in force at 18.6.2020, see art. 1

Marginal Citations

ArbitrationE+W

43.  Except where otherwise expressly provided for in this Order and unless otherwise agreed between the parties, any difference under any provision of this Order (other than a difference which falls to be determined by the tribunal) must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

Commencement Information

I43Art. 43 in force at 18.6.2020, see art. 1

Crown rightsE+W

44.—(1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and in particular, nothing in this Order authorises the undertaker or any licensee—

(a)to take, use, enter upon or in any manner interfere with any land or rights of any description—

(i)belonging to Her Majesty in right of the Crown and forming part of the Crown Estate without the consent in writing of the Crown Estate Commissioners;

(ii)belonging to Her Majesty in right of the Crown and not forming part of the Crown Estate without the consent in writing of the government department having the management of that land; or

(iii)belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department; or

(b)to exercise any right under this Order compulsorily to acquire an interest in any land which is Crown Land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown without the consent in writing of the appropriate Crown authority (as defined in the 2008 Act).

(2) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions, and is deemed to have been given in writing where it is sent electronically.

Commencement Information

I44Art. 44 in force at 18.6.2020, see art. 1

Signed by authority of the Secretary of State for Transport

David Milroy

A Senior Civil Servant,

Department for Transport Legal Advisers

Department for Transport

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources